06 Fantaye PPT muros colados
-
Upload
alfredo-a-lopez -
Category
Documents
-
view
218 -
download
0
description
Transcript of 06 Fantaye PPT muros colados
1
Design and Performance of the Buttress Wall at Vehicular Security Center, World
Trade Center New York City, NY
Mueser Rutledge Consulting Engineers14 Penn Plaza – 225 West 34th StreetNew York, NY 10122917-339-9300
Sitotaw Y. Fantaye, P.E., AssociateLixun Sun, PhDT.C. Michael Law, PhD, P.E., Associate
Site Photo: Taken December 2010
2
Site Plan: Vehicle Security Center
L i b e r t y S t r e e t
A l b a n y S t r e e t
W o r l d T r a d e C e n t e r
Outline of VSC Basement Walls
C e d a r S t r e e t
90 West(20‐StoryHistoricBuilding)
130 Cedar Street
Cutoff wall phase 1
• Owner – Port Authority of NY and NJ
• Contractor – EE Cruz/ Nicholson JV
• Engineer of Record – Liberty Security Partners/ Mueser Rutledge Consulting Engineers
Acknowledgements:
3
• Essential facility for the function of the WTC
• Vehicle screening and tour bus parking
• Southern expansion of the WTC
• Entirely below grade structure
• Plan area of 200 x 400 feet
• 60 to 100 feet of excavation
• Groundwater 10 feet below grade
• Excavation support required on 3 sides (West, South and East) – Existing original WTC wall on North
• Proposed wall along south located against the vault of an existing historic 20 story structure – 90 West
Background: Vehicle Security Center
A A
Site Plan: Vehicle Security Center
4
B
B
Geologic Profile: Section A ‐ A
130 Cedar Street
90 West Street
Rock
Fill
Organic
Sand
Decomposed Rock
310
300
290
280
270
260
250
240
Elevation(PA DATUM)
Till
Geologic Cross‐section: Section B ‐ B
Organic
Sand
Fill
Till
Rock
SlurryWall
56 Ft. Excavation
90 West St20-Story Historic Building
TimberPiles
5
Design Concept I: Slurry Wall
• Construct slurry wall at VSC perimeter
Slurry Wall
V A U L T / S I D E W A L K
Existing high rise structures with one basement level supported on piles
Design Concept I: Stand‐off frame
V A U L T / S I D E W A L K
Existing high rise structures with one basement level supported on piles
• Excavate and install stand-off frame using pin piles to allow installation of tieback anchors below the tip elevation of the timber piles supporting the Historic 90 West Building
Stand-Off Frame
6
C
C
Design Concept I: Tieback Anchors
• Install tieback anchors
Tieback Anchors
Construction Sequence1. Guide Wall
Design Concept I: Section C ‐ C
1.
7
Design Concept I: Section C ‐ C
Construction Sequence1. Guide Wall2. Slurry Wall
2.
Design Concept I: Section C ‐ C
Construction Sequence1. Guide Wall2. Slurry Wall3. Pin Pile
3.
8
Design Concept I: Section C ‐ C
Construction Sequence1. Guide Wall2. Slurry Wall3. Pin Pile4. Excavate (stage 1)
4.
Design Concept I: Section C ‐ C
Construction Sequence1. Guide Wall2. Slurry Wall3. Pin Pile4. Excavate (stage 1)5. Wale/blocking/tieback
anchor
5.5.5.
9
Design Concept I: Section C ‐ C
Construction Sequence1. Guide Wall2. Slurry Wall3. Pin Pile4. Excavate (stage 1)5. Wale/blocking/tieback
anchor6. Repeat steps 4 & 5/
Excavate to final subgrade
6.
6.
6.
Design Concept I:Why not used?
1. Stand‐off frame would interfere with the future structure
2. 90 West did not allow tieback anchors below their building
10
Design Concept II: T‐Panels
• Construct T-Panels/ first segment of buttress wall with tiedownsleeves
V A U L T / S I D E W A L K
Existing high rise structures with one Basement level supported on piles
Panel joint shear connection
Stem
FlangeTiedownSleeves
Design Concept II: Secondary Panels
V A U L T / S I D E W A L K
Existing high rise structures with one basement level supported on piles
• Construct Secondary panels between T-Panels
Secondary panels
11
D
D
Design Concept II: Buttress Panels
• Construct Buttress Panels with Caissons Sleeves
Panel Joint Shear Connection
Caisson Sleeves
Design Concept II: Section D ‐ D
Construction Sequence1. Guide Wall
1.
