1 FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa.

15
1 FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa
  • date post

    21-Dec-2015
  • Category

    Documents

  • view

    214
  • download

    0

Transcript of 1 FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa.

1

FEE Installation & Commissioning TPC Meeting, 21 April 2006

L. Musa

2

Installation of FECs and Backplanes Jan ’05 - Mar ’06

electrical and functional test of each FEC

test of the connection between FECs and pad plane

test of the connection between FECs and readout backplane

PHASE I

Installation of RCUs May – Aug ’06 Comprehensive test of all (216) readout partitions: FEE, DAQ, DCS,

TRIGGER, HLT, ECS (power bars and cooling required)

PHASE III

Characterization of the whole system with RCUs Mar – May ’06

Characterization of 1 readout partition at a time: noise, gain, width, baseline, time

offset, temperature, voltages and currents

PHASE II

Electronics Installation and Commissioning Schedule

3

FE Cards Installation 1/2

Organization and schedule

• 2 installation crews (3 people / crew)

• Installation started on the 30th January

• Installation rate: ~ 1 sector / day

Status• Installation of FECs completed (on March 15), with exception of 1 sector on C

side

• Installation of Readout &Control backplanes completed by end of March, with exception of 1 sector on C side

• The electronics of 1 sector (A09), equipped with the LV bus rods and cooling, was characterized (pedestals, noise, gain)

• The electronics of sector A08 is under test

4

Measurement of VCCA, VCCD, IA, ID and T

Measurement of the FEC Identifier

FE Cards Installation 2/2

During the installation, the FECs are tested individually (stand-alone) by means of a dedicated “mounting test tool”, U2F (USB to FEC interface)

U2F Card

Readout of trigger related data (pulser)

Connection to the pad plane

5

FE Cards Installation highlights

6

TPC A Side(17th February ’06)

7

Characterization of Sector A09

Sector A09 equipped with • backplanes • cooling circuit• LV power rods• LV PS + cables (4 x 40m)

Sector A09 equipped with • backplanes • cooling circuit• LV power rods• LV PS + cables (4 x 40m)

8

sum of charges sum of charges, pad row 46

baseline noise rms (ADC counts)

Characterization of Sector A09 - IROC

9

sum of samples

baseline rms

Characterization of Sector A09 - IROC

baseline

(PASAnoise2 + ADCnoise

2) = 0.70 ADC counts

10

sum of charges sum of charges, pad row 11

Characterization of Sector A09 - OROC

baseline noise rms (ADC counts)

11

sum of samples

Characterization of Sector A09 - OROC

baseline rmsbaseline rms

sum of samples

12

Power Regulators

RCU status and plans …

Readout Control Unit 1/2

DCS CARD

SIU CARD

13

Readout Control Unit 2/2

Mass Production (240 units including 10% spares) completed November ‘05

Mass Test completed December ’05

Delivery of tested DCS cards Mar ‘06

Delivery of tested SIU cards (DAQ project): 1st lot (108 units) Mar ’06 2nd lot (108 units) May ‘06

Assembly and final test of RCU + SIU + DCS: Apr – Jun ‘06

Installation and commissioning of RCUs: May – Aug ‘06

Production, test, installation and commissioning

14

Preparing for Commissioning Phase III

RCU Lab - setup I Final assembly and test of RCU + SIU + DCS

25 FECs (readout partition) + Backplane + RCU

1 DAQ PC (PCALD23) + single-channel RORC

1 DCS PC (local network DHCP server, DIM Server) + Ethernet Switch

Local Trigger Crate (SBC, LTU, TTvi, TTCex) + TTCoc

RCU Lab - setup II TPC FEE + DAQ + HLT Integration 2 x Readout Partitions

1 DAQ PC (EPAITBEAM02) + dual-channel RORC

1 HLT PC + 1 HRORC

P2 SXL2 – Test of the electronics, 1 Sector at a time

1 x Readout Partition

1 DAQ PC (ALDAQPC021) + dual-channel RORC

15

Conclusions

Installation of FECs almost complete (97% done)

The complete electronic chain of one TPC sector has been characterized

gain, baseline and noise distributions well within specifications

Installation of backplanes was completed by Mar ’06

Installation and commissioning of RCUs in May - Aug ‘06