1 Absorption Costing and Activity Based Costing Week 7.
-
Upload
isaiah-monroe -
Category
Documents
-
view
226 -
download
0
Transcript of 1 Absorption Costing and Activity Based Costing Week 7.
![Page 1: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/1.jpg)
1
Absorption Costing and Activity Based Costing
Week 7
![Page 2: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/2.jpg)
2
Methods of Costing The cost of a unit of production = variable
costs Direct Materials Direct Labour (Labour specifically related to the unit) Other Direct Costs Eg patents, royalties Fixed costs (overheads) are covered by
contribution to profit Thereafter each unit made and sold
contributes “pure” profit of Selling price – variable cost
![Page 3: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/3.jpg)
3
Full or Absorption costing Treats overheads as resources
consumed during manufacture Each unit consists of Direct resources consumed (direct
costs) Proportion of Overheads Distinction between Production related overheads Non-production related overheads
![Page 4: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/4.jpg)
4
Allocation of overhead costs
Two stage process Relate overheads to production
departments Allocation Directly ascribing a cost or class of
costs to a distinct department Eg Assembly department
supervisor’s salary Is Allocable overhead of Assembly
department
![Page 5: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/5.jpg)
5
Apportionment Where costs or class of costs cannot be
directly linked to distinct department Need to devise method of apportioning the
cost to all relevant departments Apportionment base must be Related to type of cost Equitable Eg costs of rent Apportionment base could be Floor area Therefore department with greatest use of
space is attributed with greatest proportion of rent costs
![Page 6: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/6.jpg)
6
Methodology Establish production and non-production
departments Allocate costs Establish apportionment bases for other
overheads Apportion costs Gives TOTAL overhead costs for each department ABSORB costs into units of production by
appropriate base Eg labour hours/machine hours Full product unit cost = Direct costs + Absorbed overhead cost
![Page 7: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/7.jpg)
7
Benefits
The benefits of full costing are that:
All the costs are included Duplication of costs can be
avoided Decisions are made with an
awareness of all costs
![Page 8: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/8.jpg)
8
Potential Disbenefits Absorption costing is often crude Particularly if the proportion of
indirect costs in the institution is high in relation to direct costs
The method is simple to administer and easy to understand
May be appropriate when direct costs are of most significance
![Page 9: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/9.jpg)
9
Worked Example
Marmoset Ltd 1. Allocate costs to departments 2. Apportion costs on appropriate
bases Rent – Floor Area Light & Heat – Power Usage Depreciation – Machine Value Insurance – Floor Area
![Page 10: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/10.jpg)
10
Worked Example
Apportionment of Rent Total Floor Area = 2,600 Floor Area of Machining = 1,000 Apportionment = 1,000 / 2,600 X Overhead
(600,000) = 230,769, etc….
![Page 11: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/11.jpg)
11
Worked ExamplePhase 2
Full costs of both Production and Non-Production service
departments Have been established Re-apportionment Service Costs to
Production Departments The FULL OVERHEAD COST of
production depts now known
![Page 12: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/12.jpg)
12
Worked ExamplePhase 2
There needs to be a link between the costs of the production depts and the product
Use Labour Hours (that’s all we’ve got) Calculate Labour Hours for each dept. Machining = 50,000 X 1 + 25,000 X 2 = 100,000 hours Assembly = 50,000 X 1.5 + 25,000 X 2 = 125,000 hours
![Page 13: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/13.jpg)
13
Worked ExamplePhase 2
Calculate OVERHEAD ABSORPTION rate
Machining = Total Overhead / Total labour hours = 967,714 / 100,000 = £9.68 per labour
hour Assembly = 722,286 / 125,000 = £5.78 per labour
hour
![Page 14: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/14.jpg)
14
Worked ExamplePhase 3
For each unit of Gibbon or Baboon made
Absorb proportion of overheads into it in proportion to the number of labour hours worked on it in each department
![Page 15: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/15.jpg)
15
Unit CostsCost Card
Gibbon Baboon
Raw materials
18.00 £15.00
Labour - M £5.80 £11.60
Labour - A £9.75 £13.00
Overhead M
£9.68 £19.36
Overhead A
£8.67 £11.56
Total £51.90 £70.52
![Page 16: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/16.jpg)
16
Activity Based Costing (ABC)
Cost objects consume activities Activities consume resources The consumption of resources
is what DRIVES costs If you can understand the
relationship you can control the costs
![Page 17: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/17.jpg)
17
The steps to ABC
Identify activities Determine costs for each
activity Determine cost drivers Collect activity data Calculate product cost
![Page 18: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/18.jpg)
18
Activity Based CostingWorked Example
Osprey Ltd
![Page 19: 1 Absorption Costing and Activity Based Costing Week 7.](https://reader036.fdocuments.in/reader036/viewer/2022082405/5515dfe0550346d46f8b4c83/html5/thumbnails/19.jpg)
19
Disadvantages of ABC
Needs a lot of work to establish “cost “drivers”
Expensive and time consuming What if cost drivers are wrong? How to deal with (say) Rent? What if product mix changes?