"Every well needs one"SPE Aberdeen 4th European Well Abandonment Seminar
© 2012 BAKER HUGHES INCORPORATED. ALL RIGHTS RESERVED. TERMS AND CONDITIONS OF USE: BY ACCEPTING THIS DOCUMENT, THE RECIPIENT AGREES THAT THE DOCUMENT TOGETHER WITH ALL INFORMATION INCLUDED THEREIN IS THE CONFIDENTIAL AND PROPRIETARY PROPERTY OF BAKER HUGHES INCORPORATED AND INCLUDES VALUABLE TRADE SECRETS AND/OR PROPRIETARY INFORMATION OF BAKER HUGHES (COLLECTIVELY "INFORMATION"). BAKER HUGHES RETAINS ALL RIGHTS UNDER COPYRIGHT LAWS AND TRADE SECRET LAWS OF THE UNITED STATES OF AMERICA AND OTHER COUNTRIES. THE RECIPIENT FURTHER AGREES THAT THE DOCUMENT MAY NOT BE DISTRIBUTED, TRANSMITTED, COPIED OR REPRODUCED IN WHOLE OR IN PART BY ANY MEANS, ELECTRONIC, MECHANICAL, OR OTHERWISE, WITHOUT THE EXPRESS PRIOR WRITTEN CONSENT OF BAKER HUGHES, AND MAY NOT BE USED DIRECTLY OR INDIRECTLY IN ANY WAY DETRIMENTAL TO BAKER HUGHES’ INTEREST.
Version 2.0
Ole Petter Nipen – Baker Hughes
![Page 2: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/2.jpg)
Agenda
� Introduction to TOGI Subsea P&A project
�Scope of work
�P&A operation Step by Step
�Big Fishing �Big Fishing
2 © 2013 Baker Hughes Incorporated. All Rights Reserved.
![Page 3: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/3.jpg)
TOGI P&A Project
� 6 slot wellhead structure,
5 wells drilled in 1990
� All ROV operated
� 300 m water depth
� Closed in down since 2002
© 2013 Baker Hughes Incorporated. All Rights Reserved. 3
![Page 4: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/4.jpg)
Scope of work
Batch P&A of 5 wells:
� Pull completion
� Log 9 5/8” casing
� Place 1st barrier
� Cut & Pull 9 5/8” Casing
� Place 2nd barrier
© 2013 Baker Hughes Incorporated. All Rights Reserved. 4
� Cut & Pull 13 3/8” casing
� Surface plug
� Remove wellhead, 30” and
42” casing
Contingency:
� Mill seal assembly
� Section mill 9 5/8” & 13 3/8”
� Casing mill 9 5/8”
� Cut & Pull 9 5/8” in one run
![Page 5: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/5.jpg)
Pull Completion
Operational steps
� Pull tubing with THRT
� Tubing pulled down to PBR
© 2013 Baker Hughes Incorporated. All Rights Reserved. 5
![Page 6: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/6.jpg)
9 5/8” X 10 ¾” section
� Log 9 5/8” X 10 ¾” Casing
� Place 1st Barrier Plug
� Cut 10 ¾” Casing Below Hanger
© 2013 Baker Hughes Incorporated. All Rights Reserved. 6
� Pull 10 ¾” Seal Assembly
� Remove 10 ¾” X 9 5/8” Casing
![Page 7: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/7.jpg)
Remove 10 ¾” seal assembly
© 2013 Baker Hughes Incorporated. All Rights Reserved. 7
![Page 8: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/8.jpg)
Remove 10 ¾” seal assembly
© 2013 Baker Hughes Incorporated. All Rights Reserved. 8
10 ¾” Seal Assembly and casing hanger
Mill 7 Seal Assembly
![Page 9: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/9.jpg)
Remove 10 ¾” x 9 5/8” casing
� Cut & Pull in same run
� Cut in tension
� Pull up to max overpull prior to cut
� Pre-defined section cutted
© 2013 Baker Hughes Incorporated. All Rights Reserved. 9
� Saved eight run
![Page 10: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/10.jpg)
Casing Mill
� Mill 58 meter of 9 5/8” Casing
� ROP was limited by swarf handling
� Small swarf
Define max ROP upfront!
