Pearl GTL Project
LINDE ENGINEERING
Shell Project No: HP-3000-QAT Contractor Project No : 5887
Project Document Number: T- 4.250.925 Project Rev.: B Page 2 of 22
Purchase Order Number:
2MH127
Tag/Item Number(s): FA-21,FB-21,FC-21 and FD-21 & GA-21,GB-21,GC-21 and GD-21
Unit(s): ASU
PCWBS: Z
-
QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION
G B 17.09.08 Issued for Review SK EO AG IFR
F A 31.08.08 Ready for Construction SK EO AG RFC
E A 21.07.08 Ready for Construction SK EO AG RFC
D O 15.06.08 Issued for Company Comments SK EO AG ICC
C O 10.06.08 Issued for Company Comments SK EO AG ICC
B 10.06.08 Issued for review SK EO AG IFR
A 09.06.08 Issued for internal review SK EO AG IIR
GAMA Rev.
Project Rev Date Description
Prepared By
Checked By
Approved By
Status
No. No. ORIGINATOR
LINDE ENGINEERING AG
Document Title:
ITP FOR INSTALLATION OF COLD BOXES
Contractor
Gama Qatar Co. W. L. L.
Document No. LOC470
GAM ITP QAC GTL 038 G
Org. Code
Doc. Type
Disc. Code
Geogr. Area
Seq. No
Rev. No Vendor Code
Project Document Number: T-4.250.925
Rev No: B
-
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-038
ITP FOR INSTALLATION OF COLD BOXES DATE: 17.09.08 REV. G
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test Frequency Reference Document Acceptance Criteria Responsible
Party Verifying Documents S X C A
T-4.250.925 Rev. B Page 4 of 22
1.0
GENERAL
1.1 Contractor drawings, project specifications, manuals, codes 100%
TECHINICAL OFFICE H R R
1.2 Lifting studies (For Heavy Equipments) 100%
T.4.234.084; T-4.250.970 HSSE H R R
R
1.3 Paint /Galvanize touch up 100% Refer Painting ITP T.4.250.919/T.4.096.672 QCI GAM-QCR-QAC-GTL-056 I S S
1.4 Procedures 100% T.4.250.947;T.4.258.501
T-4.250.968 , T.4.096.711 - QCI Verify the documents R R R
1.5 Foundations complete and accepted
100% T-4.250.947 Approved drawing DEP
34.19.20.31 T.13.376.359E;T.4.258.501
QCI GAM-QCR-QAC-GTL-113 I W/R S
1.6 Foundation chipping to sound metal
100% T-4.250.968 T.13.377.803
Approved drawing, DEP 34.19.20.31;
T.13.376.358;T.4.258.501 QCI GAM-QCR-QAC-GTL-113 I S S
1.7 Anchor bolts control & pocket cleaning
100% T-4.250.968 ,T-4.250.970
T.13.377.803
Approved drawing DEP 34.19.20.31 T.13.376.358;
T.4.258.501 QCI GAM-QCR-QAC-GTL-113 I S S
-
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-038
ITP FOR INSTALLATION OF COLD BOXES DATE: 17.09.08 REV. G
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test Frequency Reference Document Acceptance Criteria Responsible
Party Verifying Documents S X C A
T-4.250.925 Rev. B Page 5 of 22
2.0 EQUIPMENT
2.1 Equipment identification and name plate verification 100%
T-4.258.501 T-4.250.947
Approved drawing DEP 31.10.03.10, DEP
31.21.01.30,T.4.258.501 1.0
STORE
INCHARGE GAM-QCR-QAC-GTL-080 I S S
2.2 Receiving inspection 100% T.4.258.501; T-4.258.501
Approved drawing DEP 31.10.03.10,
T.4.258.501
STORE
INCHARGE GAM-QCR-QAC-GTL-080 I S S
2.3 Storage, preservation and documentation (FSI) 100%
T.4.258.501; T.13.377.360.E, T.13.376.921G
Approved drawing, DEP 70.10.70.11,
T.4.258.501,Vendor instruction
QCI GAM-QCR-QAC-GTL-069 I S S
2.4
Inspection measuring and test equipment calibration
100% T-4.250.915, Valid Certificate QCI Calibration certificate H R R
-
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-038
ITP FOR INSTALLATION OF COLD BOXES DATE: 17.09.08 REV. G
