1 CTF3 collaboration meeting 2007 G.Geschonke Status
Status of CTF3
G.GeschonkeCERN
2 CTF3 collaboration meeting 2007 G.Geschonke Status
DL
CLEX 2007-2009building in 2006
2004 2005
CTF3 Programme
2006
Thermionic gun
CR
TL2 2007
30 GHz production(PETS line)and test stand
Photo injector / lasertests from 2006
D FFD
D F D
D F D D F D
D F D
DF DF DF DF DF DF DF DF DF
D F D
F DF D
D FFFDD
D F DD F D
D F DD F D D F DD F D
D F DD F D
DF DF DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
D F DD F D
F DF DF DF D
Linac
3 CTF3 collaboration meeting 2007 G.Geschonke Status
Next steps: 2006 (shown at last collaboration meeting)
• Fully commission Delay Loop - done
• Separate Linac from rest of machine -done
• 30 GHz power testing -done
• Construction of CLEX building - started
• Install and commission Combiner Ring - ongoing
Combiner Ring and TL1:Optics: INFN Magnets: BINP/CERN/Lure/CIEMAT/
INFN Power supplies: CERN RF deflectors: INFN Septa: CIEMAT MoU not signed yetKicker: CIEMAT/CERN pulser: CIEMAT/CERN 3 GHz source: CERN Controls: CERN BPM electronics: LAPP / CERN Vacuum chamber + BPM: INFN
MoU not signed yet
If the expected contributions will be provided, the Combiner Ring will be built to schedule
4 CTF3 collaboration meeting 2007 G.Geschonke Status
DL
CLEX 2007-2009building in 2006
2004 2005
CTF3 status
2006
Thermionic gun
CR
TL2 200730 GHz production(PETS line)and test stand
Photo injector / lasertests from 2006
On schedule so far
D FFD
D F D
D F D D F D
D F D
DF DF DF DF DF DF DF DF DF
D F D
F DF D
D FFFDD
D F DD F D
D F DD F D D F DD F D
D F DD F D
DF DF DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
D F DD F D
F DF DF DF D
Linac
Combiner Ring installation ongoing, commissioning start in April 2007
Beam up to here
Laser at CERNRF gun under construction
TL1 commissioned
5 CTF3 collaboration meeting 2007 G.Geschonke Status
CTF3 in 2006
D FFD
DF
F
D F D
D F D D F D
D F D
DF DF DF DF DF DF DF DF DF
D F D
F DF D
D FFFDD
DF
FDD
FF
FF
D F DD F D
D F DD F D D F DD F D
D F DD F D
DF DF DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
D F DD F D
F DF DF DF D
Linac
Delay Loop
Transfer Line TL2and Combiner Ring
30 GHz RF power testing
Beamup to here
6 CTF3 collaboration meeting 2007 G.Geschonke Status
RF power plant
10 s-band klystrons 3 GHz35 – 45 MW, 5.5 s
9 with pulse compressors:factor 1.9 – 2 (1.6 s)
3 L-band travelling wave tubes40 kW, 3 s1.5 GHz BW >200 MHz
1 L-band klystron22 MW, 5.5s
RF Pulse compression
LIPS BOC
first 5 klystrons: ~ 5000 hours operation in 20062 klystrons replaced3 thyratrons replacedphase and amplitude stability under investigation
7 CTF3 collaboration meeting 2007 G.Geschonke Status
CTF3 main activities in 2006
a) Commission Delay Loop + 1.5 GHz bunching system, beam dynamics studies
Three 40 kW travelling wave tubesat 1.5 GHz installed
travelling wave wide-band buncherfor fast phase coding at 1.5 GHz
fast phase switch,5-pulse recombination
1.4 us train length, 3.5 A peak current 1.4 us train length, 3.5 A peak current
8 CTF3 collaboration meeting 2007 G.Geschonke Status
CTF3 main activities in 2006
b) Operation for 30 GHz CLIC component testing
100 MW produced at 30 GHz, operation for 30 GHz now routine,largely automatic, supervision from CCC
D FFD
DF
F
D F D
D F D D F D
D F D
DF DF DF DF DF DF DF DF DF
D F D
F DF D
D FFFDD
DF
FDD
FF
FF
D F DD F D
D F DD F D D F DD F D
D F DD F D
DF DF DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
D F DD F D
F DF DF DF D
CTF3 linac
PETs branch
High-gradient test stand, CTF2
High-power transf er line
Two-beam 30 GHz power production in CTF3
CTF3 linac
PETs branch
High-gradient test stand, CTF2
High-power transf er line
Two-beam 30 GHz power production in CTF3
Separation walldecouples operation of linac for 30 GHz testing from installation
9 CTF3 collaboration meeting 2007 G.Geschonke Status
CTF3 main activities in 2006
c) Installation of : Combiner Ring and Transfer Line TL1
TL1 installed, commissioned with beam,Combiner Ring injection region commissioned,
Combiner Ring installation:all magnets, septa, kicker installed,vacuum chambers and beam diagnostics will be installed before March 2007
10 CTF3 collaboration meeting 2007 G.Geschonke Status
Improvements
Big effort to improve operational reliability
water temperature stability for RF pulse compression:new system gives stability within ± 0.02 degrees !
