1 Competitive bidding guidelines for power procurement Presentation to Hon’ble Central Electricity...
-
Upload
cindy-thrasher -
Category
Documents
-
view
219 -
download
0
Transcript of 1 Competitive bidding guidelines for power procurement Presentation to Hon’ble Central Electricity...
1
Competitive bidding guidelines for power procurement
Presentation to Hon’ble Central Electricity Regulatory Commission and Distinguished Invitees
May 7, 2004
2
AGENDA
• Context and objectives
• Need and importance of competitive bidding for power procurement
• Guiding principles
• Our suggestions
–Scope of guidelines
–Bidding process and evaluation of bids
–Enablers for speed, transparency, and fairness
3
CONTEXT FOR TODAY’S DISCUSSION
Electricity Act, 2003 aspires to create a liberal framework for the development of the power sector – “An Act to consolidate the laws…for taking measures conducive to development of electricity industry, promoting competition therein, protecting interests of consumers and supply of electricity to all areas…”
Current situation End goal
Largely cost plus tariff systems with limited incentives for improving efficiencies
A well functioning power market leading to free competition – rewards more efficient generators and reduce power procurement cost
Gradual transition path
The power sector needs to introduce competition into the
power procurement process as it gradually migrates to competitive markets across electricity value
chain
4
INDIAN ELECTRICITY REGULATIONS ENVISAGE A COMPETITIVE MARKET
• “Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government”
• “Under the competitive bidding route, the Commission perceives its function of regulating tariffs to primarily be the scrutiny and approval of the process adopted for competitive bidding, with a view to ensure that competitive conditions do prevail”
• “A significant portion (which could be up to 50% of the new capacity) should be committed to trading or other forms of competitive power markets. This could be attained over a period of time, keeping in view the transition requirements.”
• “As far as possible, power procurement should be through a transparent competitive bidding mechanism.”
Section 63 Electricity Act 2003
CERC order dated 9th March 2000 on a petition filed by Power Trading Corporation Ltd.
Task force report on power sector 2004 , page # 275
Tariff Policy, Appendix 1 of the Task force report 2004 , page # 275
5
THE TASK FORCE REPORT ALSO SEEKS TO ENHANCE COMPETITION IN THE SECTOR USING COMPETITIVE BIDDING
*Page 289 – Report of the Task force on Power Sector Investment and Reforms (Feb 2004 Volume I)
The task force report of 2004 specifies five preferred mechanisms for procurement of electricity through competitive bidding*
• Tariff based bid for entire project capacity
• Tariff based bids for blocks of capacity
• Competitive tariff based bidding, without being related to any particular generation source
• Tariff based bidding for peaking requirements
• Bidding on capital cost of specific project (with overall two part tariff structure)
Linked to particular generation capacity
6
OBJECTIVES OF TODAY’S DISCUSSIONS
• Share our views on competitive procurement of generation and transmission capacity
• To achieve consensus on how to formulate and implement guidelines for competitive bidding process, so that it embodies the spirit of the Electricity Act 2003
• To discuss and arrive at a consensus on the extent of standardization required in the bidding process and documents in order to expedite the process
7
AGENDA
• Context and objectives
• Need and importance of competitive bidding for power procurement
• Guiding principles
• Our suggestions
–Scope of guidelines
–Bidding process and evaluation of bids
–Enablers for speed, transparency, and fairness
8
221
363
267230
106
98119136
POWER PROCUREMENT COST IS A LARGE PORTION OF THE TOTAL COST OF SUPPLYPaise/Kwh, 2001-02
357
469
365349
Power procurement cost
Other cost
Power procurement cost as percentage of total cost of power(Per cent)
62 77 73 66
Maharashtra Delhi Gujarat All India
