1 Chapter 13 MRP and ERP. 2 Material requirements planning (MRP): Computer- based information system...
-
Upload
candace-foxall -
Category
Documents
-
view
232 -
download
0
Transcript of 1 Chapter 13 MRP and ERP. 2 Material requirements planning (MRP): Computer- based information system...
1
Chapter 13
MRP and ERP
2
Material requirements planning (MRP): Computer-based information system (i.e. glorified database) for ordering and scheduling of dependent demand inventories
It is a production planning process that starts from the demand for finished products and plans the production step by step of subassemblies and parts.
MRP
3
Independent and Dependent Demand
Independent Demand
A
B(4) C(2)
D(2) E(1) D(3) F(2)
Dependent Demand
Independent demand is uncertain. Dependent demand is certain.
Independent demand: Demand for final products.
Dependent demand: Demand fort items that are subassemblies or component parts to be used in production of finished goods.
4
The book claims that “the independent demand is continuous while the dependent demand is lumpy”. I do not believe in this statement.
Is Dependant Demand lumpier?
Time Time
Time Time
Ind
ep.
Dem
and
Dep
. D
eman
d
Stable demand“Lumpy” demand
Am
ou
nt
on
han
d
Am
ou
nt
on
han
d
Safety stock
5
The dependent demand is not necessarily any lumpier than the independent demand
• Example: Say shoe demand rate is 80 pairs per week at a retailer. The demand rate for shoe sole is 80 for left and 80 for the right pair. The demand rate for shoe laces is 160 per week.
• Example continued: What is the demand rate for the shoe lace supplier? Still 160 per week. But if the orders for the
laces are placed once a week, lace demand is lumpy.
Order once in a week Order twice Order 4 times
Lumpy dependent demand
Smooth dependent demand
6
MRP Inputs MRP Processing MRP Outputs
Masterschedule
Bill ofmaterials
Inventoryrecords
MRP computerprograms
Changes
Order releases
Planned-orderschedules
Exception reports
Planning reports
Performance-controlreports
Inventorytransaction
Primaryreports
Secondaryreports
7
• Master Production Schedule: MPS– Time-phased plan specifying timing and quantity of production for
each end item.– MPS comes from sales and marketing– MPS covers about 1-3 months into the future
• Must cover cumulative lead time
Cumulative lead time: The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly. – From Now until Cumulative lead time plans are generally
frozen• Sometimes MPS is capacity filtered; MPS is curtailed after
taking the available capacity into account.
MRP Inputs: 1. MPS
8
MRP inputs: 2. BOM
Bill of materials (BOM): A listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product.
Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.
Most often people do not use the term product structure tree. Instead use BOM to mean the product structure tree.
9
Product Structure Tree
Chair
Seat
Legs (4) CrossBar(2)
SideRails (2)
Crossbar
BackSupports (3)
LegAssembly
BackAssembly
Level 0
1
2
10
Explosion Example
• How many leg assemblies are needed for 1 chair?
• How many Cross bars are needed for 5 chairs?
• Computing how many parts are required per a final product is called BOM explosion.
• MRP answers these questions by taking production lead times into account: Not only it tells how many, but also when.
11
How many more of each component is needed to make 15 Xs if there are 5 of each already in stock?
X
F(2)E(2)ED(3)
CB(2)
Bill of Materials – Example 1
E(4)
X:10, B:15, C:5, D:40, E: 180, F:5
12
How many more of each component is needed to make 15 Xs if there are 8 of each already in stock?
X
F(2)E(2)ED(3)
CB(2)
Bill of Materials – Example 2
E(4)
X:7, B:6, C:0, D:10, E: 38, F:0
13
Lead Times
1 2 3 4 5 6 7 8 9 10
Procurement
Fabrication
Subassembly
Assembly
14
Assembly Time Chart
1 2 3 4 5 6 7 8 9 10 11
Procurement ofraw material D
Procurement ofraw material F
Procurement ofpart C
Procurement ofpart H
Procurement ofraw material I
Fabricationof part G
Fabricationof part E
Subassembly A
Subassembly B
Final assemblyand inspection
Days
15
MRP input: 3. Inventory levels
• Beginning inventory on hand
• Scheduled receipts – Pipeline inventory not received yet but it is in the
process of coming to the inventory. We know when this will be available for use.
