BI.STR Stripping Foil exchanger: Controls hardware & spending

Pieter Van Trappen

PVT - TE-ABT-EC 3

Contents

1. Current status

2. Estimated spending1. L4T installation (test stand unit & HST unit)

2. PSB installation (4 units + 2 spare)

PVT - TE-ABT-EC 4

vessel design with control components

mechanical stop

close-up on membrane potentiometers

membrane potentiometer for vacuum

1 – Current status

motor torque tests

resolver readout

microswitch for fail-safe foil-in/foil out status

hardware tests ongoing

PVT - TE-ABT-EC 5

hardware tests ongoing

1 – Current status cont’d

Main hardware ordered and delivered until now on 65739(LIU-PSB - injection stripping foil & absorber blocks E+C):

10 vacuum-approved Honeywell microswitches: CHF 3 300 (8 per unit needed)

10 vacuum-approved flexible membrane potentiometers: CHF 6 175 (2 per unit needed, application-specific design)

motors, resolvers, drivers for testbench: CHF 1 500(now in testbench, to be used in permanent L4T unit)

IRELEC linear actioner: CHF 1 000(1 per unit)

Around CHF 11k together

PVT - TE-ABT-EC 6

2.1 – L4T installation

Test stand unit – permanent

Deadline end of November 2014, E&C bit behind on schedule. Regarding hardware the radiation resistant motor & resolver combo has not been ordered yet, awaiting torque tests results. If not in time delivered the testbench elements can be used

Budget allocation for 2014 (budget code 65739):

Description Estimated amount

PLC and electronics CHF 8 000

Stepping motors, resolvers & decoders CHF 6 000

EN-EL cabling, FSU production, reserve CHF 11 000

TOTAL CHF 25 000

PVT - TE-ABT-EC 7

2.1 – L4T installation

HST unit – temporary

Deadline September 2015 (?), no problems foreseen. After beam tests with the permanent unit we should be able to reach a final PSB design and order the components.

Budget allocation for 2015 (budget code 99232):

Description Estimated amount

PLC and electronics CHF 3 000

Stepping motors, resolvers & decoders CHF 6 000

Microswitches ordered in 2014 CHF 7 000

Potentiometers if modifications necessary CHF 3 000

IRELEC actioner CHF 1 000

EN-EL cabling, FSU production, reserve CHF 10 000

TOTAL CHF 30 000

Year 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

PV 36 24

EV 5

AC 0

New PV

5 30

Metrics per year in kCHF

Description Stripping Foil Controls *

APT wu 130453

Wu responsible [email protected]

Budget code 99232

* Half-sector test

PVT - TE-ABT-EC 9

2.2 – PSB installation

4 final units + 2 spare

Deadline Q1 2017, no problems foreseen.

Budget allocation for 2015-2016 (budget code 65739):

Description Estimated amount

PLC and electronics CHF 12 000

Stepping motors, resolvers & decoders CHF 30 000

Microswitches CHF 25 000

Potentiometers CHF 8 000

IRELEC actioners CHF 5 000

EN-EL cabling, FSU production & installation CHF 20 000

Contingency reserve CHF 25 000

TOTAL CHF 125 000

Year 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

PV 215 138 50

EV 21

AC 10

New PV

25 50 50 25

Metrics per year in kCHF

Description Provide controls for kickers magnets and generators

APT wu 92161

Wu responsible [email protected]

Budget code 65737