    Pemex Short CourseOffshore Drilling

    Lesson 1

    Introduction

  • 8/9/2019 1. Introduction (626)

    2/67

    2

    Lesson 1 - Introduction

    Floating Drilling Outline

    Floating Drilling Vessels

    Types of Motion

    Types of Waves

    When is Drilling Possible (WOW)

    Vessel Capacities

    Movement of Liquids

  • 8/9/2019 1. Introduction (626)

    3/67

    3

    Instructor: Jerome J. Schubert

    Phone: 979/862-1195E-mail: [email protected]

    Introduction - contd

  • 8/9/2019 1. Introduction (626)

    4/67

    4

    Drilling Lessons:

    Can be found on the web at:

    http://pumpjack.tamu.edu/~schubert/

    Introduction - contd

  • 8/9/2019 1. Introduction (626)

    5/67

    5

    1. Floating Drilling: Equipment and its Use,

    Practical Drilling Technology, Vol.2, by Riley

    Sheffield, Gulf Publishing Company, Houston,

    TX, 1980.

    2. Applied Drilling Engineering, by Adam T.

    Bourgoyne Jr., Martin E. Chenevert. Keith K.

    Millheim and F.S. Young. SPE Textbook Series,Vol. 2, Society of Petroleum Engineers,

    Richardson, TX, 1991.

    References

  • 8/9/2019 1. Introduction (626)

    6/67

    6

    1. IADC Deepwater Well Control Guidelines,

    Published by the International Association of

    Drilling Contractors, Houston, TX, 1998.281-578-7171

    2. Design for Reliability in Deepwater

    Drilling Operations, by L. M. Harris.ThePetroleum Publishing Company, Tulsa, OK,

    1979.

    References

  • 8/9/2019 1. Introduction (626)

    7/67

    7

    3. An Introduction to Marine Drilling, by

    Malcolm Maclachlan. Daytons Oilfield

    Publications Limited, P. O. Box 11, Ledbury,Herefordshire HR8 1BN, England, 1987.

    4. Drilling Engineering, A complete Well

    Planning Approach, by Neal Adams andTommie Carrier. PennWell Publishing

    Company, Tulsa, OK, 1985.

    References - contd

  • 8/9/2019 1. Introduction (626)

    8/67

    8

    5. Practical Well Planning and Drilling

    Manual, by Steve Devereux. PennWell

    Publishing Company, Tulsa, OK, 1998.

    6. Oilwell Drilling Engineering, Principles

    and Practice, by H. Rabia. Graham &Trotman. Printed byThe Alden Press,

    Oxford, UK, 1985.

    References - contd

  • 8/9/2019 1. Introduction (626)

    9/67

    9

    Schedule

    Introduction to Class,

    Deepwater Platforms

    Floating Vessels,

    Types of Motion, Station Keeping

    Wellheads and BOPs in Floating DrillingDrilling Risers, High Pressure Riser

    Motion Compensation

  • 8/9/2019 1. Introduction (626)

    10/67

    10

    Schedule Pore Pressure and Prediction

    Fracture Gradients

    LWD and Formation Test

    Special Problems in Floating Drilling

    Shallow water Flows; Hydrates

    Dual Gradient Drilling

  • 8/9/2019 1. Introduction (626)

    11/67

    11

    Schedule

    Special Applications

    Well Control

  • 8/9/2019 1. Introduction (626)

    12/67

    12

    Drilling Rigs

    Drilling Systems

    Drilling Rigs

  • 8/9/2019 1. Introduction (626)

    13/67

    13

    Drilling Team

    Drilling Rigs

    Rig Power System

    Hoisting System

    Circulating System ...

    Rotary Drilling

  • 8/9/2019 1. Introduction (626)

    14/67

    14

    The Rotary System

    The Well Control System

    Well-Monitoring System

    Special Marine Equipment

    Drilling Cost Analysis

    Examples

    Rotary Drilling - contd

  • 8/9/2019 1. Introduction (626)

    15/67

    15

    NobleDrillings

    Cecil

    Forbes

    A Jack-Up

    Rig

  • 8/9/2019 1. Introduction (626)

    16/67

    16

    Sonats

    George

    Washington

    A Semi-

    Submersible

    Rig

  • 8/9/2019 1. Introduction (626)

    17/67

    17

    Zapatas

    Trader

    A Drillship

  • 8/9/2019 1. Introduction (626)

    18/67

    18

  • 8/9/2019 1. Introduction (626)

    19/67

    19

    TENSION LEG PLATFORM

  • 8/9/2019 1. Introduction (626)

    20/67

    20

    Shells

    Bullwinkle

    Worlds tallest

    offshore structure

    1,353 water

    depth

    Productionbegan in 198945,000 b/d

    80MM scf/d

  • 8/9/2019 1. Introduction (626)

    21/67

    21

    Fig. 1.5

    Classification of

    rotary drilling rigs

  • 8/9/2019 1. Introduction (626)

    22/67

    22

    Drilling Operations

    Field Engineers, Drilling ForemenA. Well planning prior to SPUD

    B. Monitor drilling operations

    C. After drilling, review drilling results andrecommend future improvements

    - prepare report.