Source: Planning commission report on SEB performance (2001-02)
9
0
500
1000
1500
2000
2500
3000
3500
4000
0% 20% 40% 60% 80% 100%
POWER PROCUREMENT IS COMPLEX DUE TO DIFFERENT BASELOAD AND PEAK LOAD REQUIREMENTS
Hours of the year
Delhi’s ‘unrestricted’ load duration curve (MW)
Source: Delhi operations of REL
Baseload
Intermediate
Peak
10
TODAY, SIGNIFICANT COST DIFFERENCES EXIST AMONG GENERATORS
• While some of these differences can be explained by differences in fuel type, technology, location and vintage, some differences are attributable to differing generation efficiencies
• Current cost plus system does not adequately encourage generators to improve operational efficiencies
Tariffs of various plants supplying to Delhi
Power plant Type MUs bought Rs/Kwh
• Salal
• Baira Siul
• Tanakpur
• Singrauli
• Chamera
• Rihand
• Anta
• Auraiya
• Unchachar-I
• Uri
• Dadri (Gas)
• Unchachar-II
• Dadri (Thermal)
• Badarpur BTPS
• RPH
• IP Station
• GT
• Pragati PPCL
• RAPP(B)-III
• NJPC
• RAPP (B)-IV
• Hydro
• Hydro
• Hydro
• Thermal
• Hydro
• Hydro
• Thermal (GT)
• Thermal (GT)
• Thermal
• Hydro
• Gas
• Thermal
• Thermal
• Thermal
• Thermal
• Thermal
• Thermal (GT)
• Thermal (GT)
• Nuclear
• Hydro
• Nuclear
358
86
58
1,370
132
850
375
600
190
286
640
400
5,065
4,600
740
490
1,060
1,706
28
160
276
0.59
0.63
1.04
1.09
1.32
1.47
1.61
1.62
1.88
2.08
2.24
2.26
2.27
2.37
2.50
2.50
2.50
2.71
2.98
3.02
3.25
Source: Delhi Electricity Regulatory Commission order on Delhi Transco ARR for 2002-03 and 2003-04
11
POWER MARKET IS REQUIRED TO EVOLVE TO A NEW STRUCTURE
Today’s wholesale power procurement model
Desired market structure for power procurement (in the end-state)
• Single buyer model - SEB/transco pools distribution utility requirements to procure power
• Multiple buyer model (e.g., each distribution company procuring for its own requirements)
• Primarily long duration contracts • Suitable mix of long, medium and short term contracts
• Cost plus tariff setting– CPSUs and SEBs: cost plus tariffs
based on CERC/SERC orders– IPPs: mix of cost plus and tariff based
bidding
• Tariff setting driven by market forces
• Limited incentives to improve efficiency • Market rewards players with lower costs and higher efficiencies
12
TO REACH THE REQUIRED STRUCTURE, IT IS IMPERATIVE TO ACHIEVE COMPETITION IN GENERATION
What needs to be achieved as the market transitions to full competition?
• Reduce inefficiencies in generation plants to enable low cost power production
• Encourage private investment in generation to keep pace with growing demand
• Develop a fast, efficient and transparent bidding process that expedites procurement
• Building a framework for the end state of the power procurement in the envisaged free market pricing system
Competitive bidding based power procurement is crucial for the healthy development of this sector
13
AGENDA
• Context and objectives
• Need and importance of competitive bidding for power procurement
• Guiding principles
• Our suggestions
–Scope of guidelines
–Bidding process and evaluation of bids
–Enablers for speed, transparency, and fairness
14
GUIDING PRINCIPLES FOR COMPETITIVE BIDDING
Competitive bidding process should ensure
• Free fair and effective competition
• Transparency
• Simplicity and cost effectiveness of process
• Minimal burden on regulator and other stakeholders
• Flexibility to adapt to varying needs of power procurement according to the structure of the sector
The new guidelines should adequately build on CERC and GOI guidelines issued
earlier by incorporating new inputs from EA 2003 and the Task Force report
15
AGENDA
• Context and objectives
• Need and importance of competitive bidding for power procurement
• Guiding principles
• Our suggestions
–Scope of guidelines
–Bidding process and evaluation of bids
–Enablers for speed, transparency, and fairness
16
GUIDELINES SHOULD COVER PROCUREMENT BY VARIOUS ENTITIES
Procurement transaction
Buyers Sellers
Existing generatingstationsDistribution
Licensee
New generatingstations
Distribution Licensee (?)
