06/06/07 – 07/11/07 BIMBuilding Information Modeling

Page 2: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Research Subject:

Page 3: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Review of Literature:

BIM Concept

Image Courtesy: http://www.architecture.com.au/departurelounge/VVS_modell_1024.jpg

OWNER

CONTRACTORARCHITECT

Page 4: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Review of Literature:

Multiple Analysis from same Model

Image Courtesy: http://accuracyandaesthetics.com/wp-content/uploads/2007/05/multipletypes.jpg

Page 5: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Review of Literature:

Trends in BIMFrank Gehry

According to a survey by the joint BIM committee of the American Institute of Architects and Associated General Contractors of America, 74% of the 1,266 respondents said they're using 3-D digital modeling at some level.

The Merry Road to BIMBy Jeff Yoders, August 11, 2006,Building Design and Construction

His work includes the Experience Music Project (Seattle), the Guggenheim Museum Bilbao (Spain), and the Walt Disney Concert Hall (Los Angeles); Constructed by Mortenson Construction.

GSA: US General Services of Administration

The GSA has even taken the extreme step of mandating the use of IFC-based BIM and believes that BIM adoption should not be driven by cost savings alone, but for its many other benefits such as the ability to explore different engineering systems, perform energy analysis for LEED certification, derive specifications automatically, and eventually eliminate the use of paper and paper-based processes

Page 6: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Review of Literature:

Trends in BIMFreedom Tower : SOM Eureka Tower: Fender Katsalidis Australia

Image Courtesy: http://images.google.com/images?svnum=10&um=1&hl=en&rls=com.microsoft%3Aen-us%3AIE-Address&rlz=1I7TSHA&q=freedom+tower

Image Courtesy: http://www.sh.xinhuanet.com/2007-05/14/xin_4105041415370462036615.jpg

Page 7: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Research Case:

Case StudySHSU Academic Building 5 @ Huntsville, Texas:

Designed by WHR ArchitectsConstructed by SpawGlass ConstructionProject Start Date: 15 May 2007Project End Date: 26 September 2008Project Duration: 16 Months

The project is a 4 story high building with a basement and penthouse level

Page 8: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

SpawGlass Construction

Integrate Time schedule: 4DDetect Design ConflictsUpdate the 4D model as the project progressesA need for dynamically integrated 4D modelSub-Contractor Co-ordination.

Expected Benefits from BIM

Parts of BIM not tested

Quantity take-offsResource allocation: Man-hours, methods and materialsCost allocation across project durationFacility Management

Page 9: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Constructor 2007

Modeling Interface

Estimating Interface

Scheduling and Generating reports

Plays a 5D real time- space file.

Cost reports

Page 10: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Model Transfer

Convert Revit file to IFC fileOpen IFC file in Constructor 2007Add schedule in constructorCreate the sequencing file in Presenter 2007

Expected Transfer using IFC extension file

Issues encountered

IFC Conversion is a time-consuming processUnexpected scaling of elements in Constructor

Page 11: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Challenges Creation of second BIM model with necessary details to integrate all scheduling activities.

Page 12: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Challenges Creation of second BIM model with necessary details to integrate all scheduling activities.

Page 13: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Challenges Creation of second BIM model with necessary details to integrate all scheduling activities.

Page 14: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Challenges Scheduling to reflect updated schedule

No option for predecessor / successors relationship logic

Linear Scheduling using Construction Simulation File

Page 15: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Challenges Scheduling to reflect updated schedule

STEPS INVOLVED

1. Start project in Estimator: Establish Project Database2. Assign Recipes to Building elements in Constructor3. Define the Work Breakdown Structure4. Assign Construction Zones5. Add Task Durations in preferred scheduling software 6. Export the 4D model to Presenter

Dynamic Schedule using Recipe Menu

Result:A dynamic scheduling file made from scratch using Constructor 2007

Disadvantage:No scope to dynamically connect an already existing schedule using Constructor

Page 16: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Navisworks – (Currently under tests)

Scheduling to reflect updated schedule

STEPS INVOLVED

1. Convert Constructor/Revit file to Navisworks file format2. Link an already existing schedule to Navisworks3. Assign building elements to task components 4. Play real time-space interactive animation file

Dynamic Schedule using Recipe Menu

Result:A dynamic scheduling file made from existing schedule. Contractor need not change traditional ways of conducting business

Disadvantage:Navisworks does not let the user draw additional components. One needs to use Revit+Navisworks OR Constructor+Navisworks.

Page 17: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

BIM issues identified so far.

Page 18: 06/06/07 – 07/11/07 BIM Building Information Modeling.

MISSING END BEARING FOR BEAM.

Page 19: 06/06/07 – 07/11/07 BIM Building Information Modeling.

BEAM LOCATION INCORRECT

Page 20: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Clarify detail A6 on A 301.

Is there a concrete section behind the MS beam ?

DRAWING INFORMATION CONFLICTS

Page 21: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Additional Detailsare required to constructthe glass canopy

East canopy

DIMENSIONS MISSING

Page 22: 06/06/07 – 07/11/07 BIM Building Information Modeling.

Case Study: SHSU Academic Building 5

Work to be done

1. Phase 1: Modeling of Architectural/ Structural Elements

2. Phase 2: Test Scheduling Connectivity using Constructor/ Revit

3. Phase 3: Test Scheduling Connectivity using Navisworks

4. Phase 4: Modeling and scheduling of MEP elements

5. Phase 5: Final Reports

Page 23: 06/06/07 – 07/11/07 BIM Building Information Modeling.

THANK- YOU !