06 Fantaye PPT muros colados

29
1 Design and Performance of the Buttress Wall at Vehicular Security Center, World Trade Center New York City, NY Mueser Rutledge Consulting Engineers 14 Penn Plaza – 225 West 34 th Street New York, NY 10122 917-339-9300 Sitotaw Y. Fantaye, P.E., Associate Lixun Sun, PhD T.C. Michael Law, PhD, P.E., Associate Site Photo: Taken December 2010

description

tips muro colado

Transcript of 06 Fantaye PPT muros colados

Page 1: 06 Fantaye PPT muros colados

1

Design and Performance of the Buttress Wall at Vehicular Security Center, World

Trade Center New York City, NY

Mueser Rutledge Consulting Engineers14 Penn Plaza – 225 West 34th StreetNew York, NY 10122917-339-9300

Sitotaw Y. Fantaye, P.E., AssociateLixun Sun, PhDT.C. Michael Law, PhD, P.E., Associate

Site Photo: Taken December 2010

Page 2: 06 Fantaye PPT muros colados

2

Site Plan: Vehicle Security Center

L i b e r t y   S t r e e t  

A l b a n y   S t r e e t  

W o r l d   T r a d e   C e n t e r

Outline of VSC Basement Walls

C e d a r   S t r e e t

90 West(20‐StoryHistoricBuilding)

130 Cedar Street

Cutoff wall phase 1

• Owner – Port Authority of NY and NJ

• Contractor – EE Cruz/ Nicholson JV

• Engineer of Record – Liberty Security Partners/ Mueser Rutledge Consulting Engineers

Acknowledgements:  

Page 3: 06 Fantaye PPT muros colados

3

• Essential facility for the function of the WTC

• Vehicle screening and tour bus parking

• Southern expansion of the WTC

• Entirely below grade structure

• Plan area of 200 x 400 feet

• 60 to 100 feet of excavation

• Groundwater 10 feet below grade

• Excavation support required on 3 sides (West, South and East) – Existing original WTC wall on North 

• Proposed wall along south located against the vault of an existing historic 20 story structure – 90 West

Background: Vehicle Security Center

A A

Site Plan: Vehicle Security Center

Page 4: 06 Fantaye PPT muros colados

4

B

B

Geologic Profile: Section A ‐ A

130 Cedar Street

90 West Street

Rock

Fill

Organic

Sand

Decomposed Rock

310

300

290

280

270

260

250

240

Elevation(PA DATUM)

Till

Geologic Cross‐section: Section B ‐ B

Organic

Sand

Fill

Till

Rock

SlurryWall

56 Ft. Excavation

90 West St20-Story Historic Building

TimberPiles

Page 5: 06 Fantaye PPT muros colados

5

Design Concept I: Slurry Wall

•  Construct slurry wall at VSC perimeter

Slurry Wall

V A U L T / S I D E W A L K

Existing high rise structures with one basement level supported on piles

Design Concept I: Stand‐off frame

V A U L T / S I D E W A L K

Existing high rise structures with one basement level supported on piles

•  Excavate and install stand-off frame using pin piles to allow installation of tieback anchors below the tip elevation of the timber piles supporting the Historic 90 West Building

Stand-Off Frame

Page 6: 06 Fantaye PPT muros colados

6

C

C

Design Concept I: Tieback Anchors

•  Install tieback anchors

Tieback Anchors

Construction Sequence1. Guide Wall

Design Concept I: Section C ‐ C

1.

Page 7: 06 Fantaye PPT muros colados

7

Design Concept I: Section C ‐ C

Construction Sequence1. Guide Wall2. Slurry Wall

2.

Design Concept I: Section C ‐ C

Construction Sequence1. Guide Wall2. Slurry Wall3. Pin Pile

3.

Page 8: 06 Fantaye PPT muros colados

8

Design Concept I: Section C ‐ C

Construction Sequence1. Guide Wall2. Slurry Wall3. Pin Pile4. Excavate (stage 1)

4.

Design Concept I: Section C ‐ C

Construction Sequence1. Guide Wall2. Slurry Wall3. Pin Pile4. Excavate (stage 1)5. Wale/blocking/tieback 

anchor

5.5.5.

Page 9: 06 Fantaye PPT muros colados

9

Design Concept I: Section C ‐ C

Construction Sequence1. Guide Wall2. Slurry Wall3. Pin Pile4. Excavate (stage 1)5. Wale/blocking/tieback 

anchor6. Repeat steps 4 & 5/ 

Excavate to final subgrade

6.

6.

6.

Design Concept I:Why not used?

1. Stand‐off frame would interfere with the future structure

2. 90 West did not allow tieback anchors below their building

Page 10: 06 Fantaye PPT muros colados

10

Design Concept II: T‐Panels

•  Construct T-Panels/ first segment of buttress wall with tiedownsleeves

V A U L T / S I D E W A L K

Existing high rise structures with one Basement level supported on piles

Panel joint shear connection

Stem

FlangeTiedownSleeves

Design Concept II: Secondary Panels

V A U L T / S I D E W A L K

Existing high rise structures with one basement level supported on piles

•  Construct Secondary panels between T-Panels

Secondary panels

Page 11: 06 Fantaye PPT muros colados

11

D

D

Design Concept II: Buttress Panels

•  Construct Buttress Panels with Caissons Sleeves

Panel Joint Shear Connection

Caisson Sleeves

Design Concept II: Section D ‐ D

Construction Sequence1. Guide Wall

1.

