1 Introduction to Operations Management Material Requirements Planning (MRP) CHAPTER 13.
-
date post
19-Dec-2015 -
Category
Documents
-
view
243 -
download
0
Transcript of 1 Introduction to Operations Management Material Requirements Planning (MRP) CHAPTER 13.
2Introduction to Operations Management
Material Requirements Planning
Master Production Schedule Time-phased plan specifying timing and quantity of production for each
end item. Material Requirement Planning Process
Product Structure
TreeLead
Times
3Introduction to Operations Management
Dependent vs Independent Demand
Time
Time Time
Time
Dem
and
Am
ount
on
hand
Am
ount
on
hand
Dem
and
Stable demand“Lumpy” demand
Safety stock
4Introduction to Operations Management
Objectives of MRP
MRP answers the following production decision of a firm– What is needed?– How much is needed?– When is it needed?
5Introduction to Operations Management
Material decision
Decision on– Quantity (how much)– Time (when)– Type (what)
The first two are same as in inventory management. The last one is needed because it involves more than one type of parts or components.
6Introduction to Operations Management
MRP OverviewMRP Inputs MRP Processing MRP Outputs
Masterschedule
Bill ofmaterials
file
Inventoryrecords
file
MRP computerprograms
Changes
Order releases
Planned-orderschedules
Exception reports
Planning reports
Performance-controlreports
Inventorytransaction
Primaryreports
Secondaryreports
7Introduction to Operations Management
Output from an MRP system
Generate a feasible schedule of requirements for– subassemblies– component parts– raw materials required
to produce the quantity of items required in the given time frame
8Introduction to Operations Management
Planning Horizon
1 2 3 4 5 6 7 8 9 10
Procurement
Fabrication
Subassembly
Assembly
9Introduction to Operations Management
Master Schedule
Master schedule: One of three primary inputs in MRP; states which end items are to be produced, when these are needed, and in what quantities.
Cumulative lead time: The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly.
Time fences: Series of time intervals during which order changes are allowed or restricted.
10Introduction to Operations Management
Bill-of-Materials
Bill of materials: One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product.
Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.
11Introduction to Operations Management
BOM
Accuracy is important since errors may multiply many times
12Introduction to Operations Management
Product Structure Tree
Chair
Seat
Legs (2)Cross
barSide
Rails (2)Cross
barBack
Supports (3)
LegAssembly
BackAssembly
Level 0
1
2
3
14Introduction to Operations Management
MRP Processing
Gross requirements Scheduled receipts(orders scheduled to arrive from suppliers at the
beginning of the period) Projected on hand Net requirements Planned-order receipts Planned-order releases
15Introduction to Operations Management
MRP Processing
Net Requirement in period t
=Gross Requirement in period t
Projected on hand inventory in period t
- +
( Safety stock
Allowance for waste+ )
16Introduction to Operations Management
Assembly Time Chart
1 2 3 4 5 6 7 8 9 10 11
Procurement ofraw material D
Procurement ofraw material F
Procurement ofpart C
Procurement ofpart H
Procurement ofraw material I
Fabricationof part G
Fabricationof part E
Subassembly A
Subassembly B
Final assemblyand inspection
17Introduction to Operations Management
MRP Outputs
Planned orders - schedule indicating the amount and timing of future orders.
Order releases - Authorization for the execution of planned orders.
Changes - revisions of due dates or order quantities, or cancellations of orders.
18Introduction to Operations Management
Example (p.632)
A firm that produces wood shutters and bookcases has received two orders for shutters: One for 100 to be due for delivery at the start of week 4 and the other 150 units to be due for delivery at the start of week 8 of the current schedule. Each shutter consists of four slatted wood sections and two frames. The wood sections are made by the firm, and fabrication takes one week. The frames are ordered, and lead time is two weeks. Assembly of the shutters requires one week. There is a scheduled receipt of 70 wood sections at the beginning of week 1. Determine the size and timing of planned-order releases necessary to meet delivery requirements under each of theses conditions:
(1). Lot-for-lot ordering (order size equal to net requirement) (2). Lot-size ordering with a lot size of 320 units for frames and 70 units
for wood sections.
19Introduction to Operations Management
Solution to exampleDevelop a master schedule and a product structure tree
Wk number 1 2 3 4 5 6 7 8
Quantity 100 150
Shutter
Frames (2) Wood sections (4)
20Introduction to Operations Management
Solution to example(lot-for-lot)
1 2 3 4 5 6 7
Grossrequirements
100
Scheduledreceipts
Projected onhandNet
requirements100
Planned-orderreceipts
100
Shutters:
LT isoneweek
Planned-orderreleases
100 150
21Introduction to Operations Management
Solution to example (lot-for-lot)times 2
1 2 3 4 5 6 7
Grossrequirements
200 300
Scheduledreceipts
Projected onhandNet
requirements200 300
Planned-orderreceipts
200 300
Frames:
LT istwoweeks
Planned-orderreleases
200 300
22Introduction to Operations Management
Solution to example (lot-for-lot)times 4
1 2 3 4 5 6 7
Grossrequirements
400 600
Scheduledreceipts
70
Projected onhand
70 70 70
Netrequirements
330 600
Planned-orderreceipts
330 600
Woodsections:
LT isoneweek
Planned-orderreleases
330 600
23Introduction to Operations Management
Solution to example (fixed lot-size)
times 2
1 2 3 4 5 6 7
Grossrequirements
200 300
Scheduledreceipts
Projected onhand
120 120 120 120
Netrequirements
200 180
Planned-orderreceipts
320 320
Frames:
LT istwoweeks
Planned-orderreleases
320 320
24Introduction to Operations Management
Solution to example (fixed lot-size)
times 4
1 2 3 4 5 6 7
Grossrequirements
400 600
Scheduledreceipts
70
Projected onhand
70 70 70 20 20 20 20
Netrequirements
330 580
Planned-orderreceipts
350 630
Woodsections:
LT isoneweek
Planned-orderreleases
350 630
25Introduction to Operations Management
MRP Secondary Reports
Performance-control reports Planning reports Exception reports
26Introduction to Operations Management
Other Considerations
Safety Stock Lot sizing
– Lot-for-lot ordering
– Economic order quantity
– Fixed-period ordering
– Part-period model Yield rates
27Introduction to Operations Management
MRP Capacity requirement Planning
Capacity requirements planning: The process of determining short-range capacity requirements.
Load reports: Department or work center reports that compare known and expected future capacity requirements with projected capacity availability.
28Introduction to Operations Management
MRP Capacity Requirement PlanningDevelop a tentativemaster production
schedule
Develop a tentativemaster production
schedule
Use MRP tosimulate material
requirements
Use MRP tosimulate material
requirements
Convert materialrequirements to
resource requirements
Firm up a portionof the MPS
Is shopcapacity
adequate?
Cancapacity be
changed to meetrequirements
Revise tentativemaster production
schedule
Changecapacity
Yes
No
Yes
No
29Introduction to Operations Management
Benefits of MRP
Low levels of in-process inventories Ability to track material requirements Ability to evaluate capacity requirements Means of allocating production time
30Introduction to Operations Management
Requirements of MRP
Computer and necessary software Accurate and up-to-date
– Master schedules– Bills of materials– Inventory records
Integrity of data
31Introduction to Operations Management
MRP II
Expanded MRP with and emphasis placed on integration– Financial planning– Marketing– Engineering– Purchasing– Manufacturing