1 Asia Singapore Building and Construction Authority (Building Engineering Division) Managing...
-
Upload
melvyn-cobb -
Category
Documents
-
view
222 -
download
1
Transcript of 1 Asia Singapore Building and Construction Authority (Building Engineering Division) Managing...
1Asia
Singapore Building and Construction AuthoritySingapore Building and Construction Authority(Building Engineering Division)(Building Engineering Division)
Managing Geotechnical Risks – are we learning Managing Geotechnical Risks – are we learning from our failuresfrom our failures
2929thth September 2006 September 2006
Andy Pickles & Tom HendersonAndy Pickles & Tom Henderson
Geotechnical Consulting Group (Asia) Ltd.Geotechnical Consulting Group (Asia) Ltd.
2Asia
ContentsContents
Overview of the management of geotechnical risk Overview of the management of geotechnical risk (Tom Henderson)(Tom Henderson)
Overview of deep excavation practice in Hong Kong Overview of deep excavation practice in Hong Kong (Tom Henderson)(Tom Henderson)
Comment on the scope and reporting of site investigations Comment on the scope and reporting of site investigations (Tom Henderson)(Tom Henderson)
Design aspects for deep excavations and in particular the use of numerical Design aspects for deep excavations and in particular the use of numerical
modelling modelling (Andy Pickles)(Andy Pickles)
Instrumentation to verify design and control during construction of deep Instrumentation to verify design and control during construction of deep
excavations excavations (Andy Pickles)(Andy Pickles)
Miscellaneous lesson learnt from the investigation into Nicoll Highway Miscellaneous lesson learnt from the investigation into Nicoll Highway
collapse collapse (Andy Pickles)(Andy Pickles)
3Asia
Site InvestigationSite Investigation
Site Investigation is a continuous process - Site Investigation is a continuous process - particularly for major projectsparticularly for major projects
must have multiple phases
must be planned and structured
for complete duration of project
must have adequate budget
must be justifiable
4Asia
Site InvestigationSite Investigation
Onus is on geotechnical engineers to demonstrate the Onus is on geotechnical engineers to demonstrate the value of continuity of site investigation to project value of continuity of site investigation to project managersmanagers
Requires stand alone document introduced at inception of project that is updated as project evolves
- relates ground condition uncertainties to elements of design and construction that are particular to project needs - and how these uncertainties will be addressed
Should be driven by ground conditions “Risk Register”
5Asia
Site InvestigationSite Investigation
Principal ObjectivesPrincipal Objectives
provide adequate information for a safe economic
engineering design
provide information to plan most appropriate
method of construction and how to deal with
difficulties anticipated during construction
6Asia
Phases of Site Investigation for Phases of Site Investigation for Management of Geotechnical RiskManagement of Geotechnical Risk
Preliminary ground investigation to compliment feasibility studiesPreliminary ground investigation to compliment feasibility studies
Main ground investigation to provide input to engineering design – and Main ground investigation to provide input to engineering design – and envisaged method of constructionenvisaged method of construction
Allowance for supplementary investigation prior to construction that Allowance for supplementary investigation prior to construction that addresses anomalies/uncertainties arising from the design processaddresses anomalies/uncertainties arising from the design process
Additional investigation during construction (eg instrument installation - Additional investigation during construction (eg instrument installation - the the best site investigation availablebest site investigation available))
Collation and interpretation of as-built conditions (pile installation records, Collation and interpretation of as-built conditions (pile installation records, slope mapping etc)slope mapping etc)
Essential
7Asia
Optimum Cost of Site Investigation for Optimum Cost of Site Investigation for Major ProjectsMajor Projects
8Asia
Costing Site InvestigationCosting Site Investigation
Precedent suggests overall SI costs in Asia rarely exceed 1% of civil construction costs Precedent suggests overall SI costs in Asia rarely exceed 1% of civil construction costs
USNCTT (1984) recommends 3% for tunnel projectsUSNCTT (1984) recommends 3% for tunnel projects
JLE Costs possibly >4% (not directly comparable)JLE Costs possibly >4% (not directly comparable)
LTA NEL Costs recorded as <0.5% (Shirlaw et al, 2002)LTA NEL Costs recorded as <0.5% (Shirlaw et al, 2002)
Hong Kong – major projects – around 1%Hong Kong – major projects – around 1%
Is this total cost – Is this total cost –
does it include contractor’s SI during construction?does it include contractor’s SI during construction?
Does it include for all interpretation?Does it include for all interpretation?