Trading licensee
Nominated Buyer (?)
Trading licensee
17
GUIDELINES SHOULD COVER BOTH GENERATION AND NEW TRANSMISSION CAPACITY
Procurement category
• Generation
Should guidelines cover it?
• Yes – Capacity
– Energy
May be baseload/Peak or off peak
• Transmission capacity
• Not required– Existing
– Setting up new capacity
May be entire day/part day
• Firm
• Non-firm
• Yes
• Ancillary services
Rationale
• This would form the bulk of the power procurement bids; hence it is imperative that the guidelines cover these
• Rules for open access on transmission lines already well defined (e.g., transmission service charge bidding)
• New capacity addition not based on competitive bidding so far, but lends itself to the process quite naturally
• The concept of ancillary services not well developed yet
• In future as market matures guidelines may be expanded to include these as well
• Not initially– Spinning reserves– Reactive Power– Harmonics etc.
18
TODAY, DISCOMS/TRANSCOS PROCURE POWER MAINLY THROUGH LONG TERM BILATERAL CONTRACTS
Description/Details
• Generally 15-25 year contracts. New capacity may be added if needed
• Capacity added in three ways -
• Upto one year duration contracts; (form small part of total power procured)
• SEBs propose power purchase from third parties in their ARRs, prior to actual contract
• Some SERCs have taken a hands off view on these bids as long as the total annual power purchase cost remains within budget
Long term
Short term
• No day ahead market
• Real time power requirement (in excess or deficit of scheduled drawls) drawn directly from grid without any prior permission from regulator
• SEB pays/receives UI charges under ABT regime at the end of accounting cycle
Real time/day to day
No clear process currently for bridging medium term requirements (i.e. more than one year and less than 15 year duration)
– Self generation (SEB owned generators); capacity cleared by SERC as required
– Allocation from central generating stations ; CERC determines tariffs
– Independent power producers; Bid/MOU route for projects; CERC/SERC vets the tariff
Excessive burden on regulator
Medium term
19
PROPOSED GUIDELINES WOULD COVER POWER PROCUREMENT PHASE
Competitive bidding
Traders
Generators
• Competitive bidding
Pricing mechanism
MOU based bilateral
contracts
With generator
With traders (e.g., PTC)
• Cost plus pricing
Pricing mechanism
• Cost plus pricing
• Competitive bidding by Trader
Discom power procurement
Covered by competitive bidding guidelines
Discom forecasts its power requirements for • Long term• Medium term• Short term
Regulator approves forecasted power need
Discom procures power
20
IN TERMS OF DURATION, GUIDELINES WOULD COVER ALL PROCUREMENT CONTRACTS OUTSIDE THE DAY AHEAD AND REAL-TIME MARKET
Description of type of contracts
• All contracts greater than 10 year duration
• Contracts that span 1-10 years duration
• Power requirement for several months duration (upto 1 year)
Long term
Medium term
Short term
• Typically a day to a week ahead demand
• Requirement typically driven by forecasting error/ weather changes/unforeseen conditions
Day(s) ahead market / Emergency procurement
Proposed scope of guidelines
• Unscheduled spikes/drops in demand that have to be managed
• Can continue with current UI/ABT system until the establishment of a fully functioning wholesale and spot market
Real time
The lead time (advance
notice before start of
contract) needs to be decided for each term
(long/ medium/ short) to ensure
effective competition
21
AGENDA
• Context and objectives
• Need and importance of competitive bidding for power procurement
• Guiding principles
• Our suggestions
–Scope of guidelines
–Bidding process and evaluation of bids
–Enablers for speed, transparency, and fairness
22
BIDDING PROCESS WOULD START WITH THE REGULATOR APPROVING THE DEMAND FORECAST FOR THE DISTRIBUTION COMPANIES
Demand forecast for short / medium / long term by discom
Regulatory approval of forecast
Procurement process
Path 1
Using non-standard bid documents
