1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided...

13
TRIP REPORT Westinghouse-Sharon NPL Site - Sampling Assessment , Sharon, Mercer County, Pennsylvania July 25, 1995 1.0 INTRODUCTION : _______________ On March 9, 1995, U.S. Environmental Protection Agency (EPA) On-Scene Coordinator (OSC) Gerald Heston requested Resource Applications, Inc. (RAI) 8(a) Technical Assistance Team (TAT) Zone I to prepare a sampling plan and conduct a sampling assessment at the Westinghouse-Sharon NPL site located in Sharon, Mercer County, Pennsylvania. 2.0 BACKGROUND _______________________________' -: "" y : The Westinghouse-Sharon NPL site is located at 469 Sharpsville Avenue in Sharon, Mercer County, Pennsylvania. Industrial areas are located to the north, west and south of the site, and commercial/residential areas are to the east. The Shenango River is less than 1,000 yards to the west. Westinghouse purchased the site in 1922 from Savage Arms Corporation. The site was used by Westinghouse from 1922 until 1985, primarily for the manufacture of transformersand transformer components. Westinghouse utilized a mixture of polychldrinated biphenyl (PCB) oil and 1,2,4-trichlorobenzene as a dielectric fluid in less than 2% of the transformers manufactured at the site between 1936 and 1976. The transformer plant was shut down in 1985. The main manufacturing area was located in the Middle Sector Building. A materials and manufacturing laboratory was operated by Westinghouse until 1991 in the basement of the accounting building. Laboratory operations were kept separate from the accounting offices. . 3.0 SITE ACTIVITIES _______ ,. .___________________ '. An initial assessment of the Middle Sector Building was conducted on March 15, 1995, by OSC Gerald Heston, Remedial Project Manager David Turner andTAT members Lisa Strissel and Bob VanGorder. Pennsylvania Department of Environmental Resources (PADER) representative Chuck Tordella, Westinghouse representatives Sam Messina and John Zuemie and a Westinghouse contractor were also presentfor the initialassessment. This assessment was used to gather information on the current site conditions and to aid in preparation of a sampling . .. ' plan. '.'..- •,- . • • . ' ' ' ' " ' . ' '• '. The sampling assessment occurred the week of June 26, 1995. RPM David .. \ Turner met on site with TAT members Lisa Strissel, Bob VanGorder, Bob ^s * ' ' . - •' 1 4H,iU0882

Transcript of 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided...

Page 1: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

T R I P R E P O R T

Westinghouse-Sharon NPL Site - Sampling Assessment ,Sharon, Mercer County, Pennsylvania July 25, 1995

1.0 INTRODUCTION : _______________

On March 9, 1995, U.S. Environmental Protection Agency (EPA) On-SceneCoordinator (OSC) Gerald Heston requested Resource Applications, Inc. (RAI)8(a) Technical Assistance Team (TAT) Zone I to prepare a sampling plan andconduct a sampling assessment at the Westinghouse-Sharon NPL site located inSharon, Mercer County, Pennsylvania.

2.0 BACKGROUND _______________________________' -:"" y :

The Westinghouse-Sharon NPL site is located at 469 Sharpsville Avenue inSharon, Mercer County, Pennsylvania. Industrial areas are located to the north,west and south of the site, and commercial/residential areas are to the east. TheShenango River is less than 1,000 yards to the west.

Westinghouse purchased the site in 1922 from Savage Arms Corporation. Thesite was used by Westinghouse from 1922 until 1985, primarily for themanufacture of transformers and transformer components. Westinghouse utilizeda mixture of polychldrinated biphenyl (PCB) oil and 1,2,4-trichlorobenzene as adielectric fluid in less than 2% of the transformers manufactured at the sitebetween 1936 and 1976. The transformer plant was shut down in 1985. Themain manufacturing area was located in the Middle Sector Building. A materialsand manufacturing laboratory was operated by Westinghouse until 1991 in thebasement of the accounting building. Laboratory operations were kept separatefrom the accounting offices. .

3.0 SITE ACTIVITIES _______ ,. .___________________

'. An initial assessment of the Middle Sector Building was conducted on March 15,1995, by OSC Gerald Heston, Remedial Project Manager David Turner and TATmembers Lisa Strissel and Bob VanGorder. Pennsylvania Department ofEnvironmental Resources (PADER) representative Chuck Tordella, Westinghouserepresentatives Sam Messina and John Zuemie and a Westinghouse contractorwere also present for the initial assessment. This assessment was used to gatherinformation on the current site conditions and to aid in preparation of a sampling

. .. ' plan. '.'.. - • • , - . • • . • ' ' ' ' " ' . ' ' • ' .