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test Frequency Reference Document Acceptance Criteria Responsible
Party Verifying Documents S X C A
T-4.250.925 Rev. B Page 6 of 22
3.0 COLD BOX EQUIPMENTS
3.1 HEX BOX
3.1.1 Installation 100% T-4.250.947 T-4.258.501
Approved Drawing; DEP 31.21.01.32; T.13.376.351G,
T.4.121.350
QCI GAM-QCR-QAC-GTL-148 I S W
3.1.2 Alignment/Elevation 100% T-4.250.947 T.4.258.501
DEP 31.21.01.32; T.13.377.803G,
T.4.258.501 QCI GAM-QCR-QAC-GTL-115 I W/R I
3.1.3 Welding 100% T.4.258.501 T.13.377.441;DEP
61.40.20.30;T.13.376.796E;T.4.258.501
QCI GAM-QCR-QAC-GTL-098 I S W
3.1.4 Safety Valves (If any) 100% T.4.250.918 T.13.377.360
DEP80.46.30.11 DEP 31.38.01.31 T.13.376.796E
QCI GAM-QCR-QAC-GTL-091 I S S
3.1.5 Final Bolting up / torque 100% T.4.250.897 Approved drawings; DEP
31.29.00.10,Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-041 I S/R S
-
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-038
ITP FOR INSTALLATION OF COLD BOXES DATE: 17.09.08 REV. G
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test Frequency Reference Document Acceptance Criteria Responsible
Party Verifying Documents S X C A
T-4.250.925 Rev. B Page 7 of 22
3.1.6 Grouting 100% T-4.250.970
T.4.234.545 DEP 34.19.20.31
T.13.376.358; T.4.258.501 QCI GAM-QCR-QAC-GTL-025 I S S
3.2
RECTIFICATION BOX
3.2.1 Installation 100% T-4.250.947 T-4.258.501
Approved Drawing DEP 31.21.01.32;T.13.376.351G,
T.4.121.350 QCI GAM-QCR-QAC-GTL-148 I S W
3.2.2 Alignment/Elevation (FSI) 100% T-4.250.947 T.4.258.501
DEP 31.21.01.32; T.13.377.803G, T.4.258.501
QCI GAM-QCR-QAC-GTL-115 I W/R I
3.2.3 Welding 100% T.4.258.501 T.13.377.441;DEP
61.40.20.30;T.13.376.796E;T.4.258.501
QCI GAM-QCR-QAC-GTL-098 I S W
3.2.4 Safety Valves 100% T.4.250.918 T.13.377.360
DEP80.46.30.11 DEP 31.38.01.31 T.13.376.796E
QCI GAM-QCR-QAC-GTL-091 I S S
3.2.5 Final Bolting up / torque 100% T.4.250.897 Approved drawings; DEP
31.29.00.10,Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-041 I S/R S
3.2.6 Grouting 100% T-4.250.970
T.4.234.545 DEP 34.19.20.31
T.13.376.358; T.4.258.501 QCI GAM-QCR-QAC-GTL-025 I S S
3.3 Interconnecting Piping/Valves
-
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-038
ITP FOR INSTALLATION OF COLD BOXES DATE: 17.09.08 REV. G
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test Frequency Reference Document Acceptance Criteria Responsible
Party Verifying Documents S X C A
T-4.250.925 Rev. B Page 8 of 22
3.3 Valves/Strainers
3.3.1 Installation of Valves 100% T.4.250.918 DEP 31.38.01.31,
T.13.376.815E;Approved Drawings
QCI GAM-QCR-QAC-GTL-091 I S S
4.0 COLD BOXES
4.1 Erection Damage(Equipments) 100% T-4.251.035 - QCI GAM-QCR-QAC-GTL-127 I I W
4.2 Repair works 100% T-4.251.035 Method Statement QCI GAM-QCR-QAC-GTL-127 H R W
4.3 General Punch List (Clearing) 100% T-4.250.947 - QCI GAM-QCR-QAC-GTL-128 H R S
4.4 Equipment Box up 100% T-4.250.947 - QCI GAM-QCR-QAC-GTL-133 I W W
4.5 Operation and maintenance Instructions
100% O & M's Available for all Equipment QCI - R R R
4.6 Equipment Manufacture Data Books
100% Equipment Data Books Available for all Equipment QCI - R R R
4.7 Quality Documents 100% Quality Documents T.13.377.555G QCI Inspection Reports R R R
-
C2-ASU PROJECT
GAMA QATAR
GROUT POUR CARD(PRE/POST POUR) Form No: GAM-QCR-QAC-GTL-025 Inspection Gr.:
ITP No.: Laboratory:
Record No: Date:
TAG NO.: LOCATION:
DESCRIPTION: DRAWING:
TYPE OF GROUT: QUANTITY OF GROUT:
Item
No.
