07 Ammonia Synthesis Revamps - March 2015
Click here to load reader
-
Upload
kvspavan-kumar -
Category
Documents
-
view
71 -
download
10
description
Transcript of 07 Ammonia Synthesis Revamps - March 2015
-
Ammonia synthesis revamps
John Brightling
25 Mar 2015
Westin Hotel Gurgaon, India
-
Targets and Requirements of a Revamp
Typical targets for a revamp of a fertilizer plant:
Capacity increase
Reduction of operating cost / energy consumption
Environmental improvements (e.g. reduction of emissions)
Increase of reliability and availability
Change of Feedstock
Important things to consider to make the project a success:
Use a well proven and reliable technical concept
Keep the plant downtime for implementation and modification as short as possible
-
Reactor development
3
Max Appl, IFA Technical Conference, September 25.-26., 1997, Sevilla, Spain
Equilibrium curve
% NH3
Temperature C
500 450 400 0
5
10
15
20
Quench Heat exchange
heat exch.
-
Converter Retrofits
Interchanger rather than quench
Convert to axial-radial or radial flow
Utilise smaller catalyst
Since reaction is diffusion limited increases reaction rate and therefore increased production
Can improve efficiency by 0.5-1.0 GJ/t
Most plants have done this
-
Reactor development
5
Particle Diameter (mm)
14 12 10 8 6 4 2 0
Rela
tive A
cti
vit
y
120
100
80
60
40
0
20
-
Additional Converter Volume Options
A couple of revamp options:
Booster converter in the synthesis loop
Once through synthesis converter
-
Booster converter (e.g. additional 4th bed)
Equilibrium
3 bed converter
4th Bed booster
-
WC Synthesis Gas
(Make up gas) WC
NH3 - Synthesis
Loop
Purge Gas
1 2 3 R
S
S: Separator
WC: Water Cooler
CH: Chiller with
NH3-refrigerant
S
NH3 Product
H2O
HP Steam
CH CH CH
Synthesis
Reactor
NH3 -
Once Through
Synthesis
H2O
Booster low pressure OT Scheme
-
Revamp Case Study 1 - Once through
Duslo Ammonia Plant 950 TPD Europe, build 1973
Desire to increase plant capacity by 40%
New once through converter by Uhde
Two radial beds KATALCOJM 74-1 catalyst with one interchanger
Additional capacity by reactor 385MTPD
-
Duslo, Slovakia
-
Original Front End & Loop
HP steam
Feed
MP steam
Process air
Combustion air
CW
BFW
CO2 -removal
CO2
Refrig.Unit
BFW
FuelGas
ProductAmmonia
-
New Once Through Booster
HP steam
Feed
MP steam
Process air
Combustion air
NH3
CW
NH3
SynthesisLoop
BFW
CO2 -removal
CO
2
RefrigerationPackage Unit
BFW
BFW
Purge Gas
H2Recovery
FuelGas
AmmoniaWater
Product Ammonia
-
Four-Phase Revamp Project Execution
Test Run -> mass balances, Temps, Pressures
Precise pressure drop review
Catalyst performance data
Control valve survey
Maximum load tests
Discussions with operation staff
Plant simulation with gathered data
Revamp Study
-
Description of the revamp concept
Process Flow diagrams (PFD)
Steam Balance
Production and consumption figures
Cost estimate (+/- 15%)
Revamp Study
Study results:
Four-Phase Revamp Project Execution
-
Equipment / piping Specifications
Piping and Instrumentation diagrams (P&ID)
3-D modelling of plant
Operating handbook / analytical manual
Consumption / effluents / wastes
Plot plans
Cost adjustment / confirmation
Basic Engineering
BEP results:
Four-Phase Revamp Project Execution
-
Revamp concept checked and confirmed
Detailed configuration of the plant
Selection of equipment suppliers begins
Long delivery items ordered
Licenses acquired / updated
Safety aspects explored
Basic Engineering
Four-Phase Revamp Project Execution
-
OT Synthesis advantages for revamps
Energy efficient
Tie-In work completed during scheduled downtime
Minimisation of downtime during Revamp
Start-up any time plant is in operation
Shutdown/isolation from running plant
Spatial Integration not necessary
-
OT Synthesis Spatial layout
-
Revamp Case Study 2 - Booster
Kuibyshev Azot OJSC
Plant 1360TPD GIAP Russian, build 1977
Operating at 1600 TPD desire to increase plant capacity to 1800 TPD
The plant is a standard GIAP design of the 1970s.