The sampling assessment occurred the week of June 26, 1995. RPM David .. \Turner met on site with TAT members Lisa Strissel, Bob VanGorder, Bob s

* ' • ' . - •'

1 4H,iU0882

Page 2: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

Westinghouse-Sharon NPL Site - Sampling AssessmentSharon, Mercer County, Pennsylvania

McGlade and Sam Baughman at 1115 hours on Monday, June 26, 1995.Westinghouse representative Sam Messina granted access, to the building for thesampling event and two Cummings-Riter (Westinghouse contractor)representatives were present to observe sample collection. TAT members walkedthrough the building and divided the building into 13 sampling areas (see MiddleSector Building Sampling Areas map). The sampling plan had identified twelveareas, however, the I Building had not been included at that time. One sweepand numerous wipe sample locations were tentatively identified within each area.OSC Heston arrived on site at 1645 hours and arrangements were made to meeton site at 0800 hours on June 27 and commence sampling activities.

3.1 Site Conditions' < ' , • - , • • • • _The Middle Sector Building is approximately 1,440 feet by 540 feet, and wasdivided into 13 areas for the purpose of this sampling event. The building isgenerally structurally sound and the majority of the floors are in good condition.There was a notable amount of dust and debris (paint chips, ceiling tile pieces,etc.) on the floors throughout the building. The majority of the floor in Area #13is made up of wooden bricks that have buckled or been removed in many places.. ' • " • - " ' ' . • ' W , " • ' : - ' , " . '

During the March 15,1995 assessment, an excavated area was observed in Area#1 where an underground-storage tank had been removed. The sump pit locatedin Area #8 was filled with approximately two feet of liquid that appeared to bewater; These areas were marked, one with caution tape, the other with a fence,but they were still easily accessible and posed a trip and fall hazard.

3.2 Meteorological Conditions

Weather conditions during the sampling event ranged from overcast to mostlysunny skies with temperature highs in the low S0*s and high humidity. A severethunderstorm, with heavy downpours, passed over the site Tuesday afternoon.Due to deteriorated conditions in some locations of the building (broken windows,cracked pipes), rainwater leaked into the building and pooled in several locations.At least one previously sampled area (Sweep 9) was covered with water followingthe storm.

3.3 Sampling Activities" '' , ' . • •"' , ^' ' • • :

TAT began sample collection at 0830 hours on Tuesday, June 27 and completedsampling at 1600 hours 911 Wednesday, June 28. During the sampling event,TAT collected 55 wipe (including 2 field blanks), one water.and 13 sweep

2 AR.IU0883

Page 3: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

Westinghouse-Sharon NPL Site - Sampling AssessmentSharon, Mercer County, Pennsylvania _________v_______

. . . '•• - • .'.-• . "- -• -., - Osamples. The Westinghouse contractor (Cummings-Riter) representatives wereprovided with split samples for the sweep and wipe samples. They declined splitsamples for the wipe samples receiving dioxin/furan analysis and at first declinedsplits for the water sample, but they eventually accepted splits for TAL, cyanideand VOA analysis. Five of the wipe samples will receive dioxin/furan analysisand 53 will receive PCB analysis. One Meld blank was sent for PCB analysis anda second field blank was sent for dioxin/furan analysis. All of the sweep sampleswill receive PCB lead analysis. The water sample will be analyzed for targetanalyte list (TAL) metals, fCBs, volatile organic compounds (VOCs), totalcyanides, base neutral acid extractables (BNAs) and dioxin/furans.

The wipe sampling was not conducted entirely as outlined in the sampling plan.The plan called for the collection of 5 - 10 wipe samples per area. Thelaboratory was to retain the extract from the wipe samples to conduct dioxin/furananalysis on approximately 10% of the samples. The laboratory that was procuredwas unable to conduct bcth PCB and dioxin/furan analysis from one wipe sample.As a result, the total number of wipe sample locations was reduced and six

\. distinct wipe sample locations were selected for dioxin/furan analysis.

As stated in the sampling plan, this was a biased sampling effort. Samplelocations were chosen based on a visual inspection of the building areas.Obviously stained areas were selected, as well as visually "clean" areas. Allsweep samples were obtained from dust and debris that had collected on the floorof the building. The majority of the wipe samples were also taken from floorlocations due to the prevalence of painted wall surfaces in the high-contact areas(to a height of six feet), All wipe and sweep sample locations were measuredfrom a reference point and documented.

For die wipe sample collection, a sterile 4" x 4" gauze pad was soaked withhexane using a pipette. The pad was wiped over a 100 cm2 area using a standard-size template (10 centimeters by 10 centimeters). The pad was first wiped fromtop to bottom and then turned over and wiped from left to right and put into a 4-ounce glass jar. Four-ounce jars were used in place of 8-ounce jars because theywere available and more practical. "Split" samples were collected adjacent to the.first wipe sample. (As noted in the sampling plain, wipe samples can not be split

. equally, therefore, "splits" for the wipe samples were collected from an adjacentarea.)

Collection of the sweep samples was conducted in Level "C" personal protectiveequipment (full-face air purifying respirator) due to a potential dust hazard.Natural bristle drafting brushes and plastic scoops were used to collect the dustinto 8-ounce glass jars. New brushes and scoops were used for each sample.The sampling plan had indicated that dust pahs would be used, however, it wasdecided they were not necessary and the scoops were then used to transfer dust

\ ^ • ' , - • ' • . •

3 .AR30088U

Page 4: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

Westinghouse^Sharon NPL Site - Sampling AssessmentSharon, Mercer County, Pennsylvania

into the 8-ounce jars. Sufficient quantities of dust were collected to provide splitsat each sweep sample location. The dimensions of each sweep sampling areawere carefully measured and documented (see dimensions table in attachments).

During collection of the water sample from the sump pit, TAT personnel noticedan odor and the appearance of a milky-yellow layer of oil (approximately 1millimeter thick) on top of the clear, yellow-brown layer of water. The water inthe pit was approximately 2-4 feet deep at the time of the sample collection. One64-ounce amber jar was filled with water repeatedly and used to fill the othersample jars. .

All samples were handled and packaged for shipment as stated in the samplingplan. The samples were dropped off for Federal Express delivery to Ecology &Environment in Lancaster, New York, for analysis.

3.4 Air Monitoring .

TAT personnel performed air monitoring during the site visit of March 15, 1995. with a combustible gas indicator, photoionization detector, radiation survey meter,and a flame ionization detector. Monitoring was conducted throughout theinterior of-the Middle Sector Building. No levels above background weredetected. ,

4.0 FUTURE ACTIONS/RECOMMENDATIONS _____

* Analytical results should be received by OSC Gerald Heston in late July 1995.Future actions will be determined by the OSC and RPM based on these results.

ATTACHMENTS: Site location map• '. •' Middle Sector Building sampling areas map

Sample location maps (3)Sample analysis summary tablesDimensions of sweep samples tablePhotos

.VR300885

Page 5: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

LEGEND . Scale 1:15,625 (at center) Westinghouse-Sharon NPL Site .O State Route —;— Major Streelfltoad I innnir~i ' Mag 15.00

T c „,*•' « D 1000 Fed -Hie Aug 2214:58:301995* Town, Small City u> State Route :^ Large City - <=> US Highway 500Metere

US Highway -»-H-H Railroad ' ' f ' \ J. . . . . ^ . i . > . . \ ^ X-- County Boundary ———River

Population Center | | Open WaterStreARoad Contours ' AR300886 -

Page 6: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

(Q

OJ

«3CO01

ffl

oCO

L—J .\HU)088?

Page 7: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

SAMPLE LOCATIONS FOR AREAS 1, 4, 7 & 10 . D - SWEEP SAMPLE LOCAT.ON

. , A * WIPE SAMPLE LOCATION• . '

<J> . - WATER SAMPLE LOCATION

; J

— - -1 ' ' ' ' ' L I I I i - i ,

i l l

i i iefrir

^ B

™n

1 1 1

J 1 1

1 1 1

ACCOUNTING OFFICE

: '' " -i

I I I i isT1S' I UB' U**1 1 1 9V."|Aj/fi'| »

': , 'NORTH OFFICE I

• -

S C A L E

120 0 120 FEET

Page 8: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

SAMPLE LOCATES FOR AREAS 2, 5, 8 &11 Q . SWEEP

, A - WIPE SAMPLE LOCATION

I '•' ' . • ' • • • ' ' " ' . • <& - WATEH SAMPLE LOCATION

22

'

-

••

i14

J '

W2A

Jf '12 'fc"

,,^

/9V"

*i

W20

'i> :

i

'

twse

SWEEPS

:,pk*

WSA

t

. W11A . 'A W11F-

- .' rn

T*: r >

^

$WSA

,v-

;

-,v

i'?"

"•

•' • s

; i— .

-1

• U-^ VwilB -.

*VA n(v-

'•' ' i ; ••' ' "•."•', ''••/'• .">t~"~J'. S C A".",. • . - •'. -.•eHSHSZ

W2B

-

*

i• ' • ' ' ' , 1

ac'H"

W5C

]SW

**,

1 I •ir /V11* /\

L E

1'q

PW1

W8Bw

W2^C4»•

- 1 ,

P 2 i'Jffiv.': ;

1

W^M0 SUMP

-

I, -

f'\' ' '

^ •

h i/'

41

ODGOO

"yo"

-wKu*''cMW11D

. '

33

'•'•

•-'

120 0 120 FEET

Page 9: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

SAMPLE LOCATIONS FOR AREAS 3, 6, 9 & 12D " SWEEP SAMPLE LOCATION

, A - WIPE SAMPLE LOCATION

, -^ - WATER SAMPLE LOCATION

I I I- I j i, W12E

W12B

I I ' . I ISWEEP12D

I I Ml I I I I

oen00o

W9CW9A - A

I- i I ? V .1 I

I I I I I IW12C

S C A L E#3120 0 120 FEET

Page 10: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

SAMPLE ANALYSIS SUMMARY

WIPE,SAMPLE #

W1A

W1B

W1C

W1DW2A

W2B

W2C

W2D

W3A

W3B

W3C

W3D

W3E

W4A

W4B

W4C

W4D

W4E

W5A

W5B

W5C

W5D

W6A

' W6BW6CW6DW6E

APPEARANCE OFWIPE AREA

dry, light oil staindry, cleandry, paintdry, cleandry, paint '

light oil staindry, brickoil stain

dry, cleandry, brick

painted metal machinedry, brickdry, clean

stained cinder blockoil stain

\ dry, cleandry, brickdry, cleandry, clean

dry brick, some paintdry brick, some paint

dry, cleandry, cleandry, paintdry brjcklight staindry, clean

ANALYSIS

P£BX

X

X

XX

X

X

X

X

X

X

X

XX

X

XX

• X

X

X

xX

xsX

X

XX

DIOXIN/FURAN

X

f

x

T

, ' •

I ,

1 i

. . . ' • '

'

\

' • •

ooo

Page 11: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

WIPESAMPLE #

W7A

W7B

W7C

W8A

W8B "

W8C

W9AW9B

W9CW9DW10A

W10B

W10C

W11A

W11B

W.11C

W11D

W11E

W11F

W12A

W1 2B

W12C

W12D

W12E

W13A

W13B

WFB1 (blank)WFB2 (blank)

APPEARANCE OFWIPE AREA

heavy oil stainheavy oil stain

oil stainheavy oil stain

oil staindry, clean

heavy, oil stainoil stainoil staindry, clean , , . .oil stain

dry, cleanoil stain

oil globuleslight oil stainlight oil stainheavy oil stainheavy oil stain

dry, cleandry painted brick

light oil stainlight oil stainlight oil staindry oil staindry, clean

dry, light stainNANA.

ANALYSISPCB

XX

xX

X

X

XX

XXX

X

XX

X

xX

X

XX

XX

X

X

X

XX

DIOXIN/FURAN

i

.

-. -

X

X

X

X

300892

Page 12: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

SWEEPSAMPLE #

SWEEP1

SWEEP2

SWEEPS

SWEEP4

SWEEPS

SWEEPSSWEEP?

SWEEPSSWEEPS

SWEEP10

SWEEP11

SWEEP12

SWEEP13

SAMPLEAPPEARANCE

dry, fine dustdry, fine dust, few paint chips

dry, heavy with paint chipsheavy with paint chips

dry, heavy with paint chipsi dry, fine dust

fine dust, minimal paint chipsdry, heavy with paint chips

dry, a few paint chipsdry, fine dust, few paint chips

fine, sandy-likefine, black dust

fine, some paint & wood chips

ANALYSISPCB

X

L x '•X

XX

X

X

XXX

XxX

LEAD

X

X

xX

xX

/• xX

xxX

xX

WATER SAMPLE #

PW1

/

ANALYSIS

TAL METALS

VOC

TOTAL CYANIDES

BNA

PCBDiQXIN/FURAN

X

x' . ' •.' '•• x

x 'X

': '' X ' .'• - ••'••

.4R300893

Page 13: 1 4H,iU0882 · samples. The Westinghouse contractor (Cummings-Riter) representatives were provided with split samples for the sweep and wipe samples. They declined split samples for

DIMENSIONS OF SWEEP SAMPLES

SAMPLE NUMBER

SWEEP!SWEEP 2SWEEP 3SWEEP 4

SWEEPSSWEEP 6SWEEP 7

SWEEPSSWEEP 9SWEEP 10SWEEP 11SWEEP 12 -

SWEEP 13

DIMENSIONS OFSWEEP AREA

i12'x21'r<11' + 11'3")/2x 15'<7'7" + 8'8")/2x16'5"

6'x25'6"(5' + 4')/2x 19'8"

7'x 16'

11'2"x8'9'6"x8'8"5'8"x5'10"11'6"x7'9"4'6"x4'8"10'x7'3"

•'6'10"x. 13'4":

AREA (m2)

23.504515.503212.391914.21428.2219

10.40528.2994

7.64903.07098 787 ; . •_ '

. 1.95096.73558.4645