Using standard bid documents
• Guidelines specify process to be followed in each case
• Standard documents supplied for following path 1
• Regulator approves documents if path 2 is followed
Path 2
23
PROPOSED POWER PROCUREMENT BIDDING PROCESS IF STANDARD DOCUMENTS ARE USED
Key activities/Salient points
At each stage we may specify minimum number of bids to
proceed to next stage
Requirement definition
Initiate RFQ Shortlist bidders
RFP Bidding Evaluation of bids
Award of bid(s)
Post bid negotiations
• Specification of – Quantum– Timing– Duration of
contract
• Publish notice
• Issue RFQ
• Evaluate responses to RFQs
• Shortlist bidders
• For short term contracts bidders may be pre- qualified
• Issue RFP to selected bidders
• Conduct pre-bid conference
• Short listed bidders invited to submit bids
• Technical compliance must for any bid to be considered
• Determination of winner on bases of price bids
• Use of independent observer if necessary • RFQ/RFP process may be combined into single
step, especially for short term contracts
Regulator kept informed at all stages of the process
24
PROPOSED POWER PROCUREMENT BIDDING PROCESS IN CASE OF DEVIATIONS FROM STANDARD BIDDING DOCUMENTS
• Any modifications suggested by bidders, or due to any other reasons to be approved by regulator – possibly over several rounds of iterations
Requirement definition
Prepare bidding documents
Initiate RFQ Shortlist bidders
Seek regulatory approval
Iterations on development of bid documents
Regulatory clearance of forecast
A
RFP Bidding Evaluation of bids
Awards of bid
Post bid negotiations
ARegulator’s comments on process and go ahead
Even though active regulatory approval
needed in only certain stages, but the regulator is
always kept informed of all developments
Regulatory approval if required
25
IN THE RFQ STAGE, BIDDERS SHOULD BE SCREENED ON THE BASIS OF AN ARRAY OF METRICS
Financial metricsTechnical metrics Past record
To ensure supply contracts, in case of default
To minimise risk of delay/shortfall
To prevent frivolous/mischievous bidders
• To ensure supply contracts, in case of default Net worth
• Credit worthiness • Bank/other financial
guarantees
• For new plants – Past infrastructure
project execution– Resource raising
• For existing plants– Reliability – Performance in the past
• Tie ups with transmission companies preferred
• Should be an organization of repute
• No default on previous contracts
• Net worth • Credit worthiness • Bank/other financial
guarantees
• For long term contracts trader should show the capability/history to source 70-80% of contract amount
• Tie ups with generators and transmission companies are preferred
• Source of power has to be specified
• Trader of repute • No default on past
contracts• Past litigation record • No conflict of interest
between other obligations and contract being bid
Limits to vary by duration of contract and amount of load contracted
To be suitably relaxed in initial stages for traders, as they would have no history of trading operations
For generators
For traders
26
FOR MEDIUM/LONG TERM CONTRACTS, AT RFP STAGE, BIDS SHOULD BE SCREENED BASED ON NON PRICE EVALUATION PRIOR TO PRICE COMPARISONSElement for evaluation Details
• Financial guarantee covering supply default
• Different bidders could be capable of delivering power at different points in grid
• Most reliable/least bottlenecked point most preferable
• Relevant for time of day contracts, or for parts of long term contract
• Best fit to demand should get preference
• Bidder asking for least financial guarantee from buyer would be preferred
• Risk sharing mechanism in case of forced outages/unforeseen circumstances
Supplier’s guarantee
Delivery point
Delivery dates/period
Buyer’s guarantee
Force majeure /risk sharing
All these aspects need to be
sufficiently detailed in the standard bid
documents and processes, to
enable bids to be efficiently and transparently
evaluated/ rejected on technical merits
27
BUYER SHOULD SPECIFY THE BID STRUCTURE IN DETAIL
Whether part bidding is allowed?
