1 Control Room Habitability Program James A. Carlson, Omaha Public Power District, Author Deep...
-
Upload
clemence-park -
Category
Documents
-
view
270 -
download
0
Transcript of 1 Control Room Habitability Program James A. Carlson, Omaha Public Power District, Author Deep...
1
Control Room Habitability Program
James A. Carlson, Omaha Public Power District, Author
Deep Ghosh, Southern Nuclear Operating Greg Holbrooks, PE, Duke Energy
2
NHUG CRH Program Guide
Control RoomHabitability
Program
3
Status The latest revision of the document will be
available on NHUGweb.org The document has been reviewed at
previous NHUG meetings and by others Comments were appropriately
incorporated. Is a living document.
Refinements should be done after it is used and lessons learned can be adopted.
4
Federal Register - CRE Habitability Program
Federal Register / Vol. 72, No. 10 / Wednesday, January 17, 2007 / Notices, pages 2030 & 2031
3.4 TS 5.5.[18], CRE Habitability Program A CRE Habitability Program TS acceptable to the
NRC staff requires the program to contain the following elements:1. Definitions of CRE and CRE boundary….2. Configuration control and preventive
maintenance of the CRE boundary. 3. Assessment of CRE habitability at the
frequencies stated … of Regulatory Guide 1.197, Revision 0 … and measurement of unfiltered air leakage into the CRE in accordance with … Regulatory Guide 1.197…
5
Federal Register - CRE Habitability Program continued
A CRE Habitability Program TS acceptable to the NRC staff requires the program to contain the following elements:4. Measurement of CRE pressure with respect to
all areas adjacent to the CRE boundary…5. Quantitative limits on unfiltered inleakage….6. …the program states that the provisions of SR
3.0.2 are applicable to the program frequencies for performing the activities…
7. …that (1) a CRE Habitability Program shall be established and implemented, (2) the program shall include all of the NRC staff required elements, as described above, and (3) the provisions of SR 3.0.2 shall apply to program frequencies….
6
Guidance Documents
Tech Specs Amendments & TSTF-448. RG 1.196 guide assesses CRH
configuration control. RG 1.197 addresses testing of the
Control Room Boundary. NEI 99-03 to ensure CRH program
meets regulatory guidance.
7
CRH Program Content is All Inclusive
Purpose and Scope States Applicability Definitions Responsibilities CRH Evaluation CRH Program References Attachments
8
Comments on CRH Program Document
The following slides address the comments and how they were incorporated.
Comments are in Red. Responses are in Blue.
9
Conformance to NEI 99-03, Revision 0 is Complete
Comment: NEI 99-03, Revision 0 is the only version that will be reviewed by NRC.
Response: The Control Room Habitability Program is reconciled with Rev. 0 of NEI 99-03. Regulatory Guide 1.196 endorsed, with
exceptions, NEI 99–03 Revision 0, dated June 2001 Many aspects of the CRH program are not
covered in the NEI document, Rev. 0.
10
Scope Expanded to Discuss the Licensing Aspects. Comment: CRH Program to
address RIS 2005-20 “Inoperable” and “Operable but Degraded”. Scope was expanded to provide an
explanation of mitigating actions versus compensatory actions.
RG 1.196 only uses compensatory actions which applies to Operable but Degraded.
Mitigating actions added as alternate actions based on test results
11
Section 4: Responsibilities Comment: Where do we address
impairment of the CRES. i.e., more than just the boundary?
Response: The responsibilities address the program as a whole.
The CRHP describes the responsibilities of each principal and functional group for implementing the requirements of this procedure.
12
Section 5: CRHP The Control Room Habitability Program
consists of actions that demonstrate that systems and procedures are in place to meet the requirements in compliance
Comment: we comply with regulations and conform to guidance.
Done, terminology matches use.
13
Section 5.4 Comment: Does the evaluation
not determine which chemicals represent reasonable threats and whether the CRE remains habitable?
Response: No. This is way beyond the documents intent. Reference Regulatory Guide 1.78.
14
Section 5.4.6 Training Requirements “Training is performed to ensure the
level of understanding of … personnel.” Add Training to the CRH Program.
RG 1.196, “NRC staff endorses training using only the sections of NEI 99-03 that the staff has endorsed.” That’s it.
RG 1.196 does not provide any real guidance. No additional changes made. This is a site decision.
15
Section 5.5: Boundary Impairment
Impairment Permit is always required whenever the boundary is penetrated.
Chart is updated to reflect planned activities.
Impairment Permit is a guidance control method. Each site to control as appropriate.
Barrier is Impaired
Section I: Control Room Boundary
Impairment Permit is Required?
Section II: Compensatory
Actions required?
No
NoYes
Yes
Section IV: Control Room
Boundary Impairment
Permit Approved
Section V: Implement
Compensatory Actions
Section VI: Work Group
Restore Barrier And Test As
RequiredSection VII: Work
Activities Completed And Approved
Exit Control Room Boundary
Impairment Permit
Perform Safety Review
Determination
Section VIII: Remove
Compensatory Actions And Update Log
Old Chart
16
Section 5.5.1: Limitations and Precautions has Questions Barriers with no design basis function (??) in
any plant mode do not require a Barrier Impairment Checklist. Paragraph revised
All doors may be manually held open for ____ (15) minutes (justification?) …
Doors can be manually held open with a Barrier Impairment Checklist for repair up to ____ (14) days (justification?)
10% (are we solid ground??) of the door seal may be removed…
Numbers removed and additional guidance provided to obtain
values
17
Section 5.6.8: Inleakage Through Doors Analysis should include inleakage for
ingress and egress of the Control Rooms (currently assumed as 10 cfm). … Ingress and egress of control rooms with vestibules can assume an unfiltered infiltration airflow rate of 0 cfm
Comment: Basis for 0 cfm? Reference to the Reg Guide for the
0 cfm added
18
Section 5.9.2: Comparison to License Basis
A system walk down shall be performed to ensure that the actual field configuration agrees with the plant drawings/design.
To what extent? All drawings and all specs every assessment, or only those which have changed? – No changes were made. A determination for each site.
How much credit is to be given to the design controls? – Allows flexibility. A determination for each site.
19
General Comments There is no mention of differential
pressure monitoring in the document. Differential pressure monitoring is now
mentioned. There is no mention of on-going local
leak testing of penetrations. On-going quantifiable leak testing of
penetrations is still not mentioned. Alternate testing guidance is provided and can be used for this.
20
General Comments
Recommend we get someone with a licensing background to review this document. Performed by Brian Mann. Brian
interfaced w/ NRC representing NEI on TSTF-448.
21
General Comments Comment: After reviewing the draft
generic guide dated 4/21/07…we need two different versions. Some plants will adopt TSTF-448 into their Technical Specifications and some will not.
This is a guidance document for the industry to use as appropriate for the site’s application of a CRH Program aligned with TSTF-448.
22
Control Room Habitability Program Document Status
CONTROL ROOM HABITABILITY PROGRAM NHUG-G-001 : NHUG CRH Program 1-7-08
Document Status: Incorporating Comments Notify Jim, Deep or myself with comments. Jim Carlson, [email protected] Greg Holbrooks, [email protected] Deep Ghosh, [email protected]
After incorporation of comments, the document will be sent to NHUG Board for approval.
23
The EndJim Carlson
deserves credit for a significant amount of work to assist the industry.