Several dozen of this plant type exist in Russia
and other states of the former Soviet Union
-
Revamp Case Study 2 - The Customer
Kuibyshev Azot, Togliatti, Russia
Kuibyshev Azot OJSC:
-
Profile of the Original Ammonia plant: - fairly conventional process applicable to the whole family of such plants:
top-fired primary reformer with internal riser pipes
bayonet-type HP steam boiler downstream of the secondary reformer
CO shift with one vessel for HT and two parallel vessels for LT shift
MEA CO2 removal system
Standard methanation
synthesis gas compression by steam-turbine driven centrifugal compressor
synthesis loop with one ammonia converter
Modifications made in earlier revamp:
change from MEA to activated MDEA as CO2 removal solvent
new ammonia converter cartridge with axial/radial flow pattern
Revamp Case Study 2 - The plant
-
Ammonia plant block diagram before the revamp:
Revamp Case 2 Plant before revamp
natural
gas
air
steam
steam
BFW
ammonia
steam
process air
compressor
pre-
heating
metha-
nation
desulphu-
rization
pre-
heating
primary
reformer
secondary
reformer
gas
cooling
CO2
removal
gas
cooling LTS
gas
cooling HTS
synthesis
loop
refrige-
ration
syngas
compressor
(1st + 2nd stage)
syngas
compressor
(3rd + 4th stage)
synthesis gas generation
ammonia synthesis purge gas
proc. air
preheater
CO2 BFW BFW
-
Kuibyshev Azots target for the revamp:
production increase to 1,800 tons per day (+ 12.5 % on current / + 32 % on original nameplate capacity)
improved energy efficiency of secondary importance
Technical solution: main changes in syngas generation (front end):
Removal of fired heater for feed preheating, replacement by new preheat
coil in reformer flue gas duct
addition of blower to suction side of process air compressor
lower steam-to-carbon ratio
New feed / steam coil in flue gas duct to increase feed / steam inlet
temperature
Revamp Case 2 The revamp
-
Case Study 2: Synthesis Section
-
Water Removal from Synthesis Gas
Can use either molecular sieves or ammonia washing
Then feed synthesis gas to converter inlet
Reduces ammonia content of gas inlet converter therefore increases production
Reduced refrigeration load
No loss of reactants in purge gas
-
Technical Solution in Synthesis (1 of 2)
-
Technical Solution in Synthesis (2 of 2)
-
KATALCOJM 74-1 - Stability & Longevity
User Technology Operating
Terra Severnside, UK (closed) LCA 2 20 years
Puyang, Henan, China Uhde 20 years
Terra Severnside, UK (closed) LCA 1 15 Years
CBC, Hainan, China Casale 19 years+
CF Courtright, Canada AMV 17 years +
Orica, Australia Casale 14 years+
Incitec Pivot, Australia KBR/Casale 13 years+
SAFCO, Saudi Arabia Uhde 8 years+
Duslo, Slovakia Uhde 7 years+
Saudi Mining, Saudi Arabia Uhde 4 years+
Dyno, Australia Casale 2 years+
-
Case Study 3 : Casale Revamp
Ammonia Plant 800mtpd
KBR 4th bed booster converter installed in 1997
Used KAAP catalyst Ru on activated carbon substrate
KAAP catalyst rapidly degraded resulting in a loss of activity, loss
in plant capacity and loss of
catalyst from the reactor
Reactor converted by Ammonia Casale to use KATALCOJM 74-1
-
Case Study 2 : Casale Revamp
-
Relative Inhibition of
Ru and Fe Catalyst
Ammonia, Appl 1999
Case Study 2 : 4th Bed duty
N2+3H2 2NH3
N2+3H2 2NH3
Ru
Fe
Reacti
on
Rate
Ammonia %
-
Proven performance - catalysts
= KATALCOJM 35-series
~36
= KATALCOJM 74-series
~8
= KATALCOJM S6-10
(equivalent to 35 series)
~19
-
Proven performance - converters
= Kellogg/KBR ~9
= Topsoe ~1
= Casale ~20
= ICI ~3
= Uhde ~24
= Other ~5
-
BFW
Make-up gas
Syngas compressor
Refrigeration Purge
NH3
( liquid )
HP steam
C.W.
New large plants
2200mtpd TKIS Uhde 2 converter 3 bed, inter-bed HP boiler
-
BFW
Make-up gas
Syngas compressor
Refrigeration Purge
NH3
( liquid )
HP steam
C.W.
2200mtpd TKIS Uhde KATALCOJM 74-1 in Bed 2 and 3,
Loop pressure can be reduced 4% Additional production of 25,000te/year
New large plants
-
Johnson Matthey ammonia synthesis
..most efficient plants
..largest plant operating
..largest plant being built
Technical services
Catalyst developments
-
Thank you