12
Design Concept II: Section D ‐ D
Construction Sequence1. Guide Wall2. T‐Panel
2.
Design Concept II: Section D ‐ D
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel
3.
Perm
anent
Temporary
13
Design Concept II: Section D ‐ D
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor
4.
High Tension Resistance
Design Concept II: Section D ‐ D
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons
5.
High Shear Resistance
High Compressive Resistance
14
Design Concept II: Section D ‐ D
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)
6.
Design Concept II: Section D ‐ D
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker
7.
7.
15
Design Concept II: 3D – Wale & Raker
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker8. Excavate (stage 2)
Design Concept II: Section D ‐ D
8.
Embedded Plate for Truss Connection.
16
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker8. Excavate (stage 2)9. Truss between
buttresses
Design Concept II: Section D ‐ D
9.
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker8. Excavate (stage 2)9. Truss between
buttresses10.Repeat steps 8 and 9/
Excavate to finalsubgrade
Design Concept II: Section D ‐ D
Detail
10.
10.
17
3D Model: Buttress supported slurry wall
Construction Sequence1. Guide Wall2. T‐Panel3. Buttress Panel4. Tie‐down Anchor5. Caissons6. Excavate (stage 1)7. Wale/Raker8. Excavate (stage 2)9. Truss between
buttresses10.Repeat steps 8 and 9/
Excavate to finalsubgrade
Design Concept II: Section D ‐ D
Detail
10.
10.
Detail
18
Panel Joint Continuity: Shear across joint
Construction Sequence1. Trenching (T‐panel)
1.
Excavated slurry filled trench Unexcavated
Panel Joint Continuity: Shear across joint
Construction Sequence1. Trenching (T‐panel)2. Panel joint connector
2.
W‐Section
Hooked‐welded reinforcing bars
Removable gate
19
Panel Joint Continuity: Shear across joint
Construction Sequence1. Trenching (T‐panel)2. Panel joint connector3. Reinforcing Cage
3.
Panel Joint Continuity: Shear across joint
Construction Sequence1. Trenching (T‐panel)2. Panel joint connector3. Reinforcing Cage4. Tremie Pour T‐panel
4.
20
Panel Joint Continuity: Shear across joint
Construction Sequence1. Trenching (T‐panel)2. Panel joint connector3. Reinforcing Cage4. Tremie Pour T‐panel5. Trenching (Buttress panel)
5.
Panel Joint Continuity: Shear across joint
Construction Sequence1. Trenching (T‐panel) 6. Lift gate2. Panel joint connector3. Reinforcing Cage4. Tremie Pour T‐panel5. Trenching (Buttress panel)
6.
21
Panel Joint Continuity: Shear across joint
Construction Sequence1. Trenching (T‐panel) 6. Lift gate2. Panel joint connector 7. Reinforcing Cage3. Reinforcing Cage4. Tremie Pour T‐panel5. Trenching (Buttress panel)
7.
Panel Joint Continuity: Shear across joint
Construction Sequence1. Trenching (T‐panel) 6. Lift gate2. Panel joint connector 7. Reinforcing Cage3. Reinforcing Cage 8. Tremie Pour buttress4. Tremie Pour T‐panel5. Trenching (Buttress panel)
8.
22
3D: Finite Element Analysis – Risa 3D
Back‐calculated from observed wall deformations
Tamaro and Cermak (2004)
Finite Element Analysis: Soil Parameters
23
3D: Finite Element Analysis – Plaxis 3D
1. Plaxis 3D Foundation2. 15‐node wedge element3. Number of elements: 119044. Soil Layers: Hardening Soil Model
3D: Finite Element Analysis – Plaxis 3D
Buttress
Raker
Wale
Tiedowns
OriginalWallPosition
1 in.
Truss
24
Performance: Instrumentation Plan
Inclinometer in Slurry Wall
Performance: Inclinometer IPI‐11
25
Performance: Inclinometer IPI‐11
3D Finite Element Analysis
Performance: Inclinometer IPI‐14
26
Performance: Inclinometer IPI‐14
3D Finite Element Analysis
Summary:
1.Conventional tieback anchors could not be used.
2.Buttress walls, an innovative earth retaining solution, were implemented successfully –with no damage to the adjacent structures.
3.The estimated wall deformations match the field measured data. Back‐calculated soil parameters were the key for the reasonable estimation.
27
Photo: Looking East
Photo: Looking South
28
Photo: Looking South
Photo: Looking East
29
3D Model: Buttress supported slurry wall
Questions?