9Asia
Examples of Representative Cost/Value of Site Investigations for Major Examples of Representative Cost/Value of Site Investigations for Major Tunnnelling Projects (Tunnnelling Projects (Westland et al, 1998)Westland et al, 1998)
Lower risk of cost over-run
10Asia
Planning Site Investigations for Major Projects
Balance spatial constraints with engineering requirements
avoid over application of uniform spacing
Consider “clustering” approach
Be realistic with laboratory testing schedules
match the quality of the test with the quality of the sample
ensure there is sufficient information on basic properties to allow adequate interpretation of sophisticated tests
11Asia
Uniform Spacing v “Clustering” for SI
Use closely spaced “clusters” of SI to
obtain continuous samples fully logged profile of ground
calibrate in-situ tests (eg CPTs) with fully logged borehole
obtain high quality samples for full range of laboratory testing
(ie basic indices combined with sophisticated strength tests
BenefitsExtrapolate results to wider spaced in-situ testing and basic lab testing using reliable site specific correlations
This can often be cost effective on large projects
14Asia
JLE - Issues Associated with Lambeth Group Identified at Desk Study
Engineering interpretation was interebedded sands, silts and clays
15 to 25m thick -variable properties
oversimplified and too inconsistent for major tunnelling works
Previous experience indicated a problematic, high risk material for tunnelling and deep excavations
low OCR material and variable K0
significant lateral and vertical lithological variation
localised deposits of cemented material and/or pebble beds
evidence of perched water tables
Geologists had the basis for a well-developed model based on depositional history but no engineering parameters
Project site investigation had to correlate geological model with engineering interpretation to establish reference ground conditions for contract and provide representative parameters for engineering analyses
15Asia
JLE - Actions taken to address risk/uncertainty on Lambeth Group during SI prior to design & construction
Selective high quality site investigationSelective high quality site investigation
Triple tube rotary coring full depth in Lambeth GroupTriple tube rotary coring full depth in Lambeth Group
Large number of samples split and loggedLarge number of samples split and logged
In situ testing involving piezocones/self boring pressuremetersIn situ testing involving piezocones/self boring pressuremeters
Definitive classification of sub-unitsDefinitive classification of sub-unitsDetailed logging of recovered full depth cores Detailed logging of recovered full depth cores
BGS logging of full sequenceBGS logging of full sequence
Logging teach-in for all SI contractorsLogging teach-in for all SI contractors
Laboratory Testing ProgrammeLaboratory Testing ProgrammeLarge number of basic tests for material classification Large number of basic tests for material classification
High quality undisturbed samples for advanced laboratory testingHigh quality undisturbed samples for advanced laboratory testing
Laboratory testing regime to shadow insitu testingLaboratory testing regime to shadow insitu testing
16Asia
JLE - What was achieved in terms of addressing JLE - What was achieved in terms of addressing risk/uncertainty associated with Lambeth Grouprisk/uncertainty associated with Lambeth Group
Information available to Designers and ContractorsInformation available to Designers and Contractors Boreholes logs containing detailed and consistent Boreholes logs containing detailed and consistent descriptions of principal lithologydescriptions of principal lithology
Large volume of measurements of engineering properties Large volume of measurements of engineering properties for each of the sub-unitsfor each of the sub-units
Interpretative Report for permanent and temporary works Interpretative Report for permanent and temporary works designdesign
Engineering InterpretationEngineering InterpretationInfluence of structure and fabric on engineering behaviour Influence of structure and fabric on engineering behaviour highlightedhighlighted
Asia
Axial strain (%)
0 5 10
UU triaxial compression tests on Bothkennar Clay, 6.75-7.1mUU triaxial compression tests on Bothkennar Clay, 6.75-7.1m(Hight, personal com 2006)(Hight, personal com 2006)
0 10 20 30 40
0
10
20
30
Destructuring
conventionalmodified
Tube type
500mm "ELE"
All advanced in borehole
Japanese standardBlock
Sherbrooke
Reduction in p'i
(a-
r)/2
(kP
a)
(’a+’r)/2 (kPa)
15% reduction
Example of the effects of sample disturbance – soft clay
18Asia
Effects of Effects of sampling sampling method in UU method in UU triaxial triaxial compression compression teststestson Upper on Upper Mottled Clay, Mottled Clay, Lambeth Group Lambeth Group (Hight, personal com (Hight, personal com 2004)2004)
Rotary core samples
Driven tube samples
Example of the effects of sample disturbance – stiff clay
19Asia
Reporting/Interpretation of site investigation test dataReporting/Interpretation of site investigation test data
0
100
200
300
400
500
600
700
800
0 100 200 300 400 500 600 700 800 900 1000 1100 1200
s' (kPa)
t (k
Pa
)
Triaxial tests
Best-fit
Design line
20Asia
(-
)/2
ar
( ’+ ’)/2 a r
0
(-
)/2
ar
( ’+ ’)/2 a r
0
(-
)/2
ar
( ’+ ’)/2 a r
0
Stiff Sandy ClaysC = f(w )u
Stiff F issuredplastic C laysC = f(p ’)u 0
Stiff Mediumplastic C laysC = f(w , p ’)u 0
Results of engineering Results of engineering study on Lambeth Group study on Lambeth Group (Hight, personal com 2004)(Hight, personal com 2004)
Results of engineering study on variable stiff clays
21Asia
Inception/Planning
Factual Report
Interpretationand Review of
Data
Interpretative Report – Detailed Ground Model,Ground Parameters andEngineering Implications
Design Recommendations
Design Report
Construction Monitoring,Maintenance and Decommissioning
Validation Report –Geotechnical Structures
Manual
Ground Investigation,Fieldwork and
Laboratory Testing
Desk Study ConceptualGround Model
Guidelines for the preparation of the Ground Report (AGS, 2003)
Form of Geotechnical Reporting
Continuous Review of geotechnical uncertainty/
geotechnical risk register
Ground Investigation,Fieldwork and
Laboratory Testing & Factual Report
22Asia
Site Investigation & Reporting - Summary
Site Investigation is not a one-off exercise on major projects – continuous iterative process
Must be driven by “uncertainty” associated with the ground conditions and how this impacts on design and construction – Risk Register
Should have flexible approach – avoid blanket application
• Reporting should reflect increasing level of knowledge and interpretation