automatic system for 3 GHz conditioning, as well as 30 GHz operation for CLIC structure copnditioning/testing
supervision from CCC now possible
Beam dynamics studies:Emittance measurements,better understanding of the machine: model fits machine
11 CTF3 collaboration meeting 2007 G.Geschonke Status
Jan Feb Mar
Wk 1 2 3 4 5 6 7 8 9 10 11 12 13
Mo 2 9 16 23 30 6 13 20 27 6 13 20 27
Tu
We
Th
Fr
Sa
Su
Apr May Jun
Wk 14 15 16 17 18 19 20 21 22 23 24 25 26
Mo 3 10 17 24 1 8 15 22 29 5 12 19 26
Tu
We
Th
Fr
Sa
Su
Jul Aug Sep
Wk 27 28 29 30 31 32 33 34 35 36 37 38 39
Mo 3 10 17 24 31 7 14 21 28 4 11 18 25
Tu
We
Th
Fr
Sa
Su
Oct Nov Dec
Wk 40 41 42 43 44 45 46 47 48 49 50 51 52
Mo 2 9 16 23 30 6 13 20 27 4 11 18 25
Tu
We
Th
Fr
Sa
Su
CTF3 SHUTDOWNSee planning EDMS
2006 - CTF 3 - Schedule
CTF3 under access control for HV and
RFconditionning
Shut downCTF3
with beamCTF3 closed with keys for Hardware tests
CTF3
SHUTDOWN
CTF3 CR installationBeam in PETS
9 November 2006
Tests BDI
CCC ready
G. Frid
East May
Ascen
Whit.
Jeune G.
CTF3 stop with beam
Beam in TL1
Start conditioning and setting-upTests CO + PO
D.L.(+ PETS)
Installation C.R.
Beam in PETS only
Beam in PETS only
Tests POTests BDI during the night
D.L.
Installation CTS + TL1 + CR + CRM
Linac Conf.
EPAC
Start MKS in diode
POSIPOL
Start CLEXCivil Engineering
Machine open
CTF2 openwater stations tests in Linac
Installation CTS/TL1/CR
CTF3 under access control
Beam in PETS
Tests BI Tests PO
and polarities
1. period:DL commissioning, Beam dynamics studies
operation for 30 GHz at nights and weekends
2. period:operation for 30 GHz power production only,installation of TL1 and CR
3. period:Commissioning TL1 and CR injection,
operation for 30 GHz at nights and weekends
Operation nearly all year !
12 CTF3 collaboration meeting 2007 G.Geschonke Status
CLEX building
Construction on scheduleEquipment installation from May 2007,Beam foreseen from March 2008
June 2006
31.8.2006
25.10.2006
existing building
D FFD
DF
F
D F D
D F D D F D
D F D
DF DF DF DF DF DF DF DF DF
D F D
F DF D
D FFFDD
DF
FDD
FF
FF
D F DD F D
D F DD F D D F DD F D
D F DD F D
DF DF DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
D F DD F D
F DF DF DF D
42.5 m
8 m
2m
D FFD
DF
F
D F DDUMPD F D
F
FD
ITB
1.85m
CALIFES Probe beam injector
LIL-ACSLIL-ACSLIL-ACSD F D
D F D
DFDUMP
0.75
1.4m
1
DUMP
22.4 mTBL
2.5m
Transport path
DUMP
DUMP 22 m
2.0m
DF DF DF DF DF DF DF DF
3.0m3.0m6 m
D F D
F DF D
16.5 mTBTS
16 m
TL2’
42.5 m42.5 m
8 m8 m
2m2m
D FFFDD
DF
FDD
FF
FF
D F DD F DDUMPD F DD F D
F
FD
F
FD
F
FD
ITB
1.85m1.85m
CALIFES Probe beam injector
LIL-ACSLIL-ACSLIL-ACSLIL-ACSLIL-ACSLIL-ACSD F DD F D
D F DD F D
DF DFDUMP
0.75
1.4m1.4m
11
DUMP
22.4 m22.4 mTBL
2.5m2.5m
Transport path
DUMP
DUMP 22 m22 m
2.0m2.0m
DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
3.0m3.0m3.0m3.0m6 m6 m
D F DD F D
F DF DF DF D
16.5 m16.5 mTBTS
16 m16 m
TL2’
Test Beam Line TBL
Jan 2007
13 CTF3 collaboration meeting 2007 G.Geschonke Status
Collaborating institutes
Countries Funding Agencies LaboratoryCERN CERN
FINLAND Helsinki Inst of Phys (HIP)CEA DAPNIA Saclay
LALLAPPLURE