    D. General duties.

    What are the well requirements?

    Objectives, safety, cost

  • 8/9/2019 1. Introduction (626)

    23/67

    23

    Criteria for determining

    depth limitation

    Derrick

    Drawworks

    Mud Pumps

    Drillstring

    Mud System

    Blowout Preventer

    Power Plant

  • 8/9/2019 1. Introduction (626)

    24/67

    24

    A Rotary RigHoisting System

  • 8/9/2019 1. Introduction (626)

    25/67

    25

    Projection ofDrilling Lines

    on Rig Floor

    TOTAL

    E = efficiency = Ph/Pi = W/(n Ff) or Ff= W/(nE) (1.7)

  • 8/9/2019 1. Introduction (626)

    26/67

    26

    Load on Derrick

    (considering friction in sheaves)

    Derrick Load = Hook Load

    + Fast Line Load+ Dead Line Load

    Fd = W+ Ff+ Fs

    F WW

    E n

    W

    n

    E E n

    E nW

    d ! = 1

    E = overall efficiency: E = en

    e.g., if individual sheave efficiency = 0.98 and n = 8, then E = 0.851

  • 8/9/2019 1. Introduction (626)

    27/67

    27

    Example 1.2A rig must hoist a load of300,000 lbf.The

    drawworks can provide an input power to the

    block and tackle system as high as 500 hp.Eight lines are strung between the crown block

    and traveling block. Calculate

    1.The static tension in the fast line

    when upward motion is impending,

    2. the maximum hook horsepower

    available,

  • 8/9/2019 1. Introduction (626)

    28/67

    28

    Example 1.2, cont.3. the maximum hoisting speed,

    4. the actual derrick load,

    5. the maximum equivalent derrick

    load, and,

    6. the derrick efficiency factor.

    Assume that the rig floor is arranged as

    shown in Fig. 1.17.

  • 8/9/2019 1. Introduction (626)

    29/67

    29

    Solution1. The power efficiency forn = 8 is

    given as 0.841 in Table 1.2.The tension

    in the fast line is given by Eq. 1.7.

    lbnE

    W

    F 590,448*841.0

    000,300

    !!!

    ( alternatively, E = 0.988 = 0.851 )

  • 8/9/2019 1. Introduction (626)

    30/67

    30

    Solution2. The maximum hook horsepower

    available is

    Ph= Eypi = 0.841(500) = 420.5 hp.

    yyy

  • 8/9/2019 1. Introduction (626)

    31/67

    31

    Solution3. The maximum hoisting speed is given by

    v P

    Wb

    h!

    !

    hpft-lbf/ mi

    hp300,000 lbf

    46.3 ft / mi

    420 533 000

    .,

  • 8/9/2019 1. Introduction (626)

    32/67

    32

    Solution to 3., cont.To pull a 90-ft stand would require

    t ! !90

    1 9ft

    46 .3 ft / m in. m in .

  • 8/9/2019 1. Introduction (626)

    33/67

    33

    Solution4.The actual derrick load is given by

    Eq.1.8b:

    F E En

    EnW

    d!

    1

    = 1 + 0.841 + 0.841(8)0.841(8)

    (300,000)

    = 382,090 l f.

  • 8/9/2019 1. Introduction (626)

    34/67

    34

    Solution5.The maximum equivalent load is given

    by Eq.1.9:

    lbf

    Wn

    n

    de

    de

    000,450

    000,300*8

    484

    !

    !

    !

  • 8/9/2019 1. Introduction (626)

    35/67

    35

    Solution6.The derrick efficiency factor is:

    ,4

    ,3

    de

    dd !!

    84.9%r849.0E !

