1 Chapter 8 Lecture # 1-3 Overview of Chapter 8 A Typical CFD for Evaluation of a New Project Profitability Criteria for Project Evaluation

Transcript of 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis...

Page 1: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

1Chapter 8

Lecture # 1-3

• Overview of Chapter 8

• A Typical CFD for Evaluation of a New Project

• Profitability Criteria for Project Evaluation

Page 2: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

2Overview of Chapter 8

Title: Title: Profitability Analysis Analysis

Topics:Topics:

• A Typical CFD for Evaluation of a New Project

• Profitability Criteria for Project Evaluation

• Comparing Several Large Projects

• Comparing Investment Alternatives

• The Concept of Risk

• Evaluation of Equipment Alternatives

• Profit Margin

Page 3: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

3A Typical CFD for Evaluation of a New Project

Page 4: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

4Profitability Criteria for Project Evaluation

3 Bases for Evaluation of Profitability

Time

Cash

Interest Rate

Page 5: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

5Profitability Criteria for Project Evaluation

ProfitabilityProfitabilityCriteriaCriteria

DiscountedDiscounted NonNon--DiscountedDiscounted

Non-discounted methods do not consider the time-value of money.

Not recommended for evaluating new, large projects

Page 6: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

6Profitability Criteria for Project Evaluation

NonNon--Discounted Profitability CriteriaDiscounted Profitability Criteria

Time Criterion.

The shorter the PBP, the better.

Payback Period (PBP)

PBP = Time required, after start-up, to recover the fixed capital investment, FCIL, for the project

Page 7: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

7Profitability Criteria for Project Evaluation

NonNon--Discounted Profitability CriteriaDiscounted Profitability Criteria

Cash Criterion.

Cumulative Cash Position (CCP)

CCP = Worth of the project at the end of its life

Cumulative Cash Ratio (CCR)

CCR > 1 implies that the project is potentially profitable.

Cumulative Cash Position (CCP)

CCP = Worth of the project at the end of its life

Cumulative Cash Ratio (CCR)

CCR > 1 implies that the project is potentially profitable.

Page 8: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

8Profitability Criteria for Project Evaluation

NonNon--Discounted Profitability CriteriaDiscounted Profitability Criteria

Interest Rate Criterion.

Rate of Return on Investment (ROROI)

The higher the value of ROROI, the better.

Rate of Return on Investment (ROROI)

The higher the value of ROROI, the better.

Page 9: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

9Profitability Criteria for Project Evaluation

Page 10: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

10Profitability Criteria for Project Evaluation

Page 11: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

11Profitability Criteria for Project Evaluation

Page 12: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

12Profitability Criteria for Project Evaluation

Page 13: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

13Profitability Criteria for Project Evaluation

Page 14: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

14Profitability Criteria for Project Evaluation

Page 15: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

15Profitability Criteria for Project Evaluation

Discounted Profitability CriteriaDiscounted Profitability Criteria

Time CriterionTime Criterion.

The project with the shortest DPBP is the most desirable.

Discounted Payback Period (PBP)

DPBP = Time required, after start-up, to recover the fixed capital investment, FCIL, required for the project with all cash-flows discounted back totime zero.

Page 16: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

16Profitability Criteria for Project Evaluation

NonNon--Discounted Profitability CriteriaDiscounted Profitability Criteria

Cash CriterionCash Criterion.

Net Present Value (NPV)

NPV = Cumulative discounted cash position at the endof the project.

Present Value Ratio (PVR)

PVR > 1 implies that the project is potentially profitable.

Page 17: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

17Profitability Criteria for Project Evaluation

NonNon--Discounted Profitability CriteriaDiscounted Profitability Criteria

Interest Rate Criterion.Interest Rate Criterion.

Discounted Cash Flow Rate of Return (DCFROR)

If DCFROR is higher than the internal discount rate,then the project is considered profitable .

Page 18: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

18Profitability Criteria for Project Evaluation

Page 19: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

19Profitability Criteria for Project Evaluation

Page 20: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

20Profitability Criteria for Project Evaluation

Page 21: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

21Profitability Criteria for Project Evaluation

Page 22: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

22Profitability Criteria for Project Evaluation

Page 23: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

23Profitability Criteria for Project Evaluation

Page 24: 1 Chapter 8 Lecture # 1-3 · 2009. 2. 4. · Overview of Chapter 8 2 Title: Profitability Analysis Topics: • A Typical CFD for Evaluation of a New Project • Profitability Criteria

24Profitability Criteria for Project Evaluation