INDIA* Indian DAE RRCAT, IndoreITALY INFN LNF
Budker Inst (BINP)IAP
Dubna JINRCIEMAT
UPCIFIC
Uppsala UniversityTSL
SWITZERLAND Paul Scherrer Inst (PSI)TURKEY Ankara Univ Group (2)
Northwestern Univ Illinois (NWU)SLAC
CNRS/IN2P3FRANCE
RUSSIA
SPAINMinistry of Education &
Science (MEC)
SWEDENSwedish Research Council
Wallenberg Foundation
USA DOE
* India has not signed the CTF3 MoU, but has an agreement with CERN for the development of novel accelerator technologies
new member
Discussions with : Pakistan, Iran, UK (Cockcroft Institute, J.Adams Institute), JLAB, EPFL, INFN Milan
16 membersinvolving 21 Institutes
Collaboration with RAL within PHIN
14 CTF3 collaboration meeting 2007 G.Geschonke Status
Ongoing work (2006 and later)
D FFD
DF
F
D F D
D F D D F D
D F D
DF DF DF DF DF DF DF DF DF
D F D
F DF D
D FFFDD
DF
FDD
FF
FF
D F DD F D
D F DD F D D F DD F D
D F DD F D
DF DF DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
D F DD F D
F DF DF DF D
INFN vac chambers, BPI, installation, optics, operationCIEMAT correctors,BINP quadrupolesLURE quadrupolesCERN magnets, BPM, infrastructure, installationNWU RF bunch length monitorLAPP BPI/BPM electronics
INFN vac chambers, BPI, wiggler, installation, optics, RF deflectorsCIEMAT correctors, septa, kicker + pulserBINP quadrupoles, sextupolesLURE quadrupolesCERN Infrastructure, RF power, installation, magnets, Beam diagnostics, vacuumUppsala Bunch phase monitorLAPP BPI/BPM electronics
RRCAT optics, 5 bending magnets, Al vacuum chambersTSL magnetsCERN Infrastructure, vacuum , magnets, installation
WP 7WP 7 WP 9WP 9
Structures 30 GHz power sourceCTF3 Operation
WP 8
HIP HelsinkiCERNCIEMATSLAC structure testing
Ankara Universities,INFN,JINR Dubna automatic conditioningRRCAT softwareCERN
IAP
Project is covered including TL2.
PSI additional modulator
NWU: Beam loss monitoring
15 CTF3 collaboration meeting 2007 G.Geschonke Status
Ongoing work in CLEX (2006 and later)
42.5 m
8 m
2m
D FFD
DF
F
D F DDUMPD F D
F
FD
ITB
1.85m
CALIFES Probe beam injector
LIL-ACSLIL-ACSLIL-ACSD F D
D F D
DFDUMP
0.75
1.4m
1
DUMP
22.4 mTBL
2.5m
Transport path
DUMP
DUMP 22 m
2.0m
DF DF DF DF DF DF DF DF
3.0m3.0m6 m
D F D
F DF D
16.5 mTBTS
16 m
TL2’
42.5 m42.5 m
8 m8 m
2m2m
D FFFDD
DF
FDD
FF
FF
D F DD F DDUMPD F DD F D
F
FD
F
FD
F
FD
ITB
1.85m1.85m
CALIFES Probe beam injector
LIL-ACSLIL-ACSLIL-ACSLIL-ACSLIL-ACSLIL-ACSD F DD F D
D F DD F D
DF DFDUMP
0.75
1.4m1.4m
11
DUMP
22.4 m22.4 mTBL
2.5m2.5m
Transport path
DUMP
DUMP 22 m22 m
2.0m2.0m
DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
3.0m3.0m3.0m3.0m6 m6 m
D F DD F D
F DF DF DF D
16.5 m16.5 mTBTS
16 m16 m
TL2’
Instrumentation Test Beam Linenot presently funded(FP7 GADGET proposal)
CEA Dapnia Saclay overall responsibilityCERNCEA laser beam line, laser beam conditioningLAL RF gun for photo injector
Uppsala University Two Beam Test StandCERN PETS and Accelerating structure
CIEMAT magnet movers, PETS prototype,(+ series ????), PETS tank (series ???)UPC & IFIC : BPM development + electronics (series ???)CERN overall responsibility, optics, RF equipment, diagnostics, infrastructure, quadrupoles ???