Page 12: 06 Fantaye PPT muros colados

12

Design Concept II: Section D ‐ D

Construction Sequence1. Guide Wall2. T‐Panel

2.

Design Concept II: Section D ‐ D

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel

3.

Perm

anent

Temporary

Page 13: 06 Fantaye PPT muros colados

13

Design Concept II: Section D ‐ D

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor

4.

High Tension Resistance 

Design Concept II: Section D ‐ D

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons

5.

High Shear Resistance

High Compressive Resistance

Page 14: 06 Fantaye PPT muros colados

14

Design Concept II: Section D ‐ D

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)

6.

Design Concept II: Section D ‐ D

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker

7.

7.

Page 15: 06 Fantaye PPT muros colados

15

Design Concept II: 3D – Wale & Raker

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker8. Excavate (stage 2)

Design Concept II: Section D ‐ D

8.

Embedded Plate for Truss Connection.

Page 16: 06 Fantaye PPT muros colados

16

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker8. Excavate (stage 2)9. Truss between 

buttresses

Design Concept II: Section D ‐ D

9.

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker8. Excavate (stage 2)9. Truss between 

buttresses10.Repeat steps 8 and 9/

Excavate to finalsubgrade

Design Concept II: Section D ‐ D

Detail

10.

10.

Page 17: 06 Fantaye PPT muros colados

17

3D Model: Buttress supported slurry wall

Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker8. Excavate (stage 2)9. Truss between 

buttresses10.Repeat steps 8 and 9/

Excavate to finalsubgrade

Design Concept II: Section D ‐ D

Detail

10.

10.

Detail

Page 18: 06 Fantaye PPT muros colados

18

Panel Joint Continuity: Shear across joint

Construction Sequence1. Trenching (T‐panel)

1.

Excavated slurry filled trench Unexcavated

Panel Joint Continuity: Shear across joint

Construction Sequence1. Trenching (T‐panel)2. Panel joint connector

2.

W‐Section

Hooked‐welded reinforcing bars

Removable gate

Page 19: 06 Fantaye PPT muros colados

19

Panel Joint Continuity: Shear across joint

Construction Sequence1. Trenching (T‐panel)2. Panel joint connector3. Reinforcing Cage

3.

Panel Joint Continuity: Shear across joint

Construction Sequence1. Trenching (T‐panel)2. Panel joint connector3. Reinforcing Cage4. Tremie Pour T‐panel

4.

Page 20: 06 Fantaye PPT muros colados

20

Panel Joint Continuity: Shear across joint

Construction Sequence1. Trenching (T‐panel)2. Panel joint connector3. Reinforcing Cage4. Tremie Pour T‐panel5. Trenching (Buttress panel)

5.

Panel Joint Continuity: Shear across joint

Construction Sequence1. Trenching (T‐panel) 6. Lift gate2. Panel joint connector3. Reinforcing Cage4. Tremie Pour T‐panel5. Trenching (Buttress panel)

6.

Page 21: 06 Fantaye PPT muros colados

21

Panel Joint Continuity: Shear across joint

Construction Sequence1. Trenching (T‐panel) 6. Lift gate2. Panel joint connector 7. Reinforcing Cage3. Reinforcing Cage4. Tremie Pour T‐panel5. Trenching (Buttress panel)

7.

Panel Joint Continuity: Shear across joint

Construction Sequence1. Trenching (T‐panel) 6. Lift gate2. Panel joint connector 7. Reinforcing Cage3. Reinforcing Cage 8. Tremie Pour buttress4. Tremie Pour T‐panel5. Trenching (Buttress panel)

8.

Page 22: 06 Fantaye PPT muros colados

22

3D: Finite Element Analysis – Risa 3D

Back‐calculated from observed wall deformations

Tamaro and Cermak (2004)

Finite Element Analysis: Soil Parameters

Page 23: 06 Fantaye PPT muros colados

23

3D: Finite Element Analysis – Plaxis 3D

1. Plaxis 3D Foundation2. 15‐node wedge element3. Number of elements: 119044. Soil Layers: Hardening Soil Model

3D: Finite Element Analysis – Plaxis 3D

Buttress

Raker

Wale

Tiedowns

OriginalWallPosition

1 in.

Truss

Page 24: 06 Fantaye PPT muros colados

24

Performance: Instrumentation Plan

Inclinometer in Slurry Wall

Performance: Inclinometer IPI‐11

Page 25: 06 Fantaye PPT muros colados

25

Performance: Inclinometer IPI‐11

3D Finite Element Analysis

Performance: Inclinometer IPI‐14

Page 26: 06 Fantaye PPT muros colados

26

Performance: Inclinometer IPI‐14

3D Finite Element Analysis

Summary:

1.Conventional tieback anchors could not be used.

2.Buttress walls, an innovative earth retaining solution, were implemented successfully –with no damage to the adjacent structures.

3.The estimated wall deformations match the field measured data. Back‐calculated soil parameters  were the key for the reasonable estimation.

Page 27: 06 Fantaye PPT muros colados

27

Photo: Looking East

Photo: Looking South

Page 28: 06 Fantaye PPT muros colados

28

Photo: Looking South

Photo: Looking East

Page 29: 06 Fantaye PPT muros colados

29

3D Model: Buttress supported slurry wall

Questions?