1 Budgeting the Project Faculty of Applied Engineering and Urban Planning Civil Engineering...
-
Upload
sara-powell -
Category
Documents
-
view
216 -
download
0
Transcript of 1 Budgeting the Project Faculty of Applied Engineering and Urban Planning Civil Engineering...
11
Budgeting the Project
Faculty of Applied Engineering and Urban Planning
Civil Engineering Department
Lecture 18 + 19
2nd Semester 2008/2009
UP Copyrights 2008
Const
ruct
ion P
roje
ct
Managem
ent
Eng: Eyad Haddad
22
IntroductionIntroduction
Budgets are plans for allocating organizational
resources to project activities. على الشركة مصادر لتوزيع كخطة تعتبر الميزانية
المشروع أنشطة
forecasting required resources, quantities needed,
when needed, and costs , احتياجها وزمن المطلوبة والكميات بالمصادر التنبؤ يتم وفيها
وتكلفتها
Budgets help tie project to overall organizational
objectives.
Budgets can be used as tool by upper management
to monitor and guide projects.
44
1. Top-Down Budgeting1. Top-Down Budgeting
Based on collective judgments and experiences of top
and middle managers.
Overall project cost estimated by estimating costs of
major tasks
Advantages
accuracy of estimating overall budget لتقدير كبيرة لدقة تحتاج ال
العامة الميزانية
errors in funding small tasks need not be
individually identified الصغيرة األنشطة ميزانية تقدير عن الناجمة االخطاء عن بمعزل
55
2. Bottom-Up Budgeting2. Bottom-Up Budgeting
WBS or action plan identifies elemental tasks
Those responsible for executing these tasks estimate
resource requirements
Advantage
more accurate in the detailed tasks.
Disadvantage
risk of fail to consider tasks
66
2. Bottom-Up Budgeting2. Bottom-Up Budgeting
a work statement and set of drawings or specifications
are used to “take off” material quantities required to
perform each discrete task performed in accomplishing a
given operation or producing an equipment component.
From these quantities, direct labor, equipment, and
overhead costs are derived and added.
This technique is used as the level of detail increases as
the project develops.
77
COST ESTIMATINGCOST ESTIMATING
Data collection & normalization:
When estimating, cost data is collected.
Data may be collected from similar projects, data bases, and
published reports.
The basis of the cost data should be documented as part of the
detailed backup for the estimate.
The amount of data collected will depend on the time available to
perform the estimate and the type of estimate, as well as the
budget allocation for the estimate’s preparation.
88
HOW TO ESTIMATE DIRECT COSTS ???
In the initial stages of project development, estimates must be
derived by using various relationships.
As the project develops and more detail is available, the estimate
also will be in more detail.
Following are some general steps that may be used for developing
the direct costs of a detailed estimate.1) Material Takeoff 2) Pricing the Material and Equipment 3) Construction Equipment 4) Labor 5) Special Conditions 6) Government Furnished Material 7) Sampling and Analysis Costs 8) Transportation and Waste Disposal 9) Environmental Management Considerations
99
HOW TO ESTIMATE DIRECT COSTS ???
In the initial stages of project development, estimates must be
derived by using various relationships.
As the project develops and more detail is available, the estimate
also will be in more detail.
Following are some general steps that may be used for developing
the direct costs of a detailed estimate.1) Material Takeoff 2) Pricing the Material and Equipment 3) Construction Equipment 4) Labor 5) Special Conditions 6) Government Furnished Material 7) Sampling and Analysis Costs 8) Transportation and Waste Disposal 9) Environmental Management Considerations
1010
Detailed Estimates MethodologyDetailed Estimates Methodology
After most or all of the detail design work is complete, approximate
estimates are supplemented by detailed estimates
Stage 1: Quantity takeoffMeasurement of material & Labor quantities
Quantities usually recappedتتلخص by trade for control reasons
Stage 2: Direct Cost contributionΣ [Quantity] x [Unit Costs] = Estimated direct cost of
construction
1111
Detailed Estimates MethodologyDetailed Estimates Methodology
Notes on Detailed EstimatesHave differing ranges of uncertainties
Distributions typically asymmetric.
More an art than a science – or bookkeeping الدفاتر مسك لعلم قريبة
Detailed quantitative estimates possible– but ignore important
qualitative factors
Wealth وفرة of trade-specific and method specific.
detail complexity للحسابات المطلوبة بالتفاصيل التعقيد صفة تعطيها
Frequently depends heavily on subcontractor estimatesالفرعي المقاول تقديرات علي كبير بشكل تعتمد
1212
Cost Classification Cost Classification
1. Direct Cost
– Labor Cost
– Material Cost
– Equipment Cost
– Tests Expenses
2. Indirect Cost (“Overhead”)
– Interest on loans
– Trailer rental
– Office costs
– AC/heat
– Planning & logistics
– Supervision
1313
Suggestion table used for estimating your projectSuggestion table used for estimating your project
1414
Overhead CostsOverhead Costs
Project Overhead
Project specific Management staff, Utilities, Supplies, Management
staff, Utilities, Supplies, Engineering, Tests, Drawings, Rents,
Permits, Insurance
– Can and should be estimated directly
– Can be quite uncertain (mgmt sub. quality, time, etc.)