TYPE OF ACTIVITY
GAMA/T Const. GAMA/T - QC CONTRACTOR COMPANY REMARKS
Signature Date Signature Date Signature Date Signature Date 1.0 Setting Out 2.0 Concrete Surface Preparation
3.0 Equipment / Surface Alignment
4.0 Formworks
5.0 Isolation Joint
6.0 Metal Surface Preparation
7.0 Mixing / Placing / Finishing of Grout (1) 8.0 Curing of Grout (1)
9.0 Removal of Shims
10.0 Mixing / Placing / Finishing of Grout (2)
11.0 Curing of Grout (2)
12.0 Sealant to Isolation Joint
13.0 Final Inspection
Remarks:
Full Name/Signature/Date
GAMA QATAR CONTRACTOR COMPANY
-
GAM-QCR-QAC-GTL-041
C2 ASU PEARL GTL PROJECT RASLAFFAN INDUSTRIAL CITY
BOLT TIGHTENING INSPECTION REPORT
Subcontract Ref.: Report No.:
Item Description: Inspection Date: Item Location / Area: Test Code No.:
Subsystem: ITP No.:
Ref. DWG / Docs:
Used Measuring and test equipment ref. (if applicable):
INSPECTIONS Bolting Item No/Spool
No Mark No./Joint No
Grade Size Bolt Tightening (Torque Value)
Inspectors Signature
ORGANIZATIONS DATE NAME SIGNATURE
THIRD PARTY REP.
GAMA REP.
LINDE REP.
Acce
pted
By
QSGTL OR its PMC REP.
-
GAM-QCR-QAC-GTL-056
C2 ASU PEARL GT PROJECT RAS LAFFAN INDUSTRIAL CITY
REPAIR & TOUCHUP PAINTING INSPECTION REPORT
Subcontract Ref.: Report No.: Item Description: Inspection Date: Item Location / Area: Test Code No.: 4.7 Subsystem: ITP No.: T-4-250-916 Ref. DWG / Documents: Paint Spec: Used Measuring and test equipment ref. (if applicable): Working Conditions Internal / External Insp. Equipment Used Identification #
1. Hygrometer Time (hrs.) 2. DP / RH Calculator Air Temp
WB 3. Temperature Gauge (O C) DB 4. WFT Gauge
Dew Point (O C) 5. DFT Gauge Relative Humidity %
Metal Temp. (O C)
SURFACE PREPARATION
From: ________________
To: ________________
Method of Cleaning
PAINT APPLICATION
From: ______________ hrs. To: _______________ hrs.
Coating Manufacturer: Airless Spray Machine Sl. No. Paint: Product/Coat
Batch No. Mix Ratio
Application Methods
Colour WFT DFT Total DFT
Overcoat
Time A. B. A. B. A. B. Remarks:
ORGANIZATIONS DATE NAME SIGNATURE
Acce
pted
By THIRD PARTY REP.
GAMA REP.
LINDE REP.
QSGTL or its PMC REP.
QQQ AAA TTT AAA RRR
-
PROJECT: C2 ASU PEARL GTL PROJECT, RAS LAFFAN INDUSTRIAL CITY
EQUIP. TAG.NO.: DESCRIPTION: LOCATION:
MANUFACTURER: DRG.NO.: RFI NO:
MONTH
1 2
3 4 5 6
7
8
9
10
11
12
ACTIVITY Month
Date Checked
Check all internal and accessories storage is acceptable
Visual Check : Is there any damage
Check for protective covers on all the openings
Check all warning labels,like N2 warning plate are existent
Check Purge Pressure level
If Re-purge is required, indicate pressure level
GAMA SIGN WITH DATE
LINDE SIGN WITH DATE
QSGTL or its PMC
NOTE:
GAM-QCR-QAC-GTL-069
STORAGE, PRESERVATION AND NITROGEN PURGING REPORT
FORM NO:
SHT:
-
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
GAM-QCR-QAC-GTL-080
EQUIPMENT RECEIPT CHECK SHEET
ITEM No: PO No: REQ No:
UNIT No: MANUFACTURER :
ITEMS TO BE CHECKED INSPECTOR
INITIAL REMARKS
1 Name Plate
2 Preparation and painting
3 Desiccant installed
4 Moisture present
5 Nozzle flange faces acceptable
6 Temporary nozzle protection acceptable
7 Internals and accessories complete and storage acceptable
8 Purge - pressure:
Purge monitoring date: Pressure
Date of initial inspection:
Name and signature of Inspector:
-
Report No:
PIPING FINAL INSPECTION REPORT Date:
PROJECT: C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
TESTPACK NO SYSTEM AREA LINE NO DRG NO SHEET NO REV
PIPE CLASS INSPN. CLASS MATERIAL
Verified by (Signature) Sl. No. Inspection Description
GAMA LINDE QSGTL Date
1 Location & Orientation of Piping
2 Elevation & Levelness of Piping
3 Verticality (Plumb) of Piping
4 Type and Location of Support Installed
5 Type and Location of Valve Installed
6 Flow direction of Valve Installed
7 Vent hole location of Valve Installed
8 Flange face Inspection
9 Flange alignment to the Equipment
10 Installation of inline items
11 Installation of Gaskets
12 Installation of correct Bolts and Nuts/studs
Remarks
THE ABOVE INSPECTIONS HAVE BEEN CARRIED OUT AND FOUND SATISFACTORY IN ACCORDANCE WITH THE ISOMETRIC DRAWING AND PROJECT SPECIFICATIONS/REQUIREMENTS.