16
MPR Processing
• Gross requirements– Total expected demand
• Scheduled receipts– Open orders scheduled to arrive
• Planned on hand– Expected inventory on hand at the beginning of each time period
• Net requirements– Actual amount needed in each time period
• Planned-order receipts– Quantity expected to received at the beginning of the period
– Offset by lead time
• Planned-order releases– Planned amount to order in each time period
17
MRP Processing
• Gross requirements: (Forecasted)Demand period by period
• Net requirements(t)
=Gross requirements(t)-Projected inventory(t-1)
-Scheduled receipt(t)
• If Net requirement(t) > 0
set Planned order receipts(t)>=Net requirement(t)
• Planned-order receipts is the production planned• Projected inventory(t)
=Projected inventory(t-1)+Scheduled receipt(t)+Planned order receipts(t)-Gross requirements(t)
• Planned order release(t-LT)=Planned-order receipts(t)
18
MRP example with LT=2 and 1 level
Periods 0 1 2 3
Gross requirements 6 11 7
Scheduled receipts 2 3 0
Projected on hand 10 6 0 0
Net requirements 0 2 7
Planned order receipts 2 7
Planned order releases 2 7
Inputs
Outputs
19
Figure 13-8
20
Other Considerations
• Safety Stock– Not much for items with dependent demand
• Lot sizing– Lot-for-lot ordering– Economic order quantity– Fixed-period ordering– Part-period model
21
MRP example with Lot size=5, LT=2 and 1 level
Periods 0 1 2 3
Gross requirements 6 11 9
Scheduled receipts 2 3 0
Projected on hand 10 6 3 4
Net requirements 5 10
Planned order receipts 5 10
Planned order releases 5 10
Inputs
Outputs
22
Figure 13-9
23
MRP updates
• Regenerative MRP– Do the planning from scratch– Time between regenerations is long– Ok for stable environments
• Net Change MRP– Update the plan according to changes
24
MRP Outputs
• Planned orders - schedule indicating the amount and timing of future orders.
• Order releases - Authorization for the execution of planned orders.
• Changes - revisions of due dates or order quantities, or cancellations of orders.
• Performance-control reports
• Planning reports
• Exception reports
25
Capacity Planning
Capacity requirements planning: The process of determining short-range capacity requirements.
Load reports: Department or work center reports that compare known and expected future capacity requirements with projected capacity availability.
Time fences: Series of time intervals during which order changes are allowed or restricted.
26
MRP Planning
Develop a tentativemaster production
schedule
Develop a tentativemaster production
schedule
Use MRP tosimulate material
requirements
Use MRP tosimulate material
requirements
Convert materialrequirements to
resource requirements
Firm up a portionof the MPS
Is shopcapacity
adequate?
Cancapacity be
changed to meetrequirements
Revise tentativemaster production
schedule
Changecapacity
Yes
No
Yes
No
27
• Food catering service– End items are the catered food– Dependent demands are ingredients for
each recipe, i.e. bill of materials• Taco Bell menu items
• Hotel renovation– Activities and materials “exploded” into
component parts
MRP in Services
28
Benefits of MRP
• Low levels of in-process inventories
• Ability to track material requirements
• Ability to evaluate capacity requirements
• Means of allocating production time
Eventually it is a database with limited decision making capability
29
Requirements of MRP
• Computer and necessary software
• Accurate and up-to-date inputs:
– Master schedules
– Bills of materials
– Inventory records
• Integrity of data
30
• Expanded MRP with and emphasis placed on integration
– Financial planning
– Marketing
– Engineering
– Purchasing
– Manufacturing
MRP II
31
MarketDemand
Productionplan
Problems?
Rough-cutcapacity planning
Yes No YesNo
Finance
Marketing
Manufacturing
Adjustproduction plan
Masterproduction schedule
MRP
Capacityplanning
Problems?Requirements
schedules
Ad
just
mas
ter
sch
edu
le
MRP II
32
• Enterprise resource planning (ERP): An expanded effort to integrate standardized record
keeping that will permit information sharing throughout the organization
• Strategic considerations– High initial cost– High cost to maintain– Future upgrades– Training
• See ERP courses in the course catalog
ERP
33
Summary
• MRP:– Dependent vs Independent demand– Inputs (BOM), – Processing, – Outputs– Benefits and requirements
• Capacity planning • MRP-II and ERP
34
Practice Questions
1. The master production schedule states which end items are to be produced both when and how many.
Answer: True Page: 577 2.Load reports show capacity requirements for departments
or work centers which may be more or less than the capacity available in that work center.
Answer: True Page: 5933.MRP II permits the simultaneous planning of production,
marketing, and financial resources to support a production plan.