What is being bid for?
What is the tariff structure used?
• No part bidding
• Part bidding allowed
• Part bidding allowed in multiples of some pre-specified minimum bid unit (preferred option)
• Energy
• Capacity
• Percentage of load (varying)
• Single part tariff
• Two part tariff with suitable indexation (preferred)
Elements of a bid
Illustrative examplesElement
Discussed further
28
BID PRICING STRUCTURE WOULD USUALLY EMPLOY A TWO PART TARIFF
Details
• Two part tariff structured as followsPrice setting mechanism
Aspect
Fixed component (X) + Variable component (Y)
X = X1 + X2 X1: Inflation linked (e.g., O&M)
X2: Non-Inflation linked (e.g., debt servicing)
Y = Y1 + Y2 Y1: Variable component not linked to any index
Y2: Linked to suitable energy index*
• Both X and Y could vary by time frame
• Buyer should compare the competing bids based on annualised/NPV type calculations
• Bidder should not be disqualified for submitting different price bids in different contracts
*Index might be a reference fuel price, or price of a basket of fuels, or some other indexNote:Medium term contracts could follow a pricing mechanism similar to long term contracts with simplified indices
Tariff bid =
29
FOR SHORT TERM CONTRACTS, THREE ASPECTS SHOULD BE MODIFIED TO SPEED UP THE PROCESS
Details
• Single part tariff– No escalation/inflation– No fuel variation
• Bids compete purely on single price (i.e., all bids that fulfill all technical criteria beforehand)
Bid pricing
Aspect
• Bidders empanelled once• Panel kept updated on regular basis• For each short term requirement, panel members asked to bid –
eliminates the need for bidder qualification step in procurement process
Empanelment of bidders
• Bid process may be started (public notification stage) upto a few weeks before the actual requirement of the contract
• Thus mostly traders and existing generators would likely bid for these
Short lead times
Discussed further
30
EMPANELMENT OF BIDDERS - DETAILS
Rationale
Process/details of empanelment
Updation of bidders panel
• Short term bids need to be executed rapidly since time is of the essence
• Need to avoid unnecessary repetition/ duplication of records
• For short term bid, buyer should skip bidder qualification
• Buyer should ask the existing panel of bidders to bid
• Buyer should regularly update the list of empanelled bidders
Buyer should update the list of empanelled bidders to reflect changes over time. These would include –
• New entrants – should be allowed to submit details at 3-4 occasions in an year. Once a bidder is empanelled, he stays on the panel until he withdraws, or is disqualified
• Regular checks - Empanelled bidders should submit details of credit worthiness and make other financial/ legal disclosures annually. Any discrepancy / shortfall could lead to revoking of pre-qualified status
• Disqualification from panel - Bidders will attract disqualification if
– They default (or dishonor) on any contract
– They have not participated in the last 3-4 bids up for competition
31
INTERNATIONAL PRECEDENTS OFFER SEVERAL USEFUL TIPS FOR FORMULATING THE COMPETITIVE GUIDELINES
Aspect International examplesReference document Issue date/number
Bidding for part of the contract
• RFP for Central Maine Power Company allows bidders to bid in multiples of 20% of total contract amount
• November 18, 2003; issued by Maine PUC
Use of Independent observer
• Independent observer was used for overseeing the process of RFP’s for Portland General Electric Company
• January 20, 2004; Interim report of independent observer
Use of discounting/ NPV calculations for evaluation
• Public service commission of Maryland approved use of single discounted average term price (DATP) for evaluation of bids in the phase II settlement proceedings
• Order no. 78710 Case no. 8908; Phase II September 2003
Pre-qualification of bidders to form a panel
• Rules of the Florida Public Service Commission on general purchasing procedures allow the prequalification of bidders to form a panel
• Ch.25-25 Sup no.194
Financial guarantees from bidders
• RFP for Central Maine Power Company required bidders to provide financial guarantees upto US$ 1.21 million/month and 1.50 million/month while bidding for service to 2 classes of consumers
• November 18, 2003; issued by Maine PUC
Bidding for percentage of load