ORGANIZATIONS DATE NAME SIGNATURE GAMA QATAR REP
LINDE REP
QSGTL or its PMC
GAM-QCR-QAC-GTL-091
QQQ AAA TTT AA RRRA
-
PROJECT : C2 ASU PEARL GTL PROJECT-- RAS LAFFAN INDUSTRIAL CITY
Date : Page :
SHOP FIELDWeld Piping Insp. Welder Welder PWHT
Area System Sheet DWG Rev. Sp'l No. Class Class 1 2 Req'd Req'd % Fit-up/Root Final
Gama Qatar Rep
Linde RepQSGTL or its PMC
ORGANIZATIONS DATE NAME SIGNATURE
REPORT No. :
DAILY WELDING REPORT
Mat'l Dia SchISOMETRIC NUMBER WPS No. RemarksInspection ResultNDE
QQQ AAA TTT AAA RRR
GAM-QCR-QAC-GTL-098
-
FOUNDATION INSPECTION REPORT
Report No:
Date:
PROJECT: C2 ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL CITY
Tag No: Drg. No:
Area: Unit: Plot Plan:
ELEVATION 0 90 180 270
REQUIRED ACTUAL DEVIATION TOLERANCE REMARKS
ORIENTATION ACCEPTED REJECTED POCKET CLEANING ACCEPTED REJECTED
REQUIRED ACTUAL DEVIATION TOLERANCE REMARKS
NO. OF ANCHOR BOLTS ANCHOR BOLT DIA ANCHOR BOLT LENGTH FOUNDATION POCKET POCKET DEPTH
FOUNDATION CHIPPING REQUIRED NOT REQUIRED IF REQUIRED THICKNESS
NOTE:
THE ABOVE MENTIONED FOUNDATION IS ACCEPTED AND RELEASED FOR ERECTION ACTIVITIES
GAMA LINDE QSGTL or its PMC
Name
Sign
Date
GAM-QCR-QAC-GTL-113
-
Report No:
EQUIPMENT LEVELLING & ALIGNMENT REPORT Date:
PROJECT: C2 ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL CITY
Tag No: Manufacturer: Drg. No:
Equip. Description
No. of reading Orientation Elevation Plumpness Tolerance Remarks
ORIENTATION : ACCEPTED REJECTED
LEVELLING REQUIRED ACTUAL ACC REJECTED
GRADIENT / SLOPE REQUIRED
ACTUAL ACC REJECTED
GAM-QCR-QAC-GTL-115 PAGE 1 OF 2
-
REMARKS: ..
