PVT - TE-ABT-EC 3
Contents
1. Current status
2. Estimated spending1. L4T installation (test stand unit & HST unit)
2. PSB installation (4 units + 2 spare)
PVT - TE-ABT-EC 4
vessel design with control components
mechanical stop
close-up on membrane potentiometers
membrane potentiometer for vacuum
1 – Current status
motor torque tests
resolver readout
microswitch for fail-safe foil-in/foil out status
hardware tests ongoing
PVT - TE-ABT-EC 5
hardware tests ongoing
1 – Current status cont’d
Main hardware ordered and delivered until now on 65739(LIU-PSB - injection stripping foil & absorber blocks E+C):
10 vacuum-approved Honeywell microswitches: CHF 3 300 (8 per unit needed)
10 vacuum-approved flexible membrane potentiometers: CHF 6 175 (2 per unit needed, application-specific design)
motors, resolvers, drivers for testbench: CHF 1 500(now in testbench, to be used in permanent L4T unit)
IRELEC linear actioner: CHF 1 000(1 per unit)
Around CHF 11k together
PVT - TE-ABT-EC 6
2.1 – L4T installation
Test stand unit – permanent
Deadline end of November 2014, E&C bit behind on schedule. Regarding hardware the radiation resistant motor & resolver combo has not been ordered yet, awaiting torque tests results. If not in time delivered the testbench elements can be used
Budget allocation for 2014 (budget code 65739):
Description Estimated amount
PLC and electronics CHF 8 000
Stepping motors, resolvers & decoders CHF 6 000
EN-EL cabling, FSU production, reserve CHF 11 000
TOTAL CHF 25 000
PVT - TE-ABT-EC 7
2.1 – L4T installation
HST unit – temporary
Deadline September 2015 (?), no problems foreseen. After beam tests with the permanent unit we should be able to reach a final PSB design and order the components.
Budget allocation for 2015 (budget code 99232):
Description Estimated amount
PLC and electronics CHF 3 000
Stepping motors, resolvers & decoders CHF 6 000
Microswitches ordered in 2014 CHF 7 000
Potentiometers if modifications necessary CHF 3 000
IRELEC actioner CHF 1 000
EN-EL cabling, FSU production, reserve CHF 10 000
TOTAL CHF 30 000
Year 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
PV 36 24
EV 5
AC 0
New PV
5 30
Metrics per year in kCHF
Description Stripping Foil Controls *
APT wu 130453
Wu responsible [email protected]
Budget code 99232
* Half-sector test
PVT - TE-ABT-EC 9
2.2 – PSB installation
4 final units + 2 spare
Deadline Q1 2017, no problems foreseen.
Budget allocation for 2015-2016 (budget code 65739):
Description Estimated amount
PLC and electronics CHF 12 000
Stepping motors, resolvers & decoders CHF 30 000
Microswitches CHF 25 000
Potentiometers CHF 8 000
IRELEC actioners CHF 5 000
EN-EL cabling, FSU production & installation CHF 20 000
Contingency reserve CHF 25 000
TOTAL CHF 125 000
Year 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
PV 215 138 50
EV 21
AC 10
New PV
25 50 50 25
Metrics per year in kCHF
Description Provide controls for kickers magnets and generators
APT wu 92161
Wu responsible [email protected]
Budget code 65737