Firm Overhead
– General office Salaries, office rent, utilities, insurance, taxes,
shops/storage yards, other expenses
– Hard to estimate; often use % multiplier
Sometimes distinction unclear
1515
Fair-Cost EstimatesFair-Cost Estimates
Prepared from the actual bid documents provided to the bidders
(before award)
Used by owner’s representative to evaluate changes
(after award)
May use Research Means or other sources
No lump-sum subcontract quotations
Somewhat diff. dis-aggregation than bid
– May be simplified number of line items
– May be more detailed in certain breakdowns (related to
subcontractor work)
Primary basis for measuring job progress, for scheduling and
for cost control.
1616
Contractor’s Bid EstimateContractor’s Bid Estimate
Low enough to obtain the work, yet high enough to make profit
Often relies on
– Historical productivity data for company
– Intuition on speed of movement
– Quantity takeoff for most important items
Sometimes less detailed than fair cost estimates -
subcontractors from 30% to 80% of the project
Is estimating a streamlined process?
– A look at bids received for a typical project in a competitive
area will sometimes show more than 50% difference between
the low and the high bidders
1717
Definitive EstimatesDefinitive Estimates
There comes a time when a definitive estimate can be prepared that
will forecast the final project cost with little margin for error…
This error can be minimized through the proper addition of an
evaluated contingency
Four categories for purposes of reviewing definitive estimates:
– Traditional
– Design-Build
– Professional CM
– Unit-price
1818
Definitive Estimates - TraditionalDefinitive Estimates - Traditional
Lump-sum - definitive estimate = low bidder’s quotation +
evaluated contingency
•Fast track guaranteed maximum price, cost- plus-a-fee
•Definitive estimate will need
– Detailed project and specifications
– Firm material quotations
– Subcontractor quotes
– Prices for major equipment
1919
Definitive Estimates – Design-BuildDefinitive Estimates – Design-Build
Lump-sum, guaranteed maximum price, cost plus-a-fee
• Lump-sum can be misleading to an unknowledgeable owner.
– The cost is known but the facility that is going to be delivered is
unknown
• In guaranteed maximum price and cost plus-a- fee contracts
the definite estimates can be obtained earlier if compared to the
traditional approach because one entity is performing both
design and construction
2020
Definitive Estimates - CMDefinitive Estimates - CM
The definitive estimate can be accurately prepared about the same
time as the guaranteed-maximum or cost maximum or cost- plus-a-
fee option under traditional approach
• Examples show that is possible to develop definitive
estimates after the detailed design is about 95% complete.
2121
Definitive Estimates – Unit PriceDefinitive Estimates – Unit Price
Unit Price Projects:
• Usually heavy construction projects like dams, tunnels,
highways, and airports Prices constants while quantities vary within
limits inherent in the nature of work.
• Quantities may overrun or underrun owing to a number of
potential causes such as additional foundation, excavation to solid
rock, poor ground conditions, etc.
• Without reliable geological information the final cost may not
be known accurately until the end of the
project
2222
Quantity TakeoffQuantity Takeoff
Really requires thinking!
• Systematic identification of quantities of materials
and work required
• Key features sought
– Exhaustive
– Mutually exclusive
• Used to calculate several factors
– Amount of material (e.g. concrete CY)
– Equipment utilization
– Labor
• Breakdown often uses WBS
2323
Labor EstimationLabor Estimation
Most difficult, tricky
• For easy transferability, should separate into - Q: Unit
(Quantity)
– P: $/hour (Labor Price per hour)
– W: hour/unit (Labor hours per unit -- productivity)
• Total cost $ = Q * P * W
2424
Labor Price Estimation (P)Labor Price Estimation (P)
Components
– Wages (varies by area, Law, seniority, …)
– Insurance (varies w/contractor record, work type)
– Social security (insurance)
– Unemployment tax (state)
– Fringe benefits (holiday, retirement, health…)
– Wage premiums(prize)
2525
Wage PremiumsWage Premiums
For shift work
– Sometimes adjust hours
• Overtime
– 1.5-3x for overtime
– Some crafts paid overtime if over 32 hours
• Hazardous/difficult work
– Larger crane
– Underground work
2626
Labor Productivity Estimation (W)Labor Productivity Estimation (W)
Difficult but critical
• High importance of qualitative factors
(environment, morale, fatigue, learning, etc)
• The primary means by which to control labor costs
• Historical data available
– Department of Labor, professional orgs, state govs..)
2727
Productivity ConsiderationsProductivity Considerations
Considerations
• Location of jobsite (local skill base, Law rules)
• Learning curves
• Work schedule (overtime, shift work)
• Weather
– Elaborate work-difficult, costs
• Environment
– Location on jobsite, noise, proximity to matereials
• Management style
• Worksite rules
3030
EstimateEstimate of Project Cost: of Project Cost: Estimate Made at Project StartEstimate Made at Project Start
3131
Three Basic Causes for Change in ProjectsThree Basic Causes for Change in Projects
Errors made by cost estimator about how to achieve tasks.
• New knowledge about the nature of the performance goal or
setting.
• A mandate.
3232
Risk ManagementRisk Management
Risk Management Planning
• Risk Identification
• Qualitative Risk Analysis
• Risk Response Planning
• Risk Monitoring and Control
3333
Failure Mode and Effect Analysis (FMEA)Failure Mode and Effect Analysis (FMEA)
List ways project might fail
• Evaluate severity (S) of each failure
• Estimate likelihood (L) of each failure occurring
• Estimate ability to detect each failure (D)
• Calculate Risk Priority Number (RPN)
• Sort potential failures by their RPNs