GAMA LINDE QSGTL or its PMC
Name
Sign
Date
GAM-QCR-QAC-GTL-115 PAGE 2 OF 2
-
PROJECT: C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Originator Date of observation:
Discipline:
Location / Area:
Unit No :
SYSTEM NUMBER:
Drawing / Specification Numbers Description of Discrepancy/Observation (Be specific, events, time, date, location, etc :)
Corrective Action:
Originator: Name: _____________________________Signature: _____________________Date: ________________ NCR Required YES NO (Circle one) CTQ to Contractor Required YES NO (Circle one) Remarks if any: Site Engineer: Name: _______________________ Signature: ________________ Date: ______________ QA/QC Manager: Name: _________________________ Signature: _______________ Date: ______________ Discrepancy Corrected/Remarks: GAMA Representative: Name: ____________________ Signature: ______________ Date: ________________ Close-out of Corrective Action - Remarks: NCR No.: ___________________ CTQ No: ______________ Site Engineer: Name: ___________________ Signature: __________________ Date: ___________ DISTRIBUTION (Original QA/QC file)
QA/QC Manager Site Manager
Site Engineer Project Manager
Construction Manager Originator GAM-QCR-QAC-GTL-127
REPORT NO.:
SITE INSPECTION REPORT
DATE:
-
Report No:Inspection Date:SYSTEM NUMBER:
TAG NUMBER:
LOOP FOLDER:
(A,B,C,D,E) (X,Y,Z)
GAMA REP
LINDE REP
QSGTL or its PMC
SIGNATURE
DESCRIPTION OF WORK QSGTL or its PMCGAMA LINDE
COMPLETED(Date/Initials)
DATE NAME
C2 ASU PEARL GTL PROJECT
GENERAL PUNCH LIST
RAS LAFFAN INDUSTRIAL CITY
Sub System:
ITEM NO ISO or DWG NUMBER
EQUIPMENT CIVIL STRUCTURAL PAINTING INSULATION
Sub contractor Ref:Item Description:Item Location / Area:
PRIORITY/ CATEGORY
Ref Dwg/Documents:
AC
CE
PTE
D B
Y
ORGANIZATIONS
ALL PRIORITY A ITEMS SHOWN ABOVE HAVE BEEN VERIFIED AND ARE COMPLETED .INCOMPLETE PRIORITY B ITEMS
CATEGORY X: CONSTRUCTION GROUP IS RESPONSIBLE FOR COMPLETION OF ITEM. CATEGORY Y: ENGINEERING INPUT IS REQUIRED FOR COMPLETION OF ITEM.
WILL BE TRANSFERRED TO THE MECHANICAL COMPLETION PUNCH LIST
CATEGORY Z: COMMISSIONING GROUP IS RESPONSIBLE FOR COMPLETION OF ITEM.
PRIORITY A : ITEMS SHALL BE COMPLETED BEFORE MECHANICAL COMPLETION (MC)PRIORITY B : ITEMS MAY BE COMPLETED AFTER MCPRIORITY C : ITEMS WILL BE COMPLETED BEFORE SYSTEM RFSU (READY FOR START UP UNIT) IS ACHIEVEDPRIORITY D : ITEMS SHALL BE COMPLETED BEFORE RFSU IS ACHIEVEDPRIORITY E : ITEMS SHALL BE COMPLETED BEFORE ACCEPTENCE IS ACHIEVED
QQQ AAA TTT AAA RRR
GAM-QCR-QAC-GTL-128
-
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Report No: Date: Area:
Equipment Box-Up Acceptance Sheet
QQQ AAA TTT AAA RRR
It is hereby certified that the Equipment referenced has been mechanically completed in accordance with Drawings, Specifications, Inspection and Test Records. The referenced Equipment is ready for box-up. Equipment No
Equipment Designation
Vendor / Manufacturer
PID No
C h e c k l i s t Accepted
GAMA Accepted VENDOR
Accepted LINDE
Accepted QSGTL
1 Name Plate, CE-marking (if applicable)
2 Internals installed 3 Internal piping installed
4 Fillings completed 5 Refractory completed
6 Internal transport protection removed
7 Equipment internally clean and dry
8 Nozzles / manholes closed acc. drawing
9 Specified blind flanges installed
10 Specified nozzle gaskets installed
11 Specified bolts and nuts installed
12 Specified torques applied
13 Bolts lubricated (covers, manholes)
14
Remarks /
ORGANIZATIONS
NAME
DATE
SIGNATURE
GAMA
VENDOR
LINDE
QSGTL or its PMC
GAM-QCR-QAC-GTL-133
-
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
COLD BOX INSTALLATION PROCESS SHEET
Item No: Report No: Item Description: Date: Drawing No: Area:
Item No
Description
Signature & Date Gama Linde QSGTL
1. Foundation, complete, level & accepted 2. Setting Plumb/ level Orientation correct Elevation correct Slide plate in place Anchor bolts tight Base plate grouted 3. Provision for expansion/ contraction checked 4. Piping Flanges aligned 5. Blind flanges on nozzles & plugs for couplings where required Remarks:
The installation of the above equipment has been satisfactorily completed in accordance with the Drawings & Specifications. ORGANIZATIONS
DATE NAME SIGNATURE
GAMA QATAR REP
LINDE REP
QSGTL REP
GAM-QCR-QAC-GTL-148
QQQ AAA TTT AAA RRR
091-PIPING FINAL INSPECTION REPORT.pdfPIPING FINAL INSPECTION REPORTReport No:Date:
127-SITE INSPECTION REPORT.pdfSITE INSPECTION REPORTOriginatorDD
091-PIPING FINAL INSPECTION REPORT.pdfPIPING FINAL INSPECTION REPORTReport No:Date:
127-SITE INSPECTION REPORT.pdfSITE INSPECTION REPORTOriginatorDD