Answer: True Page: 592
35
Practice Questions
• 1. The output of MRP is: • A) gross requirements • B) net requirements • C) a schedule of requirements for all
parts and end items • D) inventory reorder points • E) economic order quantities and
reorder points • Answer: C Page: 577
36
Practice Questions
2. The MRP input listing the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product is the:
• A) master production schedule • B) bill-of-materials • C) inventory-records • D) assembly-time chart • E) net-requirements chart • Answer: B Page: 578
37
Practice Questions
• 3. Which one of the following most closely describes net material requirements?
• A) gross requirements - amount on-hand - scheduled receipts
• B) gross requirements - planned receipts • C) gross requirements - order releases +
amount on-hand • D) gross requirements - planned order
releases • E) gross requirements - amount on-hand +
planned order releases • Answer: A Page: 581
38
Practice Questions
4.In MRP, "scheduled receipts" are: • A) identical to "planned-order receipts" • B) identical to "planned-order releases" • C) open orders (that is, ordered before the
first time bucket, but not delivered yet) • D) "net requirements" • E) available to promise inventory • Answer: C Page: 582
39
Practice Questions
5. Which is true of a net-change system?
A) It is a batch-type system which is updated periodically.
B) It is usually run at the beginning of each month.
C) The basic production plan is modified to reflect changes as they occur.
D) It is used to authorize the execution of planned orders.
E) It indicates the amount and timing of future changes. • Answer: C Page: 588
40
Chapter 14
Just-In-Time Systems
41
JIT/Lean Production
• Just-in-time: Repetitive production system in which processing and movement of materials and goods occur just as they are needed, usually in small batches
• JIT is characteristic of lean production systems
• JIT operates with very little “fat”
42
JIT Goals
• Eliminate disruptions
• Make system flexible by reduce setup and lead times
• Eliminate waste, especially excess inventory
43
Sources of Waste
• Overproduction
• Waiting time
• Unnecessary transportation
• Processing waste
• Inefficient work methods
• Product defects
44
• Big JIT – broad focus– Vendor relations– Human relations– Technology management– Materials and inventory management
• Little JIT – narrow focus– Scheduling materials– Scheduling services of production
Big vs. Little JIT
45
JIT Building Blocks
• 1. Product design
• 2. Process design
• 3. Personnel/organizationalelements
• 4. Manufacturing planning and control
46
1. Product Design
• Standard parts
• Modular design
• Highly capable production systems
47
2. Process Design
• Small lot sizes
• Setup time reduction
• Manufacturing cells
• Limited work in process
• Quality improvement
• Production flexibility
• Little inventory storage
48
Benefits of Small Lot Sizes
Reduces inventory
Less storage space
Less rework
Problems are more apparent
Increases product flexibility
Easier to balance operations
49
Production Flexibility
• Reduce downtime by reducing changeover time
• Use preventive maintenance to reduce breakdowns
• Cross-train workers to help clear bottlenecks
• Reserve capacity for important customers
50
3. Personnel/Organizational Elements
• Workers as assets
• Cross-trained workers
• Continuous improvement
• Cost accounting
• Leadership/project management
51
4. Manufacturing Planning and Control
• Level loading
• Pull systems
• Visual systems
• Close vendor relationships
• Reduced transaction processing
• Preventive maintenance
52
Pull/Push Systems
• Pull system: System for moving work where a workstation pulls output from the preceding station as needed. (e.g. Kanban)
• Push system: System for moving work where output is pushed to the next station as it is completed
53
Kanban Production Control System
• Kanban: Card or other device that communicates demand for work or materials from the preceding station
• Kanban is the Japanese word meaning “signal” or “visible record”
• Paperless production control system
• Authority to pull, or produce comes from a downstream process.
54
Traditional Supplier Network
BuyerBuyer
SupplierSupplierSupplierSupplierSupplierSupplier SuppilerSuppiler
SupplierSupplier
SupplierSupplier
SupplierSupplier
55
Tiered Supplier Network
SupplierSupplier
SupplierSupplier
SupplierSupplier
SupplierSupplierSupplierSupplier SupplierSupplier
BuyerBuyer
SupplierSupplierFirst Tier Supplier
Second Tier Supplier
Third Tier Supplier
56
Summary JIT Goals and Building Blocks
Product Design
ProcessDesign
PersonnelElements
Manufactur-ing Planning
Eliminate disruptionsMake the system flexible
Reduce setupand lead times
Eliminate wasteMinimize inventories
Abalancedrapid flow
UltimateGoal
SupportingGoals
BuildingBlocks
57
Converting to a JIT System
• Get top management commitment
• Decide which parts need most effort
• Obtain support of workers
• Start by trying to reduce setup times
• Gradually convert operations
• Convert suppliers to JIT
• Prepare for obstacles
58
Obstacles to Conversion
• Management may not be committed
• Workers/management may not be cooperative
• Suppliers may resist
59
JIT in Service
The basic goal of the demand flow technology in the service organization is to provide optimum response to the customer with the highest quality service and lowest possible cost. – Eliminate disruptions– Make system flexible– Reduce setup and lead times– Eliminate waste– Minimize WIP– Simplify the process
60
• New challenges– Meeting manufacturing requirements– Changing from traditional thinking and practices –
frequent on-time delivery of small quantities– Long term relationships with suppliers as
partners
• How about Exchange purchasing: Auctions?