Pakistan: stainless steel vacuum components + ???Iran: RF + Beam dynamics simulations
16 CTF3 collaboration meeting 2007 G.Geschonke Status
Photo Injector
Solenoid
RF inputPhotocathode
Phase 1:off-line testing from 2007
Phase 2:Gun in CTF3: earliest spring 2008 ?????
smaller emittance, faster phase coding, no “satellite bunches”
Cs2Te photo cathode3% QE40 hours life timepulse train: 1.5 s,charge per bunch: 2.33 nCbunch spacing 0.67 nsnumber of bunches: 2332
diode pumped Nd:YLF laser10 J IR / bunch 0.37 J UV on cathode /bunch
LAL CERN RAL
Present status: RF gun being built, Laser at CERN, needs to be finished with strong involvement from CERN, INFN Frascati and Milan
Laser is needed also for CALIFES injector !
17 CTF3 collaboration meeting 2007 G.Geschonke Status
Plan for 2007
Jan Feb Mar
Wk 1 2 3 4 5 6 7 8 9 10 11 12 13
Mo 1 8 15 22 29 5 12 19 26 5 12 19 26
Tu
We
Th
Fr
Sa
Su
Apr May Jun
Wk 14 15 16 17 18 19 20 21 22 23 24 25 26
Mo 2 9 16 23 30 7 14 21 28 4 11 18 25
Tu
We
Th
Fr
Sa
Su
Jul Aug Sep
Wk 27 28 29 30 31 32 33 34 35 36 37 38 39
Mo 2 9 16 23 30 6 13 20 27 3 10 17 24
Tu
We
Th
Fr
Sa
Su
Oct Nov Dec
Wk 40 41 42 43 44 45 46 47 48 49 50 51 52
Mo 1 8 15 22 29 5 12 19 26 3 10 17 24
Tu
We
Th
Fr
Sa
Su
2007 - CTF 3 - Schedule
CTF3 under access control for HV and
RFconditionning
Shut downCTF3
with beamCTF3 closed with keys for Hardware tests
CTF3
SHUTDOW
N
CTF3 CR installationBeam in PETS
16 October 2006
Tests BI
G. Frid
East
May
Ascen
Whit.
Jeune G.
CTF3 stop with beam
Start conditioning
Tests CO + PO
Start MKS in diode
Machine open
Start with beam
WaterInstallation
CR
PAC 07
Work possible in Linac
Work possible in C.R.
Install BPI
Align BPI
start with beam 2. half March,Commission Combiner Ring operation
Install vacuum system for Combiner Ring
operate for 30 GHz productionlike in 2006:nights and weekends, supervised by CCCfull-time during installation of TL2
Install equipment in CLEX from May 2007
Install TL2: Finish optics, detailed layout produce all vacuum elements produce magnets, power convertersVery ambitious, spill over into 2008 ?
18 CTF3 collaboration meeting 2007 G.Geschonke Status
12 GHz
Decision to change CLIC structure development from 30 GHz to 12 GHz
For 30 GHz: bunch repetition frequency in Linac: 1.5 GHz increase by x2 in DL x5 in CR 15 GHzFor 12 GHz: bunch repetition frequency in Linac: 1.5 GHz increase by x2 in DL x4 in CR 12 GHz
small circumference change in CR can be accomplished with wiggler
no effect on hardware
30 GHz structure programme continues for the moment 12 GHz PETS in TBL 12 GHz PETS and accelerating structures in Two Beam Test Stand
smaller nominal beam current: can be increased by higher current in linac and higher RF power (shorter pulse)
Effect on CTF3:
19 CTF3 collaboration meeting 2007 G.Geschonke Status
DL
CLEX 2007-2009building in 2006
2004 2005
Conclusion
2006
Thermionic gun
CR
TL2 200730 GHz production(PETS line)and test stand
Photo injector / lasertests from 2006 2007
D FFD
D F D
D F D D F D
D F D
DF DF DF DF DF DF DF DF DF
D F D
F DF D
D FFFDD
D F DD F D
D F DD F D D F DD F D
D F DD F D
DF DF DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF
D F DD F D
F DF DF DF D
Linac
Beam up to here
2007
20 CTF3 collaboration meeting 2007 G.Geschonke Status
Conclusion
Highly motivated team, excellent collaboration between all partners
Programme almost on schedule
• Commissioned up to including TL1 and CR injection• Combiner Ring to be completed in 2007, • TL2 in 2007 (?)• CLEX : many components covered by collaboration some still missing
Already demonstrated:
• full Beam Loading operation of linac• Phase coding of bunches• Bunch Interleaving in Delay Loop
21 CTF3 collaboration meeting 2007 G.Geschonke Status
Meeting Objectives
Define some open questions:
BPM / BPI: electronics TBL diagnostics – monitor + read-out
PETS TBL: Advance on tank design
Open topics not covered: TBL RF + other diagnostics - discussions with EPFL started, analog front-end ?TBL series components: quadrupoles, PETS, diagnosticsMachine protectionRadiation monitoring