![Page 1: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/1.jpg)
Copyright 2007 blueVisions Management Pty Ltd
1
Project Performance Measurement Approach Project Performance Measurement Approach InIn
Road Construction IndustryRoad Construction IndustryUsing EVPMUsing EVPM
Pedram Daneshmand; [email protected] [email protected]
Adel Khreich; [email protected][email protected]
June 07, Australia
![Page 2: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/2.jpg)
Copyright 2007 blueVisions Management Pty Ltd
2
Introduction
Project Monitoring & Control Ideal Control System Main Elements: Cost, Time, Quality and Safety
Techniques: Leading parameter Activity based ratios Variances Earned Value Performance Measurement (EVPM)
![Page 3: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/3.jpg)
Copyright 2007 blueVisions Management Pty Ltd
3
Ideal Control System
Example: Construction of a bridge Budget: $10’000’000 Project Duration: 1 year After 6 months, we have received an invoice
of $5’000’000. The question is how much job really done?
More accurate answer, ideal Control System
![Page 4: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/4.jpg)
Copyright 2007 blueVisions Management Pty Ltd
4
EVPM Background
Industrial base – at the turn of the 20th century
US - Department of Defence Idea took root in 1960’s C/SCSC (35 criterions) in 1967 Emerged as a PM tool in the early 1990’s
![Page 5: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/5.jpg)
Copyright 2007 blueVisions Management Pty Ltd
5
EVPM Process
Decompose the WBS Assign responsibility Planning/Scheduling Develop time-phased budget Objective measures of performance Set the performance baseline Monitor & Report
![Page 6: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/6.jpg)
Copyright 2007 blueVisions Management Pty Ltd
6
Case Study – NWT-Way, Sydney, Australia
Bus rapid transit line A$500M D&C Feb 04 to Dec 07 24 Km 30 Stations 7 Bridges 1 Underpass Cycleway, pedestrian
facilities
![Page 7: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/7.jpg)
Copyright 2007 blueVisions Management Pty Ltd
7
Case Study – NWT-Way, Sydney, Australia
![Page 8: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/8.jpg)
Copyright 2007 blueVisions Management Pty Ltd
8
Case Study – NWT-Way, Sydney, Australia
![Page 9: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/9.jpg)
Copyright 2007 blueVisions Management Pty Ltd
9
1 – WBS & Work Packages
North West T-Way
Zone 1 Zone 2 Zone 3 Zone 4
Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Section 8
50Locations(all Sections)
34 Disciplines
L1
L2
L3
L4
L5
![Page 10: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/10.jpg)
Copyright 2007 blueVisions Management Pty Ltd
10
2 – Budget Cost Allocation
Locate the 4th or 5th level of WBS. Get the direct cost info. Allocate costs over each Work Package. Allocate the linear relationship or a more
accurate non-linear expenditure against time.
![Page 11: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/11.jpg)
Copyright 2007 blueVisions Management Pty Ltd
11
3 – Schedule & Plan Value (PV)
Prepare your schedule plan using CPM Locate the WP’s within the schedule Allocate the costs to WP’s Create the S-Curve, PV or BCWS Do resource levelling Check the financing plan Finalise the PV curve
![Page 12: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/12.jpg)
Copyright 2007 blueVisions Management Pty Ltd
12
Plan Value (PV)
![Page 13: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/13.jpg)
Copyright 2007 blueVisions Management Pty Ltd
13
4 – Progress Monitoring/Updating
Schedule updating Fortnightly with: Actual Start & Finish dates Revised Start & Finish dates Revised Duration Updated Incomplete activities
0-100; 50-50; 25-75; and 33-67 Level of Effort (LOE) Percent Complete
![Page 14: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/14.jpg)
Copyright 2007 blueVisions Management Pty Ltd
14
4 – Progress Monitoring/Updating
Cost updating Monthly with: Claim Costs Site Actual Costs (AC) or ACWP
![Page 15: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/15.jpg)
Copyright 2007 blueVisions Management Pty Ltd
15
5 – EVPM calculation
EV(BCWP) = % Comp x PV(BCWS)
Schedule Variance (SV) = EV – PV Cost Variance (CV) = EV – AC SPI = EV / PV CPI = EV / AC PCP = PV / Total Budget PCA = EV / Total Budget EAC = AC + ETC
![Page 16: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/16.jpg)
Copyright 2007 blueVisions Management Pty Ltd
16
6 – Data Analysis & Progress Report
Summary Programme Progress Report Critical Path Investigation Design Progress Report Construction Progress Report Earned Value Progress Report Schedule/Cost Variance Progress Report Cash Flow Report
![Page 17: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/17.jpg)
Copyright 2007 blueVisions Management Pty Ltd
17
6a – Programme Progress Report
Cumulative Progress Monthly Progress
Description PlannedActual
*Varianc
e PlannedActual
* Variance Zone 1:
Design Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%Construction Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%
Zone 2:
Design Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%Construction Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%
Zone 3:
Design Status (%) = 100% 100% 0% 0.0% 0.0% 0%
Construction Status (%) = 77.4% 86.9% 9.5% 3.9% 3.5% 0.4%Zone 4:
Design Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%
Construction Status (%) = 67.2% 70.1% 2.9% 9.3% 7.1% 2.2% TOTAL:
Design Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%
Construction Status (%) = 85.7% 88.7% 3.0% 3.5% 2.8% 0.7% TOTAL Project Status (%)
= 86.8%89.5
% 2.7% 3.1% 2.6% 0.5%
![Page 18: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/18.jpg)
Copyright 2007 blueVisions Management Pty Ltd
18
6b – Critical Path Investigation
![Page 19: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/19.jpg)
Copyright 2007 blueVisions Management Pty Ltd
19
6c – Design Progress Report
![Page 20: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/20.jpg)
Copyright 2007 blueVisions Management Pty Ltd
20
6d – Construction Progress Report
![Page 21: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/21.jpg)
Copyright 2007 blueVisions Management Pty Ltd
21
6e – Earned Value Progress Report
![Page 22: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/22.jpg)
Copyright 2007 blueVisions Management Pty Ltd
22
6f – S/C Variance Progress Report
![Page 23: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/23.jpg)
Copyright 2007 blueVisions Management Pty Ltd
23
6g – Cash Flow Report
![Page 24: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/24.jpg)
Copyright 2007 blueVisions Management Pty Ltd
24
Conclusion
EVPM is a good tool for improving the analysis of progress and performance on a construction project.
Although level 4th WP’s give accurate results, site engineers feel more confident at 5th level.
General overheads and profits should be eliminated from the analysis so that actual expenditure can be directly compared with budgeted expenditure.
Within this closed network, activities are updated with time data and WP’s updated with cost info.
The test data needs to be expanded with data from a wider range of road projects to provide more practical usages and procedures of EVPM system.
Getting the accurate cost figures from financial dept and the real time and performance data from site engineers, makes the EVPM system a reliable performance measurement tool.
![Page 25: 1 Copyright 2007 blueVisions Management Pty Ltd Project Performance Measurement Approach In Road Construction Industry Using EVPM pedramd@bluevisions.com.au.](https://reader035.fdocuments.in/reader035/viewer/2022062714/56649d1a5503460f949f0505/html5/thumbnails/25.jpg)
Copyright 2007 blueVisions Management Pty Ltd
25
Acknowledgment
Consulting services was undertaken and fully supported by: Blue Visions Management Pty Ltd (BVM), Sydney, Australia.
Database support has been provided by: Leighton Contractors Pty Ltd (LCPL), Australia.