  • 8/9/2019 1. Introduction (626)

    36/67

    36

    Drillshi

    - moored

  • 8/9/2019 1. Introduction (626)

    37/67

    37

  • 8/9/2019 1. Introduction (626)

    38/67

    38

    Heave

    SurgeSway

    Roll

    PitchYaw

  • 8/9/2019 1. Introduction (626)

    39/67

    39

    Motions restricted to the horizontal planeSURGE: Translation fore and aft (X-axis)

    SWAY: Translation port and starboard (Y-axis)

    YAW: Rotation about the Z-axis (rotation aboutthe moonpool)

    Motions that operate in vertical planesHEAVE: Translation up and down (Z-axis)ROLL: Rotation about the X-axis

    PITCH: Rotation about the Y-axis

    Vessel Motions

  • 8/9/2019 1. Introduction (626)

    40/67

    40

  • 8/9/2019 1. Introduction (626)

    41/67

    41

    Wave Direction

    Beam Waves

    Quartering Waves

    Head

    Waves

  • 8/9/2019 1. Introduction (626)

    42/67

    42

  • 8/9/2019 1. Introduction (626)

    43/67

    43

  • 8/9/2019 1. Introduction (626)

    44/67

    44

    Significant Wave Height, ft

    Roll vs. Significant Wave Height

  • 8/9/2019 1. Introduction (626)

    45/67

    45

    Significant wave height is the average height

    of the 1/3 highest waves in a sample.

    EXAMPLE The significant wave height in thefollowing sample is 24 ft.

    7, 21, 19, 11, 18, 26, 13, 17, 25

    [ Sign. WH = (21 + 26 + 25) / 3 = 24 ft ]

    Avg. WH = (7, 21, 19, 11, 18, 26, 13, 17, 25) / 3 = 17.4 ft

    What is Significant Wave Height?

  • 8/9/2019 1. Introduction (626)

    46/67

    46

    Significant Wave Height, ft

    Heave vs. Significant Wave Height

  • 8/9/2019 1. Introduction (626)

    47/67

    47

    Heave vs. Wave Approach Angle

    BOW BEAM

  • 8/9/2019 1. Introduction (626)

    48/67

    48

    Roll & Pitch vs. Wave Approach Angle

    BOW BEAM

  • 8/9/2019 1. Introduction (626)

    49/67

    49

    Typical Vessel Motion Limits - Criteria

    Operation Wave Height Heave

    ft ft

    Drilling Ahead 30 10

    Running and

    Setting Casing 22 6

    Landing BOP and Riser 15 3Transferring Equipment 15 -

  • 8/9/2019 1. Introduction (626)

    50/67

    50

  • 8/9/2019 1. Introduction (626)

    51/67

  • 8/9/2019 1. Introduction (626)

    52/67

    52

  • 8/9/2019 1. Introduction (626)

    53/67

    53

  • 8/9/2019 1. Introduction (626)

    54/67

    54

    What is lt ?

  • 8/9/2019 1. Introduction (626)

    55/67

    55

    Some Definitions

    Freeboard

    Draft

    Width

  • 8/9/2019 1. Introduction (626)

    56/67

    56

  • 8/9/2019 1. Introduction (626)

    57/67

    57

    G = center of gravity. B = center of buoyancy

    G is

    above B!

  • 8/9/2019 1. Introduction (626)

    58/67

    58

    U

    NOTE:

    B has moved!

    GZ =righting

    arm

  • 8/9/2019 1. Introduction (626)

    59/67

    59

  • 8/9/2019 1. Introduction (626)

    60/67

    60

    Dynamic Stability - for certification

  • 8/9/2019 1. Introduction (626)

    61/67

    61

    Dynamic Stability

    For adequate stability, the area under the

    righting moment curve to the second

    intercept or to the down-flooding angle,

    whichever is less, must be a given amountin excess of the area under the wind

    heeling moment curve to the same limiting

    angle. The excess of this area must be atleast 40% for shiplike vessels and 30% for

    column-stabilized units (see Fig. above).

  • 8/9/2019 1. Introduction (626)

    62/67

    62

    Free Surface Effects

    CG moves!

  • 8/9/2019 1. Introduction (626)

    63/67

    63

    Tall, narrow tank is more stable ...

  • 8/9/2019 1. Introduction (626)

    64/67

    64

    Effect of Fluid Level in Tank

  • 8/9/2019 1. Introduction (626)

    65/67

    65

  • 8/9/2019 1. Introduction (626)

    66/67

    66

    Effect of Partitions in Tank

  • 8/9/2019 1. Introduction (626)

    67/67

    67

    The Vessel - Classification

    Three classification societies are particularly

    important to offshore drilling. These societies are: