081126 Report AIDECO Version

download 081126 Report AIDECO Version

of 43

Transcript of 081126 Report AIDECO Version

  • 8/2/2019 081126 Report AIDECO Version

    1/43

    ENGINEERS WITHOUT BORDERS

    Imi NTizghte

    Agricultural project irrigation and boar fences

    Stephen Ollier and Clare Wilding

    1/1/2008

    December 2008

  • 8/2/2019 081126 Report AIDECO Version

    2/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    2

    Contents1.0 Introduction ...................................................................................................................................... 4

    2.0 Lifestyle and Agriculture in Anbdour and Imi NTizghte ................................................................... 5

    3.0 Soil testing ............................................................................................................................................... 8

    3.1 Introduction to soil surveys ................................................................................................................ 8

    3.2 Factors affecting Soil Fertility, Erosion and Desertification ................................................................ 8

    3.3 Methodology Used ............................................................................................................................ 10

    3.4 Results Obtained ............................................................................................................................... 11

    3.5 Analysis of Results and Recommendations ...................................................................................... 11

    4.0 Irrigation System ................................................................................................................................... 13

    4.1 Indroduction ..................................................................................................................................... 13

    4.2 Khettara ............................................................................................................................................ 144.2.1 History ........................................................................................................................................ 14

    4.2.2 Existing Khettara in Imi NTizghte .............................................................................................. 15

    4.2.3 Problems with Khettara 1 .......................................................................................................... 16

    4.2.4 Khettara Remediation Options .................................................................................................. 17

    4.2.6 Recommendation ....................................................................................................................... 18

    4.3 Seguia and Water Tanks .................................................................................................................... 19

    4.3.1 Existing Infrastructure ................................................................................................................ 19

    4.3.2 Problems with existing Infrastructure ....................................................................................... 20

    4.3.3 Remediation Options ................................................................................................................. 21

    4.3.4 Costs ........................................................................................................................................... 22

    4.3.5 Recommendations ..................................................................................................................... 22

    4.4 Clothes washing area ........................................................................................................................ 22

    4.4.1 Existing usage and problems ...................................................................................................... 22

    4.4.2 Remediation options .................................................................................................................. 23

    4.4.3 Costs ........................................................................................................................................... 24

    4.4.4 Recommendations ..................................................................................................................... 24

    4.5 Earth Channels (Earth Seguia) ........................................................................................................... 24

    4.5.1 Existing Infrastructure and the problems .................................................................................. 24

    4.5.2 Problems with existing infrastructure........................................................................................ 25

    4.5.3 Options for re-lining channels .................................................................................................... 25

  • 8/2/2019 081126 Report AIDECO Version

    3/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    3

    4.5.4 Recommendations ..................................................................................................................... 26

    4.6 Field Application ............................................................................................................................... 27

    4.6.1 Existing Operation Strategy ....................................................................................................... 27

    4.6.2 Crop requirements and Irrigation Efficiency .............................................................................. 27

    4.6.3 What is the potential?................................................................................................................ 28

    4.6.4 A note on Drip by Drip irrigation ................................................................................................ 28

    4.6.5 Summary table, costs and Recommendations........................................................................... 29

    5.0 Boar Fence ...................................................................................................................................... 30

    5.1 Introduction ...................................................................................................................................... 30

    5.2 Initial design considerations and materials ...................................................................................... 31

    6.0 Crops ..................................................................................................................................................... 38

    Different crop typesa critique with respect to Imi nTizghte .............................................................. 38

    6.1 Existing Crops .................................................................................................................................... 38

    6.2 New crops ......................................................................................................................................... 38

    6.3 Future outlook .................................................................................................................................. 40

    7.0 Final Recommendations........................................................................................................................ 41

    8.0 Project 2009EWB in Imi nTizghte ..................................................................................................... 42

    References .................................................................................................................................................. 43

    Appendix A: Leaflet, invitation and poster .....................................................................................................

    Appendix B: Crops questionnaire and results .................................................................................................

    Appendix C: DPA fiche techniques ..............................................................................................................

    Appendix D: Soil test results ...........................................................................................................................

    Appendix E: Calculations .................................................................................................................................

    E1 Flow calcs ............................................................................................................................................

    E2 Flow losses ..........................................................................................................................................

    E3 Crop Requirements .............................................................................................................................

    Appendix F: Drawings .....................................................................................................................................

    Appendix G: Bill of Quantities .........................................................................................................................

  • 8/2/2019 081126 Report AIDECO Version

    4/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    4

    Figure 1.1: View of Imi nTizghte

    1.0IntroductionA project has been established by Engineers Without Borders with a local NGO, AIDECO, in the

    mountainous Ammeln Valley region of Morocco. EWB provided AIDECO with a source of free

    engineering consultancy to progress design work on agricultural infrastructure in the village of IminTizghte. AIDECO is likely to be able to source funding to pay for the post design construction costs but

    would have been unable to pay for a comprehensive design to be carried out.

    The overall goal of the EWB project was to increase agricultural productivity, and thus economic

    stability, in Anbdour and Imi nTizghte. One indicator for success would be for the farmers to be less

    affected by price fluctuations and to have a more steady income. What was found in the village was that

    the majority of the farming is subsistence and many people rely on money sent from relatives living in

    the cities for their income. The goal has therefore been extended to have less reliance on money sent

    from cities/abroad and to stem the movement of people to the cities by providing better opportunities

    in agriculture in the village.

    Another goal is to suggest ways for slowing and preventing mass soil erosion and eventual

    desertification in the valley. It is clear to see when travelling through the region that many areas of land

    which used to be cultivated are now abandoned, leaving a bare and extremely vulnerable soil behind.

    This is generally due to lack of water (drought), and possibly lack of labour or inadequate boar

    protection. In these areas, mass erosion and desertification are inevitable in this arid/semi-arid climate.

  • 8/2/2019 081126 Report AIDECO Version

    5/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    5

    2.0 Lifestyle and Agriculture in Anbdour and Imi NTizghteImi nTizghte is a small Berber village in the Ammeln valley with a population of about 320. The local

    language is Teshleheet and most people also speak Moroccan Arabic. Some more educated people also

    speak French. There is mixed primary school in the village. The secondary school and college are inTafraout 10km away and now that there is school transport provided, the girls are able to get there as

    well as the boys who used to cycle or catch a lift. This is only a recent change so there are girls in their

    twenties who only had primary school education. Most women over the age of about 35 didnt have any

    schooling and are illiterate.

    The traditional houses are built with stone and earth based mortar however they require yearly

    maintenance and many are now in ruins. Newer construction is normally in concrete blocks which are

    often rendered and painted, though some are not. The village has mains electricity and a piped drinking

    water supply which comes from the same source as the irrigation water and is occasionally treated.

    There is also a water supply from ONEP (Office National dEau Potable) but this is expensive and only acouple of houses are connected to this.

    Out of 17 households questioned, two had washing machines. Most people use the communal clothes

    washing area though some do it at home particularly if they live a long way from the wash area. An

    average family uses the wash area 2 to 3 times a week. Some of the girls find that the position washing

    on the concrete floor gives them back ache and would prefer sinks, others are happy with the set up but

    say that the surface is too rough and sometimes rips the clothes.

    There is no municipal waste collection and so all households are forced to burn their rubbish and the

    majority of people use the dry river bed for this. This is a poor environmental solution and is

    aesthetically very unpleasing particularly in view of the fact that the association would like to increase

    tourism. A future project for the Association in collaboration with a Peace Corps volunteer is to set up a

    waste collection service providing communal bins and someone to collect the rubbish. Of those

    questioned on this they all thought it was a great idea but it will be interesting to see whether people

    will actually be prepared to pay for this service. It is hoped that some materials can be separated for

    recycling.

    Many of the younger generation move to the big cities to work (generally Casablanca), often in family

    run shops, or because of marriage. This means that there are less people to work on the land and some

    fields are abandoned. Also for those families receiving money from family in the cities there is less

    incentive to invest in the land and use it to its full potential. There are currently two family run shops inthe village. There is at least one person employed at a local hotel and two families with edukan

    (traditional shoes) shops in Tafraout. Other than this there is little employment opportunity.

    There is a womens Co-operative about 12 strong who produce Argan oil. There is also a group of about

    10 girls in their twenties and thirties who use the AIDECO building to make crafts. They also receive

    French and English lessons.

  • 8/2/2019 081126 Report AIDECO Version

    6/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    6

    Figure 2.1: Freshly ploughed parcels

    Figure 2.2: Local fruit trees

    Figure 2.3: Parcels sprouting wheat

    Agriculture here is not done on a large scale. Most families own a

    few plots of land and these are often shared with extended family.

    Up to five households might share land and trees. The plot sizes

    are on average 5m x 10m and often a families land is scattered in

    many areas. It is mostly the women who work in the fields and all

    the work is manual or with donkeys. There is no machinery as even

    if it was economically viable it would not suit the small terraced

    plots

    A lot of the land is covered in trees, the most common being

    Argan, Almond, Olive and Date with a few Carob and the

    occasional Pomigranite. The majority of the produce is kept for

    personal use. Even if a large quantity of Argan oil is produced, any

    surplus is usually given as presents to visiting relatives rather than

    being sold. Last year the harvest was particularly bad because of

    the drought, some trees produced no fruit at all and some evendied. So far in 2008, rainfall has been higher than usual so a better

    harvest is hoped for in 2009.

    From the information gathered from the questionnaire the only products sold are Carob pods and the

    bitter Almonds (edible ones are kept). These can both be sold in Tafraout to someone who then sells on

    to factories in Agadir. Carob is sold for 7DH/kg and Almonds for 35DH/kg. Of 17 families asked only two

    sell Almonds and, although anyone who has a Carob tree does sell the pods, there were only 4 families

    with any trees and a total of only 6 trees amongst these families.

    Any crops grown are only for personal consumption. The main one

    is wheat and this is something the boars do not eat. This year it

    was sown in November after the fields had been ploughed with

    donkeys. Some other vegetables are grown but this has diminished

    a lot because the boars eat them. The main vegetables that are still

    grown are squash, 50% of families questioned continue to grow

    them. A very few people also grow onions, tomatoes, potatoes and

    other root vegetables. In the past there was a market in the village

    where people sold their vegetables. Now most people dont even grow enough for themselves and go to

    Tafraout to buy them. The general opinion of people we spoke to was that they would like to be able to

    grow their own vegetables again to save money.

    On Sunday 23rd October 2008 a presentation was given to the people of Imi NTizghte to present the

    work carried out during the EWB project.

  • 8/2/2019 081126 Report AIDECO Version

    7/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    7

    Figure 2.6: Presentation of work

    Figure 2.4: EWB and AIDECO meeting

    Figure 2.5: The survey team

  • 8/2/2019 081126 Report AIDECO Version

    8/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    8

    3.0 Soil testing

    3.1 Introduction to soil surveys

    A soil survey was necessary to gain an understanding of the nature of the ground in Imi nTizghte. This

    exercise was carried out in order to asses the state of the existing soil and determine its fertility,

    suitability to existing/recommended crops and whether desertification and soil erosion are a real

    concern. As with most aspects of the project, one of the main aims is to try and establish a baseline

    against which future studies can be compared. Since the soil type does not really vary across the site

    (apart from the topsoil, which will vary slightly based on crop type, etc) a soil map has not been

    produced.

    3.2 Factors affecting Soil Fertility, Erosion and Desertification

    Soil Fertility

    There are many factors which affect soil fertility, and different plant species thrive in different

    conditions. The primary factors are listed below with a short text highlighting the indicators;

    Aeration - Good free movement of air is essential for a healthy soil (see free drainage).

    Moisture content - Should be adequate and balanced. Affects size and texture of soil particles.

    Organic content - Relates to moisture content, high organic content gives a fertile soil.

    Temperature - Increased temperatures (within threshold

  • 8/2/2019 081126 Report AIDECO Version

    9/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    9

    Soil Erosion

    As a general rule, the topsoil is the most fertile part of the soil and simultaneously the most vulnerable.

    Simply put, a decrease in vegetation cover, and hence organic content, leads to an increase in soil

    erosion. Organic matter fertilizes the soil by binding particles, increasing microbial activity and promotes

    permeability and infiltration capacity. The loss of vegetation cover can turn an arid region into desert in

    just 10 years! Note an arid region is classified as an area with annual rainfall < 250mm/year. Imi

    nTizghte receives 170mm/year and hence is classed as arid. Figure 3.1 shows that Imi nTizghte is right

    on the boundary of Hyperacid andDrylands classification (Hyper arid regions receive less than 100mm

    of rainfall annually).

    Conservation techniques, in principle, are implemented to ensure that the erosion rate equals the rate

    of new soil formation. The main aims are to protect the soil from raindrop erosion, increase infiltration

    capacity (minimising run-off) and increase ground roughness (retard wind and water erosive forces).

    Methods for achieving this include;

    Terracing; to reduce effective slope angle and length.Planting crops; provides necessary protection

    Contour farming; reduces run-off and promotes soil moisture conservation.

    Crop rotation; in 4/5 year cycles. Helps retain moisture by utlising soil retaining crops e.g.

    Alfalfa, control pests by eliminating abnormal molds/blights/viruses, control erosion, increase

    soil nutrients, and improve soil structure.

    Fallow periods; allows the soil to conserve moisture (land must be mulched, tilled and weeded

    carefully) and in arid regions can be recommended up to every other year.

    Mulching; disturbs capillary action to conserve water and provides soil nutrients to promote

    repair after harvest (0.5kg/m2 provides enough cover to protect from wind erosion also). Also

    reduces wind and run-off erosion and increases soil surface permeability.Afforestation; increases soil permeability and provides wind and raindrop shelter.

    Gullies; to provide run-off with a designated route. Can be grassed, impermeable, etc.

    Many of these techniques work by reducing moisture loss from the soil. Another method of doing this is

    humid culture where plants are grown in a poly-tunnel. Water is initially provided by irrigation and then

    because it is recycled it does not need to be replaced for a few weeks. (1)

    Desertification

    Defined as the environmental degradation in arid and semi arid

    lands causing a critical decrease in the productive capacity of the

    soil. Deserts expand and contract naturally over time, the

    problem comes when human activity generates unsustainable

    demands on already fragile soils ecosystems. The three main

    causes are overgrazing, over farming and poor water

    management, all of which can lead to desertification of arid and

    semi arid lands within 5 10 years!Figure 3.2: Desertification approaches

  • 8/2/2019 081126 Report AIDECO Version

    10/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    10

    Figure 3.5: Cohesion and

    plasticity test

    Figure 3.4: Basic soil grading

    Desertification can be permanent if there is no capital or resources invested. It is without doubt far

    cheaper and easier to invest initially in measures to avoid desertification in the first place! Poor

    communities may abandon areas once the soil is, in effect, destroyed.

    The cause and effects of desertification come hand in hand. Lack

    of vegetation, organic matter and moisture leads to soil removalwhich decreases fertility and increases wind erosion. The process

    of desertification is difficult to recognise in the field, it is a kind of

    creeping disaster. Therefore, effective monitoring is key, this

    can be through annual agricultural surveys (production, etc) and

    aerial photos.

    3.3 Methodology Used

    Four sets of tests were undertaken on site, these were soil description, classification, 1-D permeability

    and home mineral testing. Samples were also sent to INRA for further testing.

    Soil Description

    Every soil has its own unique properties and qualities, a soil description is a

    qualitative method of explaining the details of a particular soil. The testing

    should also include a shear strength test (Standard Cone Penetration Test).

    Also useful is the general geography, land use and historical land use if

    known. The data is useful in design for estimating bearing pressures, etc. For

    this test, the topsoil was removed (top 200mm or so). (2)

    Soil ClassificationThis system involves the testing of samples and classifying the soil based on a

    list a categories including properties such as particle size and plasticity. For

    example, a gravelly silt with little plasticity and a liquid limit of 50%. This data

    is useful when using soils as part of a stability design, earth embankments for

    example. Again the geography, land use and historical land use is useful and

    the topsoil is removed for testing.

    Permeability Tests

    Permeability coefficient, k, is defined as the as the quantity of unit flow through unit area of soil under a

    unit pressure gradient. This is the basis of Darcys L aw. Here, we have only conducted an on site test as

    specified by Engineering in Emergencies (3). The macrostructure of soils have a large influence on

    permeability, the lack of these features in small laboratory test samples make it difficult to obtain true

    values. A field test has its own problems, but in this case it was deemed more appropriate. Simply, a

    100mm diameter cylinder (large tin can) was driven into the soil, the top section was filled with water

    and the rate at which the water level dropped was recorded over a 60 minute period. Generally the

    initial infiltration rate is high and then, as the soil approaches saturation, the rate levels off, it is this rate

    that we are most interested in (in m/s).

    Figure 3.3: Desertification complete

  • 8/2/2019 081126 Report AIDECO Version

    11/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    11

    Figure 3.6: pH testing

    Mineral Testing

    A home tester kit was used to measure pH and nutrient levels. The nutrient

    levels are interpreted through levels of Potassium, Nitrates and

    Phosphorous. The aim is to gather information on the general quality and

    fertility of the soil. It is important to note that nutrient levels vary

    significantly throughout the year, depending on the type of crops, the

    harvest, the season and application of fertilizer.

    3.4 Results Obtained

    The site owners, Soltana and Hassin Sain, agreed for their plot to be surveyed 24th September, this was

    after the summer harvest so mainly only grass was growing. A flat parcel at the base of the valley, the

    plot receives lots of sunlight and irrigation water from the khettara via the earth seguia network. Trees

    on the northern edge shade a portion of the plot whilst providing wind protection. The plot had

    corn/maize, marrow, mint and grass (for feeding their 5 goats) and carrots. They use fertilizer (cow

    manure) every February, also if they plant new crops.

    Soil Description

    The fines area a brown uncompacted silt. The particles are fine to coarse silt with some clay and sand

    particles with frequent fine to coarse gravel. The gravel is angular, possibly Gneiss. The Topsoil is

    frequent organic matter. Shear strength was estimated as SPT = 10 (ground is difficult to dig due to

    gravel).

    Soil Classification

    Gravelly SILT (approx 40% fines) with low to intermediate plasticity. The sample showed some cohesion

    and a little plasticity. Liquid Limit (LL) estimated at approx 40% (category silt with some clay).

    Permeability

    A rate of 24mm/hour was taken (varying from 24 to 39mm/hour). A typical sandy loam has a rate of

    25mm/hr and a silt loam up to 20mm/hr. Considering the fissures and gravel in the soil, this seems like a

    reasonable result. According to Cassagrand and Farram (1940) (4) 24mm/hr (6.7x10 -6m/sec) represents

    a low permeability soil with good drainage conditions or a fissured clay modified by the effects of

    vegetation.

    Results of home testing

    The pH result was 7.5 (slightly alkaline). Nitrates levels low/medium to low and Phosphorous levels are

    low.

    3.5 Analysis of Results and Recommendations

    This plot is well looked after, receiving plenty of irrigation water and sunlight. The area is sheltered from

    wind and the plot is flat which help to minimize soil erosion and facilitate moisture retention. The

    permeability is reasonable also, that value will be more useful later on in the earth seguia chapter. The

    low nutrients and slightly high pH are most probably due to the recent harvest and lack of fertilizer. This

  • 8/2/2019 081126 Report AIDECO Version

    12/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    12

    plot is exemplorary for others, it also has a functioning boar fence which allows the user to plant root

    vegetables, etc which the boar would otherwise eat.

    Recommendations

    It is recommended that an annual land use survey is undertaken every year to keep check on

    deteriorating or abandoned parcels. All abandoned parcels should be planted with dryland crops toreduce the risk of crop failure and soil deterioration. For example prickly pears survive and fruit without

    irrigation water and provide a valuable crop. It is also recommended that some food waste and plant

    waste is placed back on the land rather than being fed to the animals, thus increasing organic content

    and fertility. The notes given above on increasing fertility and reducing erosion/desertification should

    also be considered.

  • 8/2/2019 081126 Report AIDECO Version

    13/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    13

    Table 4.1: Water flow test results

    Table 4.2: Summary of flow losses

    4.0 Irrigation System

    4.1 Introduction

    There are two concrete water collection tanks in the village which fill up overnight and are used to

    distribute water to the fields during the day. The water source is an underground spring higher up in the

    valley. Flow from the source is collected and reaches the tanks via approximately 300 metres of

    underground channels (khettara) and then an open channel for 900m (seguia). From these tanks the

    water is distributed to the fields via open earth channels and applied to the crops using flood irrigation.

    The total flow arriving at the tank was estimated using several methods and the results are summarised

    in Table 4.1 below, see appendix E1 for calculations.

    Method Flow rate l/s

    Measurement of seguia velocity 2.5

    Depth of pipe flow (150mm UPVC) 3.5

    Mannings equation (5) 4.0

    Tank volume 3.3

    50mm pipes at full bore 3.4

    Average 3.34

    One of the main aims of the project is to increase the flow in the irrigation system or, more importantly,

    the amount of flow reaching the parcels. It is difficult to increase the amount of flow ebbing from the

    springs, therefore the key to increasing water flow is understanding and pinpointing the main losses in

    the system and reducing them. There are three main areas where water is lost; the khettara, the

    concrete seguia and the earth channels. For each of these three elements, evaporation and infiltrationlosses were calculated. Table 4.2 below summarises the results and the calculations can be found in

    appendix E2.

    Element Losses (l/s) Losses (m3/day)

    Evaporation Infiltration Total Evaporation Infiltration Total

    Khettara 0 0.5 0.5 0 43.2 43.2

    Seguia 0.017 0 0.017 1.35 0 1.35

    Earth channels 0.018 0.6 0.618 1.5 52 53.5Total 0.035 1.1 1.135 2.85 95.2 98.05

    The calculations of losses have been based on evaporation and infiltration rates measured on site. The

    losses in the earth seguia are based on 300m of channel, this was chosen as an average distance of

    each parcel from the supply tanks.

  • 8/2/2019 081126 Report AIDECO Version

    14/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    14

    4.2 Khettara

    4.2.1 History

    Khettara, or qanats, are underground tunnels that tap the groundwater and lead the water artificially to

    a human settlement and agricultural lands using gravity flow conditions. The tunnels can be many

    kilometres long and very deep. The longest qanatis more than 40 km long and 100m deep and can befound in Iran. In general a qanat system consists of an underground part and a part above ground

    surface. The underground part is divided into the "water production section" and the "water transport

    section". In the "water production section", the water is collected, either from a natural source or

    infiltration of groundwater. This section is underneath the groundwater level of the surrounding area.

    The "water transport section" transports the water to the surface. This section is usually lined on the

    sides to prevent leakage of water. The gradient of the tunnel is very precise and should not exceed 5 %

    in order not to let the flow erode the rock or sand in which the tunnel is dug. On the other hand, the

    gradient should not be too low because then the water can not be transported to the surface as self

    cleaning velocity is not achieved. The technique is similar to mining and originates from Old Persia

    (present day Iran) around 3000 years ago. (6)

    Figure 4.1: Khettara/qanat typical

    Figure 4.2: Khettara/qanat typical

  • 8/2/2019 081126 Report AIDECO Version

    15/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    15

    4.2.2 Existing Khettara in Imi NTizghte

    The system here uses three different underground springs. The mothershafts are 3m, 3.5m and 6m

    deep, each being sited to collect water from the individual underground springs. Each spring is created

    by water percolating through the earth and bedrock higher up in the mountains. The groundwatercontinues under gravity down the valley and eventually passes over a shallow section of impermeable

    bedrock where the motherwell picks up the flow. Further investigation is required to confirm this which

    would be difficult, expensive and at this point unnecessary.

    There are two khettara in Imi nTizghte, both of which were built in the 1940/50s by the French. Figure

    4.3 below shows the layout. The khettara from source 2 was originally built with 12km of pipe to supply

    Tafraout with drinking water. This pipe was destroyed sometime afterwards by the villagers so they

    could have retain all the water that they felt was rightfully theirs.

    Key

    River (Asif)

    Khettara 1 (poor condition)

    Khettara 2 (UPVC/Dimatit)

    Barrage (sub river concrete dam

    Seguia (300x300 concrete channel)

    Manholes

    Figure 4.3: Existing Khettara layout (See drawing 2011 in appendix F)

    SOURCE 1

    (6m)

    SOURCE 2

    (3.5m)

    SOURCE 3

    (3m - TBC)

    SEGUIA

    FLOW

    RIVER

  • 8/2/2019 081126 Report AIDECO Version

    16/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    16

    Figure 4.4: Khettara 1 (MH11)

    Figure 4.5: Khettara 2 (source)

    Khettara 1

    Khettara 1 is a stone lined channel approximately 400mm wide by

    900mm high with a gravel and sediment invert. Six years ago, two 75mm

    MDPE pipes of approximately 2l/s capacity each were added in the base

    of this khettara between MH11 and the seguia to try to increase water

    flow. We believe this had an initial impact of increasing flows to approx

    3l/s because the total flow from both sources was measured as 6l/s

    according to a local engineer in 2001. Today, based on a visual inspection

    of the flow at MH06 (manhole 6, see drawing 2011), only one of the

    pipes has a significant amount of flow, approx 0.4l/s (just less than half

    bore). The khettara runs beneath a river which only flows as a seasonal

    torrent during the rare periods of heavy rainfall in the area. During this

    time water percolates through the khettara walls and into the channel

    temporarily increasing flow. A dam running perpendicular to the river

    flow also traps flow and directs it into the khettara. This dam is

    supposedly broken, we were unable to confirm.

    Khettara 2

    Khettara 2 is a stone lined channel for the first 20m, it then becomes

    simply a buried Dimatit pipeline. Most of the flow in the seguia comes

    from this khettara, running at approximately 3l/s. In the 1980s the lower

    section of Dimatit was replaced with UPVC. This khettara runs beneath a

    smaller river at its upper section. Generally this khettara is in good

    condition and will not be considered for renovation as part of this study.

    4.2.3 Problems with Khettara 1Consider the khettara as having an upper section and a lower section. The lower section has 2No 75mm

    MDPE pipes running along the invert, whereas the upper section is as originally constructed with stone

    walls and gravel/sediment invert. The problem with the upper section is that the channel is unlined for

    approximately 180m, therefore the infiltration losses are considerable (estimated at 0.5l/s equivalent).

    The walls and roof have also deteriorated over time, leaving stones, rocks and debris in the channel

    invert which, when not cleared, restrict water flow. To get past these obstacles the flow depth increases

    which allows further water to escape through the khettara walls. The upper section has not been

    cleaned since the 1980s.

    The lower section has two main problems. Firstly the 75mm MDPE pipes have blocked over the last 7

    years restricting the amount of flow able to pass down them, this is due to the low flow and lowgradient meaning self cleansing velocities are not achieved. Secondly, the original invert has not been

    cleaned often enough, meaning that when flow percolates through the khettara walls it is quickly lost

    through the invert due to infiltration as it cannot pass through the blocked channel.

  • 8/2/2019 081126 Report AIDECO Version

    17/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    17

    Figure 4.6: Khettara 1 section

    Table 4.3: Khettara remediation Options

    4.2.4 Khettara Remediation Options

    The main aim of the remediation options are:

    - Reduce/remove infiltration losses i.e. all flow gathered at source reaches seguia

    - Stop the pipes and khettara silting up and blocking with stones and rocks.

    - Retain permeable walls to allow for continued infiltration along the khettara length

    All 4 options below include the new silt traps to be built at selected manholes (MH06 and MH11, see

    drawing 2011), this will prevent the MDPE pipes silting up and ensure the silt gathers in a manholewhich can be accessed easily.

    Option Description Advantages Disadvantages Cost

    1

    New MDPE pipework

    from spring (Source 1)

    to MH11

    No infiltration losses in upper

    section, cheap (pipe already exists on

    site)

    Does not allow fresh flow percolating

    in to join the MDPE flow. Will sediment

    up due to lack of flow velocity and

    difficult to clean.

    Labour

    2Concrete lining entire

    khettara invert

    No infiltration losses, captures

    percolating flow also.

    Channel can still be blocked by falling

    rocks, debris and sediments.

    64740

    (MDH)

    3

    Concrete lining entire

    khettara invert, walls

    and roof (re-build

    khettara)

    New long lasting infrastructure,

    provides safe working and

    maintenance area, channel no longer

    blocks from falling stones/debris

    Expensive, difficult construction (with

    very limited access for machinery) and

    complete removal of existing

    infrastructure.

    180000

    (MDH)

    4New 400mm concrete

    perforated pipe.

    New infrastructure, easier and safer

    construction, allows for percolation

    Removal of existing infrastructure, not

    a proven technology in the area. Access

    into manholes only (like a small sewer)

    151900

    (MDH)

    5

    Re-line invert with

    perforated UPVC pipe,

    gravel and PVC

    membrane

    Cheaper than concrete lining (option

    2), also perforated pipe prevents

    channels blocking with large stones

    Tricky construction using straight pipe

    sections in the meandering khettara.

    Fig roots may grow in the perforations

    and block the pipe this is TBC.

    67710

    (MDH)

    FLOW LOSSES

    FLOW IN

  • 8/2/2019 081126 Report AIDECO Version

    18/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    18

    Figure 4.7: Khettara remediation Options

    Option 2 Option 3 Option 5

    Option 4

    4.2.6 Recommendation

    Reline using UPVC pipe with perforations (option 5). It is not confirmed as to whether fig roots will

    block the perforations, further study is required here to confirm before construction starts. If fig roots

    are deemed a problem, then the pipes should be solid and maintenance improved to ensure thechannel is cleared annually (remove fallen stones/boulders). Regular maintenance will also be

    required to remove collected silt as well as roots growing along pipe joints. See drawing 2012 in

    appendix F for full details.

  • 8/2/2019 081126 Report AIDECO Version

    19/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    19

    Figure 4.8: Seguia and water tanks layout

    4.3 Seguia and Water Tanks

    4.3.1 Existing Infrastructure

    The concrete seguia and storage tanks were built around 15 years ago. The seguia used to be the earth

    channels like the ones seen between the parcels today. The open seguia runs for 900m from the

    khettara outlet to the storage tanks.

    Water from the seguia is used for irrigation, washing clothes and drinking. There is a pumping chamber

    (Manhole C, see AutoCAD drawing) which raises the water to the header tank at the top of the village.

    The Seguia details are shown below in figures 4.9 and 4.10. The seguia hugs a steep slope for most of its

    course, traversing around regular rocky outcrops and changing in gradient to mirror the natural

    contours. There are also several lateral outfalls (generally 100mm DIA holes) which, using stone dams,

    can direct flow into parcels running next to the seguia.

    N

    IMI NTIZGHTE

    ANBDOUR

    PARCELS

    Key

    Concrete Seguia

    Wash Area

    Storage Tanks

    Khettara 1

    Khettara 2

    River

    Figure 4.9 Typical section through concrete seguia Figure 4.10 Seguia photo

  • 8/2/2019 081126 Report AIDECO Version

    20/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    20

    Figure 4.11: Tank 2 filling

    & emptying via twist valve

    Figure 4.12: Cracks and weeds Figure 4.13: Unlined sides Figure 4.14: Steep section

    There are two water collection tanks. Tank 1, which is smaller and

    higher up so the seguia water reaches it first, is sometimes by-

    passed. Tank two, the larger tank shown in the photo, is 17mx 8.5mx

    2.15m, therefore having a capacity of 310m. This tank is filled

    overnight and discharged to fields each morning. Both tanks

    can be bypassed if necessary using steel blanking plates. Tank

    2 has three different outlets to serve different areas of

    parcels, each controlled by cast iron twist valves. Each tank

    has an emergency overflow and both have a build up of

    sediment along the invert. Both tanks are in structurally good

    condition and will not be considered further in this report.

    4.3.2 Problems with existing Infrastructure

    The 900m of open channel is all concrete lined but varies in quality with some sections having cracks

    along the invert and sides. In general it does not look like there are any significant leakages. Most of the

    cracks have allowed plants to cling to and grow within the channel. Therefore, as shown in table 4.2

    infiltration losses are negligible. In some areas the walls are falling away or are no longer lined.

    The gradient also varies along the length with some very steep sections. These create regions of fast

    flowing water which accelerate the degradation of the concrete lining. To date however the lining is still

    generally OK. There are also flat sections where flow is deep and slow, this causes deposition of

    suspended sediments which slowly block the channel and slow the flow further.

    Roots and plants growing within the channel also inhibit the flow and will gradually widen cracks in the

    concrete lining, they also use the water. Where there are cracks and the flow is slow, there are oftenmany plants and weeds are growing. There is also lots of debris in the channel, generally dead leaves,

    which further inhibit flow and could compromise the quality of the drinking water. Evaporation losses

    from the seguia, as shown in table 4.2, are negligible.

  • 8/2/2019 081126 Report AIDECO Version

    21/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    21

    4.3.3 Remediation Options

    There are four steps, or options, for remediation discussed here. Whichever scheme is chosen, it is vital

    that first the channel is cleaned and all plant life removed. Option 1-Step 2 should not be carried out

    with step 1 being carried out first.

    Option 1 Step 1: Fix cracks and re-line base and walls where necessary

    This involves fixing individual cracks by breaking out the cracked section, cleaning and scabbling the

    area, then re-applying concrete and finishing until smooth with the existing channel. Sections where the

    walls are not lined require new concrete lining, the walls should also be stabilized where they are falling

    away due to the steep bank adjacent. This is a quick and cheap solution, however the results will not

    last long unless the works are carried out to a high quality.

    Option 1 Step 2: Improve gradients locally

    There are three sections where the gradient would be unacceptable from a design perspective. These

    sections could be removed by introducing new backdrop manholes or a series of steps set into the

    existing channel. This would increase the life expectancy of the seguia. However the steps or manhole

    would be in reinforced concrete and tricky to construct with limited working space, a dangerous slope

    on one side and shallow bedrock.

    Option 2 Re-line the whole seguia

    This option is to effectively re-built the seguia with new concrete sections cast in-situ. The most cost

    effective and quickest solution would be to line the existing channel with membrane and pour concrete

    on top. The new concrete section requires expansion and contraction joints (bitumen filled) every 10m

    and at each major bend/change in gradient. It is estimated that this could give a lifespan for the seguia

    of at least 20 years, however the solution is time consuming and costly.

    Option 3 Piped flow

    A quick and cheap re-line solution is to pipe the flow for the 900m of seguia. The 150mm UPVC pipe

    would sit within the existing channel with regular open sections at major bends, changes in gradient

    and lateral connections. The solution is fairly simple to install and cheaper than option 3. However, the

    pipe is aesthetically less pleasing, it removes the openness which helps local community trust

    (everyone can see where the water is going) and it makes it more difficult to find/remove blockages.

    Figure 4.15: Option 2-Backdrop Figure 4.16: Reline option 3 Figure 4.17: Option 2 Concrete Steps

  • 8/2/2019 081126 Report AIDECO Version

    22/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    22

    Figure 4.18: Concrete wash area

    Figure 4.19: Contamination in channel

    4.3.4 Costs

    For full costing details see detail BOQ.

    Option Description Cost (MDH)

    1 Step 1 Fix cracks and re-line base and walls where necessary 3,800

    1 - step 2A Improve gradients locally (backdrop manholes) 12,858

    1 - step 2B Improve gradients locally (concrete steps) 11,150

    2 Re-line the whole seguia in concrete 100,800

    3 Piped flow (900m of new UPVC pipework + open sections) 75,080

    4.3.5 Recommendations

    Since the seguia is in decent condition, it is prudent that money is invested elsewhere before large

    amounts are spent upgrading here. It is recommended that the channel is cleaned first including the

    removal of all weeds growing in/near the channel. Then remediation option 1 - Step 1 carried out,which only tackles areas which are in need of repair. It is our understanding that the UPVC pipe

    (option 3) has already been decided on in order to improve the quality of the drinking water.

    Therefore recommend manholes at significant bends and changes in gradient to allow for access for

    cleaning (sediment, etc) and repairs.

    4.4 Clothes washing area

    4.4.1 Existing usage and problems

    The clothes washing area is used by many women in the village.Flow is diverted from the concrete seguia just upstream and runs

    through the middle of the wash area in an open channel as

    shown. This water is extracted by hand. The used soapy water

    then rejoins the main irrigation channel and is used on the fields.

    A small treatment section in the channel already exists just

    downstream of the wash area. It consists of a series of four stone

    dams which are supposed to filter the flow.

    However the dams do not work effectively as all the suspended

    sediments and soaps pass through the cracks in the rocks. Afterseeing the physical evidence and speaking with the local

    population it is clear that contamination is an issue. According to

    the DPA this contaminated water doesnt actually do much harm

    to the trees but it does damage crops and vegetables.

    Table 4.4: Seguia costs

  • 8/2/2019 081126 Report AIDECO Version

    23/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    23

    4.4.2 Remediation options

    Option 1 is to make sure that none of the washing wastewater is used for irrigation by diverting the dirty

    water into a new septic tank or soakaway. This would only be possible if there was a piece of land close

    by available for this. One big disadvantage is the loss of water. Also the effectiveness of a septic tank or

    soakaway is compromised by the antibacterial agents in the washing powder, especially when no other

    bacteria are added (from a toilet, for example). This option includes new concrete washing sinks and

    header tanks.

    Option 2, suggested by the DPA, is to move the entire wash area to a position close to the river and to

    use the soapy water to irrigate trees only. This option would be costly, require a large piece of land and

    the backing of the community because it would change their usual habits, making it much further for

    some people to walk. Although the water would be made use of it means less water is available for the

    main fields where the crops are grown. It would also be difficult to set up a system where all of the

    wastewater reaches trees only, especially if the system is entirely gravity fed.

    Option3, is the purchase of washing machines particularly if it could be shown that they were economic

    on water usage. It would be important that models chosen were modern energy and water efficient.

    This option was chosen in another area of Morocco where they had the same problem, funded by a

    French charity Leau de Desert. The used water would still need to be put into a soakaway or sewer.

    There are the obvious benefits to the women of the village, giving them more time to work in the fields

    for example, but it would take some organisation to avoid disputes and to agree on how much the use

    of it would cost. There would need to be a building, electricity supply (possibly solar) and sewer system.

    There would also need to be a strategy for the eventual repair and replacement of the machines.

    Option 4 is to install a grease trap to remove the contamination. This would need to be cleaned

    periodically, perhaps once a day, which would be a fairly quick and simple operation which involves

    removing the top scum layer and putting it into a soakaway or cesspit (it is not recommended that the

    waste is put into a septic tank as it will affect its operation). The settled sediments could be removed

    around once per month depending on wash area usage. It is recommended that a temporary grease trap

    is installed first to check the dimensions (the bigger it is, the less cleaning required) and the

    effectiveness. This can then be replaced with either a new reinforced concrete unit or a system of

    baffles cast into the existing outlet channel (where the stone dams exist today).

    Figure 4.20: Temporary grease trap steel drum construction

  • 8/2/2019 081126 Report AIDECO Version

    24/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    24

    4.4.3 Costs

    Option Description Cost (MDH)

    1 New soakaway and concrete sinks/header yank 4,500

    2 New wash area by river TBC

    3 New washing machines 4,000 each

    4 Grease trap - temporary steel drum Labour only

    4 Grease trap Utilise existing concrete channel 1,775

    4 Grease trap RC unit 5,050

    4.4.4 Recommendations

    It is recommended that the temporary grease trap is installed (option 4) and the community to be

    consulted to decide the next step.

    4.5 Earth Channels (Earth Seguia)

    4.5.1 Existing Infrastructure and the problems

    There is a network of over 2000m of earth channels delivering irrigation water to over 15ha of

    agricultural land. The channels are lined with large stones and gravels. The less used channels have grass

    growing in them. There are many steps and drop offs to allow the channels match the parcel terracing.

    The channels are aesthetically pleasing and promote trust and openness with the water distribution.

    The permeable invert also allows water to infiltrate into the surrounding soil and feed trees which live

    adjacent to the seguia.

    Figure 4.5: Contamination options - Costs

    Figure 4.21: Section through existing earth seguia

  • 8/2/2019 081126 Report AIDECO Version

    25/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    25

    4.5.2 Problems with existing infrastructure

    The earth seguias serve their purpose in transporting water to the fields but their efficiency is quite low.

    The permeability test (see section 3.4) gave an infiltration rate of 6.7x10 -6m/sec for the soil. This test

    was carried out on a dry earth seguia bed. The initial infiltration rate was 1.08x10

    -5

    m/sec which thensettled to 6.7x10-6m/sec. This means that, over say 300m of channel on average 300mm wide, 0.6l/s

    should be lost (see table 4.2). Over a 12 hour day of irrigation that equates to 26m 3 of water wasted

    (26,000 litres). If 3.4l/s leaves the tanks and 2.8l/s reaches the field, the efficiency is 82%. This

    corresponds to data in The Civil Engineers Reference Book (7) which gives field canal efficiency of 80%

    for unlined canals in blocks of up to twenty hectares. If the water has to travel further or the channel is

    dry, which is often the case, the losses are greater. Other losses of water have also been observed, they

    are hard to quantify but they mean that the total loss could easily be greater than 0.6l/s. The following

    list gives the potential sources of inefficiencies which could be tackled:

    1. Infiltration losses through channel invert.2. Undersizing of channels (flow spills over the edge).3. Losses at the many unlined steps and drop-offs.4. Wastage at stone dams/junctions which do not function correctly (flow dribbles into adjacent

    lines, without actually reaching any fields and even if they did, the fields are not prepared).

    5. Slow flow and pooling due to lack of gradient and high invert roughness (Mannings).

    4.5.3 Options for re-lining channels

    There are 4 re-lining options, all will reduce infiltration losses and increase water availability by up to

    20%.

    Option Description Advantages Disadvantages Cost (MDH)1 UPVC pipe lining Longevity and hard wearing Difficult to construct with many the bends, 132,700

    2 PVC membrane Easy construction and cheap Vulnerable to punctures if not protected 42,700

    3 MDPE pipes Very quick and easy constructionLose openness and aesthetics. Junctions

    awkward (many valves would be expensive)115,500

    4 Concrete lining Longevity and very hard wearing Expensive and long construction time 107,360

    STONE DAM

    WASTAGE

    MAIN FLOW WASTAGE MAIN FLOW

    Figure 4.22: Wastage at dams (4) Figure 4.23: Undersized channel (2) Figure 4.24: Poor drop-off design (3)

    Table 4.6: Earth channel re-lining options (labour inc)

  • 8/2/2019 081126 Report AIDECO Version

    26/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    26

    As part of the re-lining there will need to be new junctions built. There are several options for this, the

    cheapest and easiest to construction and maintain is as shown below. A concrete section with steel

    baffle or piped sections with valves could also be used, though both incur greater costs.

    4.5.4 Recommendations

    Recommend re-lining with PVC membrane (option 2) with major junctions built as shown in figure

    4.29 above. The channel needs to be well bedded and carefully covered with smooth stones to protect

    the membrane. Recommend that a 200m section and one junction built first as a pilot (test) scheme.

    Figure 4.25OPTION 1, UPVC half pipe Figure 4.26OPTION 2, PVC membrane

    Figure 4.27OPTION 3, MDPE pipes Figure 4.28OPTION 4, Concrete lining

    Figure 4.29 UPVC/concrete junction

  • 8/2/2019 081126 Report AIDECO Version

    27/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    27

    Figure 4.30 : Flood irrigation

    4.6 Field Application

    4.6.1 Existing Operation Strategy

    The distribution is based on water rights. Each family has the right to a certain amount of water

    depending on historic agreements; however this does not necessarily represent current needs. The

    scope of this project does not include altering these rights however, only to increase the total quantityof water. The water rights have been the source of many disputes, especially when water levels are low.

    Also, now that homes have tapped water without meters, water usage goes unmonitored and people

    can be as inefficient as they like (many even use the tap water on their fields). To amplify the problem,

    many villagers refuse to pay for the tap water.

    During summer, when flow is low, each farmer is allocated certain time slots when they can extract

    water from the seguia. This is measured in hours, the ancient method was to used a plate with a hole in

    it. A plate full of water would take, on average, 7.5 minutes to empty, therefore they knew 8 plate-loads

    was an hour of extraction time. Now the time is used. The distribution cycle during summer runs in 7

    day loops (one farm in the morning, another in the afternoon)

    During winter, when flows are higher, the time slots still exist,

    however there is more water available per person. The distribution

    cycle runs in 12 day loops. Winter is considered November to April

    and the amount of rainfall varies from year to year, winter 2008 has

    already seen more rain than the whole year preceding it (TBC by

    DPA, Tafraout). The water is diverted from the earth seguias by

    building temporary dams just downstream of their respective

    lateral connections. This flow is channeled using stones/gravel

    weirs. Once in the fields a variety of irrigation techniques are used

    including flood irrigation, furrow irrigation and border irrigation.

    4.6.2 Crop requirements and Irrigation Efficiency

    As stated previously, the irrigation system is not performing to its full potential with flow losses from

    source (khettara outlet) to destination (parcels). Presently, of the 3.4l/s leaving the khettara, only

    2.77l/s arrives at the fields (based on EWB preliminary studies, see table 4.2 above). Based on crop

    water requirements and irrigation efficiency it is possible to calculate the existing and potential

    irrigatable area. The results were as follows; see Appendix E3 for full details.

    Based on the Blaney and Criddle method, Crop water requirements in Imi nTizghte = 562mm/year

    (based on average monthly temperatures and daily daylight hours, and a summer crop of tomato orsorghum. Millet, for example requires less water and has a shorter crop cycle, hence this value would be

    reduced (7)).

    This value does not take into account rainfall (8), hence we are assuming drought conditions. It does not

    take into account any water added to the field between crops. Finally, this value does not take into

    account the efficiency of the water application method. In this case we have an earth canal distribution

    system (80% efficient) and flood irrigation (60% efficient). This increases the net annual crop water

  • 8/2/2019 081126 Report AIDECO Version

    28/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    28

    Figure 4.31 : Typical Drip by Drip layout (12)

    requirement to 1171mm/year(562/(0.8*0.6)). To verify this, the Engineers In Emergencies design guide

    was used (3), giving a value of 1092mm/year. We will work with the higher value.

    2.77l/s gives a total water volume of87,355m3/yearavailable (arriving at the fields). The 2.77l/s takes

    into account the distribution efficiency (previously taken as 0.8), therefore the crop water requirement

    for every parcel becomes 0.937m3

    per square metre/year (937mm/year), therefore the area which canbe adequately irrigated is 9.32 Ha. At present, approximately 15ha are irrigated with this 2.77l/s, which

    means the crops are receiving around 60% of the water they need. This helps to explain the crop failures

    and lack of fruiting trees in the summer 2008 harvest.

    4.6.3 What is the potential?

    There are two factors which can be looked at. That is to firstly increase the flow (reduce losses) and

    hence the application efficiency. Secondly to improve the field application efficiency by, for example,

    installing a Drip by Drip irrigation system.

    By removing infiltration losses in the khettara and earth seguias, the flow arriving at the fields can be

    increased to 3.87 l/s. This increases the annual water available to 122,044m3/year.

    With a crop water requirement of 0.937m3 per square metre, it possible to irrigate an area of13.02Ha, a

    large increase from 9.32Ha.

    By installing Drip by Drip irrigation, field application efficiency increases to 0.8, the potential irrigation

    area subsequently increases to 17.37Ha.

    4.6.4 A note on Drip by Drip irrigation

    Drip by Dip irrigation is an efficient irrigation method, it is a proven technology and many trees and

    crops have very been successful under the system. The trickle system transports water through an

    extensive pipeline network to the soil near the plant and puts the water directly into the root zone. The

    main issue, however, is the cost and difficulty in construction. The most efficient and intricate systems

    are generally used only for high value cash crops due to the high setup costs. Setting up a system to

    work correctly in Imi nTizghte will

    require a professional with the

    correct knowledge, skills and

    experience. It requires a hands

    on approach, training the local

    farmers in the process and would

    most certainly benefit from a pilot

    project on a few parcels (to test

    construction methods and

    effectiveness). INRA and DPA

    involvement are absolutely

    necessary here.

  • 8/2/2019 081126 Report AIDECO Version

    29/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    29

    4.6.5 Summary table, costs and Recommendations

    SCHEMEAREA POSSIBLE

    TO IRRIGATEADVANTAGES DISADVANTAGES

    COST

    (MDH)

    Existing 9.32 Ha Costs nothingPoor efficiency, less crops, more

    soils erosion

    Free

    Fix khettara an line

    earth seguias13.02 Ha

    Farming practices do not have to change,

    more water available and more/better crops.Setup costs 114,210

    As above + Drip by

    Drip17.37 Ha Maximum efficiency

    Difficulty setting up correctly and

    high associated costs177,210

    As shown in the table above, investment in the irrigation network can have a very significant impact on

    the total area which could be effectively irrigated. At present the Boar fence design will contain an area

    of 9.75 Ha. The total area covered by the channels is in excess of 15Ha (DPA, Fiche Techniques), it is

    therefore recommended that firstly the khettara and earth seguia upgrades are completed. Followingthis, steps need to be taken to improve the irrigation efficiency further, via drip by drip or other forms of

    water efficient irrigation. As a quick example, a Carob tree requires 350mm/year to fruit, so a flood

    irrigation system (60% efficient) would demand 580mm /year (over the root area). To compare, a drip

    by drip irrigation system (80% efficient) would need 438mm/year. This step, very much into the

    unknown for many of the local farmers, needs be driven by INRA, DPA, AIDECO and the people of Imi

    nTizghte.

    In conjunction with this, it is suggested that steps are taken to encourage people to start using more

    dryland crops. For example Pearl Millet (which can replace other grains such as wheat and corn), Carob

    trees, and Cactus trees (prickly pear).

    Finally, one of the main risks with flood irrigation is salinisation. This is when >0.1% salts (Na) exist in the

    top 200mm of soil. Salinisation can be avoided by ensuring adequate surface and sub-surface drainage

    to ensure no excess water pools and deposits salts. It is recommended that annual soil tests be carried

    out by INRA (this could be organized by AIDECO/DPA/EWB each summer) to monitor salt levels and

    irrigation/drainage modified as required. Remediation of salinisation is achieved in several ways, the

    most appropriate and simple example is to flood the fields to flush excess salts out.

    Table 4.7: Field Application options and costs

  • 8/2/2019 081126 Report AIDECO Version

    30/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    30

    Figure 5.2: AIDECOs sketch of boar fence

    5.0Boar Fence5.1 Introduction

    In recent years the wild boar population in the region has dramatically increased. A major factor in this is

    the absence of natural predators such as wolves and jackels which have been completely wiped out. The

    reproductive pattern of the boars has also amplified the problem. The boars are very destructive

    because they eat most vegetables, even cactus, and also rummage in the ground for grubs which causes

    further damage. Some people have built personal boar fences around their land. Materials seen include

    stone walls, brambles, reeds, and wooden posts with chicken wire. Where there are these fences

    vegetables seem to be successfully grown, however the vast majority of land remains unfenced.

    There has been talk of building a perimeter boar fence for many years and it is something that many

    people in the village say is the most important thing they would like to happen. The association had

    sketched a suggested outline for the fence and then the EWB engineers surveyed the land to produce a

    more accurate map. The total length of the perimeter was measured as 1430m. The terrain is

    changeable and quite hilly and there is one length in particular that the slope is very steep,

    approximately 30 degrees.

    The original design produced by the DPA was a fence with

    steel T sections as posts at 5m centres and galvanised steel

    mesh (50x50). This design was not accepted by AIDECO who

    thought it was excessive. See Appendix C for original fiche

    techniques.The cost per metre was given as 80DH and the

    total cost based on 1200m of fencing was 96000DH. The aim

    of the EWB engineers was to propose a cheaper fence

    design.

    Figure 5.1: Existing Fence types in Imi nTizghte

  • 8/2/2019 081126 Report AIDECO Version

    31/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    31

    Figure 5.3: Wild Boar and electric fencing

    Various options were looked at with each one have advantages and disadvantages in terms of cost,

    appearance, effectiveness, time to construct, maintenance required and environmental impact.

    5.2 Initial design considerations and materialsOne of the first things that was looked into was an electric fence as this is what is typically used in

    France. The cost of this fence would be quite modest, as low as 20Dh/m, based on prices from a French

    website (9). However it was decided that it would probably not be appropriate here because the

    maintenance is so important for it to work correctly. With a wall or solid fence a small area of damage

    might leave an area that can be breached but if an electric fence is not working the entire thing becomes

    useless. Given the length of the fence and the relatively high level of maintenance required it was

    deemed an inappropriate technology for the village. To back this, there is an electric fence somewhere

    else in the valley which has proved ineffective, thought the reasons for the failure are unknown.

    It was thought that local materials would be the cheapest

    and have least environmental impact. There are fences that

    have been built using the trunk of a date palm as the base

    and then palm branches to as the barrier. This is ok for the

    small fences some people have but there would not be

    enough for the kind of lengths necessary.

    The British CIRIA Wildlife Fencing Design Guide (10) and all

    evidence of fencing seen in the UK is that timber fence posts

    are used. This guide does also show examples of steel posts

    but says that concrete is not suitable because it does not

    perform well under tension. The problem here might be sourcing good quality timber and preservative.

    Some of the electricity poles in the village are in timber and this type of timber would be suitable. It

    should be found out where this timber comes from, what is its expected lifetime if treated and the cost.

    Any timber sourced needs to be from a sustainable resource, a local managed forest is the ideal.

    The other obvious local material is stone. All the traditional buildings are built from stone with an earth

    based mortar. The advice from the DPA was that this option would be no cheaper because stone would

    still have to be bought still that problems could be caused by people taking stone from existing terrace

    walls. The opinion of the EWB engineers was that enough stone could be collected from the surrounding

    area if there was enough of a volunteer labour force from the village.

    Design 1:Dry stone walling with living barrier

    EWB and DPA agreed on the merits of the option of dry stone walls along the river where there is an

    abundance of stone. It is a traditional technique and could enhance rather than degrade the natural

    landscape. There is also the advantage that in some places walls already exist which just need building

    up to a suitable height. In addition to the walls prickly branches are placed on top to create a more

    effective barrier. These could be Gigibier or Argan. A line of trees can also be planted on the inside of

  • 8/2/2019 081126 Report AIDECO Version

    32/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    32

    Figure 5.4: Section through river stone dry walling with trees

    the wall which within a couple of years will grow to a height that the can be pruned to form a living

    barrier over the top of the wall. It is hoped that these trees will require no irrigation and can be provided

    by the Department dEau et Forets.

    Environmental issues: One concern with this is that it may affect the river if too many stones are taken

    from it though the DPA assured that this would not be a problem so long as stones are not taken from

    the river banks as this could change the course of the river. These rivers actually only flow normally

    about once a year and are used by most people to burn their rubbish, therefore the environmental

    impact is considered negligible. The embodied energy in this option is almost zero (only the transport

    required for labour and trees) and the planting of trees has a positive impact.

    Cost: The cost of this wall is very much dependant on the labour since the materials are free. If there is

    enough local know-how and people willing to volunteer the cost of the wall would be very low.

    Otherwise due to the length of time it takes to build compared to a fence the cost would not be that

    much less.

    Maintenance: For this length a maintenance strategy would need to be in place with people assigned to

    ensure that the Gigibier is intact, to make any repairs necessary to the walls and to prune the trees.

    Design 2: Mesh fence

    This is similar to the original design by the DPA however it is suggested that timber posts are used

    instead of steel to reduce the cost and also as a material with lower embodied energy. Due to the

    transparency of the mesh this fenceline would not have a big impact on the landscape. It is most

    suitable for terrain which is reasonably flat. Mesh can be placed to a depth of 200mm in the ground and

    attached to a tension cable to prevent the boars from digging underneath. On steeper ground masonry

    walls could be built to provide to provide a horizontal base on which to place the fence.

  • 8/2/2019 081126 Report AIDECO Version

    33/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    33

    Figure 5.5: Elevation section of Timber post and 50mm mesh

    In order for a mesh fence to be effective certain specification should be made and it is recommended

    that the following advice is taken:

    Posts at the start of a fence line or at a change of direction need to be at least 900mm below ground and

    need to be supported with a strut and tie, see the figure.

    For a boar fence the guide recommends a minimum of 200mm below ground and 900mm above ground

    level. However it suggests that this may need to be increased in certain circumstances. The high

    population and determination of the boars here would justify increasing this height.

    It is important to specify a good mesh. If it is a woven mesh, the joints should be lock joints rather than

    hinge joints so that verticals cant slip on the horizontals.

    Foundations are not required if the posts can be driven into the ground without first digging out the soil.

    It would be beneficial to source a mechanical post driver if possible to drive the posts into the hard

    ground, this is made easier with pointed ended posts.

    It is important that the mesh is attached to the outside of the fence, i.e. so that the animal pushes the

    mesh onto the post rather than pushing it off.

    Environment and Costs

    The timber posts MUST be specified from a sustainable forest resource. For this scheme to become a

    symbol of best practice then we must invest in protecting the environment wherever possible. The

    openness of the mesh also helps to minimise the visual impact. As stated above, using timber also

    helps to reduce the cost.

    Maintenance

    These fence sections will need to be checked regularly for weaknesses and breakages. The tension wire

    can be tightened manually so it would be prudent to train a local person how to do this.

  • 8/2/2019 081126 Report AIDECO Version

    34/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    34

    Figure 5.6: Timber end post detail

    Figure 5.7: Endpost

    Design 3: Half blockwork wall half mesh

    For the length of fence along the road a robust solution is necessary because

    of the possibility of impact from vehicles and the amount of pedestrians

    including children who frequent this route. A fence line with posts and mesh is

    one option, although it might be subject to damage. There is also a reasonable

    slope which is makes it difficult to accommodate the mesh. The DPA suggested

    that a wall built in concrete blocks could work out to be cheaper, particularly if

    a machine were purchased to produce the blocks in the village using sand

    dredged from the river. This seems like a good suggestion however solid

    concrete walls would not be very aesthetically pleasing, particularly because

    they would block the view and give a closed atmosphere. Therefore the

    proposed option is to have a block wall built to a height of 600mm 980mm

    with a mesh for the upper half (the height of blockwork varies over each 5mlength according to the slope, 4 courses of blocks suggested as minimum). It is

    recommended that the blocks are plastered and painted a similar colour to the

    houses for a better look. The mesh required would not need to have such

    small squares as the 50x50 suggested for a full height mesh fence because the

    boars can exert more force if on the ground rather than if they have tried to

    climb up. A mesh size of 100 x 100 is proposed.

  • 8/2/2019 081126 Report AIDECO Version

    35/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    35

    Figure 5.8: Elevation section, half blockwork wall half 100mm mesh

    Environmental issues: One disadvantage of this wall is the amount of cement needed to construct it,

    with the high embodied energy which that entails. A more environmentally friendly method would be touse earth blocks, or rammed earth. The DPA do not think that the soil here is appropriate for this use

    but it is something that should be given more consideration before being completely ruled out,

    particularly when earth has been used in the construction of the old houses here.

    Cost: The cost depends on whether or not the blocks could be produced locally with a new machine.

    This mesh size is cheaper than for the type of mesh required for a full height mesh fence.

    Maintenance: Maintenance is quite low. Repainting of the wall every few years would improve the

    appearance. The mesh may need some repairs and the posts may need replacing after 10-20 years

    depending on the quality of timber and preservative.

    Design 4: Masonry wall

    This option was decided upon because it offers a stiff, robust solution on steep rocky ground. It is

    expensive but it is a well known method used throughout the region and utilises local materials, hence it

    fits well with the surrounding environment.

    Environmental Issues: Embodied energy from the mortar and reinforced concrete posts. Using local

    stones removes the need for quarrying and transportation. The wall fits in well aesthetically and its high

    lifespan improve the overall environmental impact.

    Costs: Are high due to the concrete and steel volumes. Can be made cheaper if local/volunteer labour is

    used.

    Maintenance: Low. This is as maintenance free as it gets. This wall will also last longer than any other

    fence type discussed here.

  • 8/2/2019 081126 Report AIDECO Version

    36/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    36

    Figure 5.9: Mortared stone wall with concrete posts

    Figure 5.10: Typical gate detail

    (Timber with mesh infill)

    Gates

    The position of the gates along the fenceline should be

    agreed with the community in order to ensure adequate

    access. However the number of gates should be kept to

    the minimum required because they represent a

    weakness in the fence (continuity) and they can be left

    open. They also increase the overall cost. A practical note;

    you need to put end posts either side of a gate rather thanusing the gate posts as end posts. This is because the

    endposts take the strain of the main cable and will move

    over time, therefore the rigid gate would not last very

    long under such conditions. The gate consists of timber

    cross members with 50x50mm mesh infill and a 200mm

    deep concrete footing linking the two gate-posts.

    Maintenance issues

    Problems are envisaged here because of problems in the community. The evidence of a very small

    turnout to a presentation given on the fence and irrigation scheme suggests that a community meeting

    to discuss maintenance would be impractical. A more likely outcome is that there will be a few

    dedicated people in the village who end up doing all the work. If this were the case it would be fairer for

    everyone to pay a small amount to pay these people for the work. Though again getting a consensus on

    this would be difficult. In summary this is an area which need a lot more consideration and work from

    AIDECO. It would be prudent to assign some budget to the upkeep of the fence.

  • 8/2/2019 081126 Report AIDECO Version

    37/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    37

    Table 5.1: Fence sections cost and appraisal

    Figure 5.11: Fence sections and plan of Imi nTizghte

    Section TERRAIN FENCE TYPE ADVANTAGES DISADVANTAGES COST MDH

    A

    235m

    Riverside -

    flat

    Drystone wall (river

    stones)

    Cheap solution and longevity, also

    aesthetically very pleasing and

    sustainable material usage

    Time consuming

    construction, living part

    needs maintenance. Takesup space on land.

    8225

    35Dh/m

    B

    222m

    Roadside -

    moderate

    slope

    Bottom half block work,

    top half 100mm mesh

    Suits sloping ground, longevity,

    strong, keeps open view.High embodied energy.

    22270

    100Dh/m

    C

    206m

    Roadside -

    moderate

    slope

    As above As above As above19775

    96Dh/m

    D

    72mFlat bare soil

    50x50 mesh and timber

    fenceposts

    Quick and easy construction.

    Low visual impact.

    Relatively expensive,

    vulnerable to vandalism

    9479

    132Dh/m

    E

    280m

    Riverside

    flatAs above (A) As above (A) As above (A)

    11100

    40Dh/m

    F

    35m

    Steep rocky

    section

    Mortared wall with

    concrete posts (5m c/c)

    Longevity, aesthetics and extremely

    robust

    Costly, time consuming

    construction

    7685

    220Dh/m

    G

    110m

    Linkages

    betweenhomes

    Mortared wall with

    concrete posts (10m c/c)

    Longevity, aesthetics and extremely

    robust

    Getting agreement from

    locals to use existing walls

    14605

    133Dh/m

    H

    119mFlat bare soil As above (D) As above (D) As above (D)

    14426

    121Dh/m

    J

    147m

    Stepped Soil,

    rocky

    terraces

    As above (B & C) As above (B & C) As above (B & C)14985

    102Dh/m

    TOTAL 122550

    KEY STATS

    1426 m LENGTH

    122550 MDH TOTAL COST

    86 MDH/m COST/M

    98550 MDH MATERIALS

  • 8/2/2019 081126 Report AIDECO Version

    38/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    38

    Figure 6.2: Map showing

    Pearl millet in Africa. Photos

    of Pearl Millet (top) and Okra

    6.0 Crops

    Different crop types a critique with respect to Imi nTizghte

    A number of different crop types are grown today in Imi nTizghte, this chapter looks at those species

    which are grown, those which could be exploited further, and new crops which may not have been

    considered before. The hope is to leave the local population with ideas for future agriculture to make

    best use of the water whilst bolstering income.

    6.1 Existing Crops

    There is a limited variety of crops grown in Imi nTizghte today, generally due to the fact that the boars

    eat most crops. They do not eat wheat, therefore it is the most popular crop. Some small parcels have

    simple self maintained boar fences and they grow Courgettes, Aubergines, Squashes, Peppers and

    various root vegetables. Alfalfa is also grown as animal feed.

    The vast majority of the oasis is taken up by fruit trees including Argan, Olive, Almond, Date with a few

    Carob and the occasional Pomigranite. There are also some fruiting cactus trees.

    6.2 New crops

    Suggestions for new crops include Pearl Millet, Pistachio tree,

    Marama bean and Okra. These are all dryland crops, though

    market value in the region requires further assessment. Pearl

    Millet is often preferred to maize or wheat because of its

    tolerance to difficult growing conditions such as

    drought (it can survive on 200mmrainfall /year!), low

    soil fertility and pH, high salinity levels and high

    temperatures. It can be used as animal feeds, bread

    and cous-cous making, and porridges. The Marama

    bean is rich in oil and protein (rivaling soya) and

    grows well in the Kalahari Desert. Okra is a another

    dryland crop. It is a vegetable which grows wild in

    Ethiopia and Egypt and is now grown and used for

    cooking and making oil throughout the world.

    Olive Almond Date Argan

    Figure 6.1: Some trees of Imi nTizghte

  • 8/2/2019 081126 Report AIDECO Version

    39/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    39

    Fi

    re

    .

    :T

    e

    r

    ist

    c

    i

    tree

  • 8/2/2019 081126 Report AIDECO Version

    40/43

    Agricultural Project- Irrigation and boar fence, Ammeln Valley, Morocco December 2008

    40

    6.3 Future outlook

    It is recommended that an effort is made to increase the numbers dryland cash crops in the area. This

    can be in the form of the potential new crops mentioned in 6.2 and increasing numbers of certain

    existing crops and trees such as Carob and Cactus. INRA are very interested in driving and monitoring

    the use of the Prickly pear cactus. This i