• Rather than a fixed load (in MW/ MWh) the bid may be asked for the percentage of the utility’s load, so as to offload some risk to the suppliers
• EPSA guidebook for design implementation and monitoring of competitive power supply solicitations
Bidding for partial duration
• EPSA guidelines mention use of annuity based calculations while comparing bids for unequal (part) duration and choosing a lower overall bid portfolio
• EPSA guidebook for design implementation and monitoring of competitive power supply solicitations
32
INTERNATIONAL BIDDING PROCESS - EXAMPLE
US long term PPA bid process
• Posting of information publicly
• Request for Expressions of Interest (EoI)
• FERC and PJM qualification
• Credit application and financial information received
• Pre-bid conference
• Eligible bidders qualified and issued certification
• Request for detailed proposals from eligible bidders
• Price proposals received
• Bids evaluated
• Award of bids
• More rounds if previous rounds fail to meet objectives
• Iteration continues till satisfactory solution reached
• Retail prices published 6 months before start of contract
Receiving proposals
Process start
Receiving EOIs
Regulatory Validation
Bidder selection
Round 1Revision/Round 2
Contract start
Steps
Timeline
Details
3½ months 15 days 15 days 15 days 2 months 9 months
Source: Allegheny power RFPs and RFQs
33
AGENDA
• Context and objectives
• Need and importance of competitive bidding for power procurement
• Guiding principles
• Our suggestions
–Scope of guidelines
–Bidding process and evaluation of bids
–Enablers for speed, transparency, and fairness
34
SYSTEMS REQUIRED TO ENSURE SPEED, TRANSPARENCY AND FAIRNESS
Communications
Information dissemination
Independent observer
• All communications to be made in written form
• All records retained for a certain duration after the end of bidding
• Optional separate rounds for RFP and RFQs
• All details of bid process and method given to all bidders
• All factors that will be considered and their relative weights notified in advance
• Not required in usual biddings – as long as standard processes are being followed
• Needed if an affiliate of the buyer is also bidding for the contract
• This would be more of an oversight role without any involvement in decision making
Standardization of contracts
• Standard contract documents to cover as many scenarios as possible
• All deviations counted as material deviations – requiring regulatory approval
Speed
Transparency
Fairness
Discussed further
35
STANDARDIZED BIDDING DOCUMENTS NEEDED FOR EXPIDITING PROCESS
• Providing standard documents as templates is important to
– Expedite process
– Prevent the whole process from getting bogged down in litigation
– Reduce burden on regulator and all shareholders
• Standardization is easy for short term contracts. It gets increasingly complex as the duration of contracts increases
• For new plants standard documents need to capture all possible aspects of
– Finance structuring
– Risk sharing
• Need to provide flexibility for future requirements
Need for detailed documents as standard templates; but with sufficient flexibility to ensure responsiveness to
new needs
36
IMPORTANT ISSUES FOR DEBATE – NOT EXHAUSTIVE
• Can any buyer aggregate power requirements
– Across distribution companies?
– Across states?
– Across regions?
• Even though the Electricity act itself does not prohibit such aggregation, would this lead to a dispute between state and central bodies ?
• How do these guidelines change with the development of a power pool?
• Should there be a common energy index to link the variable costs of plants? If yes, how should it be developed/monitored/updated?
• Should the buyer inform rejected bidders about reasons for rejection?
• Should the buyer seek power at one specific delivery point per bid and compare costs accordingly?
• For long-term procurement requiring set up of new capacities, should the buyer specify location, fuel, technology (e.g., for BOT basis)?
• Evaluation of non-price factors
• What is the process for dispute resolution?
• Is the duration definition (long-term > 10 years, medium-term between 2 and 10 years, and short-term less than 2 years) rigid or evolving over time?
• Should these guidelines cover competitive bidding by a trader as well?
In order to avail benefits of scale (e.g., flattened load curve, economic size of the plant) and reduce transaction costs
37
Thank you