JIT Purchasing
61
• JIT II: the practice of allowing vendors to manage some aspects of buying their products or services for the buyer
JIT II
62
Benefits of JIT Systems
• Reduced inventory levels
• High quality
• Flexibility
• Reduced lead times
• Increased productivity
63
Benefits of JIT Systems (cont’d)
• Increased equipment utilization
• Reduced scrap and rework
• Reduced space requirements
• Pressure for good vendor relationships
• Reduced need for indirect labor
64
• Smooth flow of work (the ultimate goal)• Elimination of waste• Continuous improvement• Eliminating anything that does not add
value• Simple systems that are easy to manage• Use of product layouts to minimize
moving materials and parts• Quality at the source
Elements of JIT
65
• Poka-yoke – fail safe tools and methods
• Preventative maintenance
• Good housekeeping
• Set-up time reduction
• Cross-trained employees
• A pull system
Elements of JIT (cont’d)
66
Case Study based on a trip on Nov 19, 02
NUMMI
67
History/Products
• Late 70’s oil crisis• GM closes Fremont, CA plant firing 6000 in 1982• Toyota approaches GM to set up Toyota production system
at a GM plant, United Auto Workers accepts the deal• GM and Toyota put together $400M in 1984. GM owns the
infrastructure, Toyota is the tenant.• Nummi = New United Motor Manufacturing, Inc is born in
1984 as the unique example of a Toyota – GM joint venture• Products: Toyota Corolla, Tacoma Trucks, Pontiac Vibe
(Toyota bottom, GM top) and Toyota Voltz (Toyota bottom, GM top, sold in Japan) , GM Prism until 13/12/01
68
Workers
• Nummi has about 4500 unionized workers• Workers are under two types:
– Production, high school graduates– Maintenance
• Workers work in teams of 4-6• Workers in a team rotate the tasks every 1-3 hours• Team leader is responsible for the rotation. • Team leader withdraws parts from the inventory (every 1-
2 hours) and provides the tools as necessary • Workers make $17 per hour
69
Capacity
• Nummi has a cycle time of – 60 seconds for Corolla, 1 body– 82 seconds for Tacoma, 3 bodies (only cabin is
produced at Nummi, the bottom and the back are bought from suppliers)
• Nummi works in two shifts– I: 6:00-14:30, II: 16:30-1:00– Each shift has 1 hour lunch/dinner break– Starting the first shift at 6:00 workers avoid heavy
morning traffic– Two hours between shifts I and II is to allow for
overtime after the first shift when necessary
70
Work Flow
• Stamping: Forming metal (side, back, front) panels with presses• Body & Weld: Putting panels together• Paint: Paint inspection is the current bottleneck
– Primer body paint applied by robots (chemically hazardous task)
– Door jambs painted manually• Plastics: Making bumpers, inside panels• Assembly: Putting in tires, engine, seats, bumpers, harnessing.
Cars , trucks on 2 km , 0.8 km conveyors• Cars contain Building manifest = BOM = Ingredients list at every
step of these operations
71
Just in time
• Kaizen: continuous improvement• Kanban: replenishment every 1-2 hours• Jidoka: Assure 100% quality. Otherwise pull the Andon
chord– 1000 times per shift– 9% of line stops are longer than 30 seconds– Line stops longer than an hour once every month
• Muda: Waste to be eliminated• Genchi Genbutsu: Go to the source to learn and to solve
the problems• This Japanese terminology is all over the boards in the
plant
72
Creative Tool / Work Place Design
• Die change at the stamping in 3 hours• Tilted storage bins for ease of access• Collapsing storage boxes when empty
– To reduce the empty box storage requirements in trucks returning to suppliers, say in Indiana
– These boxes save about $10M annually– The worker who suggested the boxes earned several
thousand points. 1 point = $1.
• More info www.nummi.com