© 2013 Baker Hughes Incorporated. All Rights Reserved. 10
Define max ROP upfront!
55
![Page 11: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/11.jpg)
Contingency
� Contingency on all wells
� 9 5/8” & 13 3/8”
© 2013 Baker Hughes Incorporated. All Rights Reserved. 11
![Page 12: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/12.jpg)
13 3/8” section
� Log 13 3/8” Casing
� Place 2nd Barrier Plug
� Pull 13 3/8” Seal Assembly
© 2013 Baker Hughes Incorporated. All Rights Reserved. 12
� Remove 13 3/8” Casing
![Page 13: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/13.jpg)
18 5/8” section
� Set 18 5/8” Mechanical Plug
� Place Surface Cement Plug
� Cut & Pull 18 5/8”
© 2013 Baker Hughes Incorporated. All Rights Reserved. 13
� Cut & Pull 30”
� Cut & Pull 42”
![Page 14: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/14.jpg)
Big Fishing
1. Remove 18 5/8” wellhead (Blue)
2. Remove 30” Conductor (Red)
3. Remove 42” Washout sleeve (Green)
Shear at 136 ton
© 2013 Baker Hughes Incorporated. All Rights Reserved. 14
![Page 15: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/15.jpg)
Cut & Pull 18 5/8” Wellhead
D-spear
� Two Trip Solutions
� Dressed to catch ID:18,000"-19,162"
© 2013 Baker Hughes Incorporated. All Rights Reserved. 15
D-spear Wellhead
![Page 16: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/16.jpg)
Cut 30”
© 2013 Baker Hughes Incorporated. All Rights Reserved. 16
![Page 17: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/17.jpg)
Pull 30” Conductor
© 2013 Baker Hughes Incorporated. All Rights Reserved. 17
����
E-spear
20 ¾” D-spear
![Page 18: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/18.jpg)
Cement?
� Cement above 42” hanger and inside template housing!
© 2013 Baker Hughes Incorporated. All Rights Reserved. 18
45 ½” Cement MillCement outside of 30”
![Page 19: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/19.jpg)
Cut 42”
© 2013 Baker Hughes Incorporated. All Rights Reserved. 19
MS-Cutter with Stabilizer 42” Conductor cut
![Page 20: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/20.jpg)
Pull 42”
Remove 42” Washout sleeve (green)
� Catch 38,5”
© 2013 Baker Hughes Incorporated. All Rights Reserved. 20
Modified E-Spear
Stack-Up Test
42” Conductor on Deck
![Page 21: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/21.jpg)
Big Fishing
Movie
© 2013 Baker Hughes Incorporated. All Rights Reserved. 21
![Page 22: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/22.jpg)
TOGI P&A Project – Sum up
Operational time: 1208.4 hrs
Downtime: 4.5 hrs
Operational factor: 99.62%
Mill 9 5/8” & 13 3/8” Seal Assembly: 7 seal assy milled
Cut operation of 9 5/8”, 10 ¾” & 13 3/8”: 16 run
© 2013 Baker Hughes Incorporated. All Rights Reserved. 22
Cut operation of 9 5/8”, 10 ¾” & 13 3/8”: 16 run
Cut & pull operation with Spear, and motor: 8 run!
Pulling & Cutting operation: 25 run
9 5/8” casing milled: 58 meter
![Page 23: 04 Nipen Baker Hughes](https://reader031.fdocuments.in/reader031/viewer/2022013115/563dbb61550346aa9aaca4f6/html5/thumbnails/23.jpg)
TOGI P&A Project – Sum up
� Robust fishing package offshore
� Standardise BHA`s
� Milling Seal Assembly
� Back-up equipment for Big Fishing Tools
� Personnelo Planning and follow up operation
o Operators offshore
© 2013 Baker Hughes Incorporated. All Rights Reserved. 23
Operational factor: 99.62%