03 Design Example Case 1

download 03 Design Example Case 1

of 26

Transcript of 03 Design Example Case 1

  • 8/7/2019 03 Design Example Case 1

    1/26

    PurafloPEAT FIBRE BIOFILTER for Wastewater Treatment

    PURAFLOPEAT BIOFILTER CASE 1DESIGN EXAMPLE (GENERAL)

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 http://www.bnm-us.com/

  • 8/7/2019 03 Design Example Case 1

    2/26

    CASE 1PURAFLO PEAT BIOFILTER - DESIGN EXAMPLE (GENERAL)

    Site Conditions:

    3 bedroom dwelling (360 gpd design flow; this will vary from state to state) Group II soil (Sandy Loam) with a 0.5 LTAR for conventional drainfield Soil wetness condition at 18 inch below natural grade in limited area close to

    water-front Water-front property with 50 ft set-back - best soil at or inside the 50 ft.

    setback Level site (0-1% slope)

    System Design:

    1. Size Treatment System

    One module required per bedroom; therefore, 3 modules are required

    2. Select Disposal SystemArea of suitable Group II soil is limited; therefore, select a Type A(Pad/Bed) Puraflo disposal system

    3. Size and Locate Disposal SystemUse a loading rate of 1.0 gpd per sq. ft. for pre-treated effluent in a SandyLoam, Group II soil. In general, we can use a higher loading rate for pre-treated effluent (how much higher will vary). The better soil is at or withinthe 50 ft. setback. Based on the high quality of the effluent, reduce the

    horizontal setback to 35 ft. This allows us to install the system in the mostsuitable soil without polluting near by surface waters. (Some reduction inhorizontal setback is usually permitted with high quality effluent.)Therefore, use the 1.0 gpd per sq. ft. and reduce the 50 ft. water-front set-back to 35 ft.

    Pad Size = 360 gpd at 1.0 gpd per sq. ft. = 360 sq. ft.

    4. Disposal Field Layout/ConfigurationLonger narrower pads are preferred in most cases. Available area, soiland topographic limitations will also influence the pad layout. Pad should

    follow contour to insure required vertical separation distances aresatisfied, pad bottom must be level

    Select a 10 ft. by 36 ft. pad to provide the required 360 sq. ft.(with adjacent reserve area of equal size)[SHOW ACCURATE POSITION OF DRAINFIELD ON PLAT]

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    3/26

    CASE 15. Determine Module and Manifold Configuration

    Modules with weep holes are placed in a row (end to end), leveled andcentered along the long axes of the pad disposal area (preferred layout).They can also be placed side by side and in some cases in a cluster

    arrangement. Modules can be centered on equal portions of the pad orplaced adjacent to each other.

    Place modules in a row on 10 by 12 sections of the padRun manifold along side modules. Manifold connects into each modulevia a Tee piece with short flexible connection pipe [SEE MODULE GRIDDETAIL].

    6. Determine Installation Depthdue to the quality of the effluent, the vertical stand-off distance from trenchbottom to wetness condition, rock or other restrictions can be reduced

    (reductions will vary). A typical system requires a 12 inch verticalseparation distance (VSD) between the pad bottom and the seasonalwetness condition (which is the limiting factor in this case). Assume the10 ft. by 36 ft. pad was staked out on contour in the most suitable areaand spot elevations on the four corners indicated a negligible difference inelevation over the selected area. Therefore, maximum installation depthat the low point on the pad is:

    (Depth of suitable soil) minus (VSD);or in this case, 18 - 12 = 6 inches below grade

    The pad will be installed 6 inches below grade[SHOW ACCURATE CROSS-SECTION OF DRAINFIELD PAD]

    7. Determine Pump Requirements2 inch PVC Sch.40 force main line is standardEstablish total equivalent length as usual between pump and manifold

    Example:Horizontal pumping distance.......................................... 60 ft.7 elbows at 9 equivalent ft. per elbow ............................ 63 ft.1 diversion Tee at 11 equivalent ft. per Tee ................... 11 ft.1 disconnect at 2 equivalent ft. per disconnect................. 2 ft.

    1 check value at 17 equivalent ft. per check valve ......... 17 ft.1 ball value at 54 equivalent ft. per ball valve................. 54 ft.

    Total Equivalent Length................................................ 207 ft.

    From Friction and Pressure Head Tables, select the closest correspondingequivalent length for a three bedroom application (the 200 ft. column inthis case) to determine the friction and pressure heads for a range of flows

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    4/26

    CASE 1Flow gpm 200 ft.0 0.0010 1.6020 6.39

    30 14.3740 25.5450 39.91

    Determine the static head for given site conditionsGround elevation at proposed pump tank location is 9 ft.Assume the OFF float switch will be set at 5 ft. below grade (el. 4 ft.)Ground elevation at module location = 10 ft.Module height (grid height) above ground elevation = 2 ft.Module grid elevation = 12 ft.

    Therefore, total static head = 12 - 4 = 8 ft. (constant)Add static head to friction and pressure heads from table to yield TDH(Total Dynamic Head)

    Flow gpm 200 ft. Static Head TDH0 0.00 8.0 8.0010 1.60 8.0 9.6020 6.39 8.0 14.3930 14.37 8.0 22.3740 25.54 8.0 33.5450 39.91 8.0 47.91

    Plot TDH system curve over the selected pump curveThe pump will operate where the two curves intersectDrop a vertical line from the intersection point and read off the anticipatedflow in gpm - approximately 27 gpm in this case for the Zoeller 98 1/2 HPeffluent pump (or 9 gpm per module)

    The pump delivery rate should be between 7 to 12 gpm per module (below7 gpm the distribution to each module may begin to suffer and above 12gpm indicates an unnecessarily powerful pump is being considered)

    Therefore, the above selected 1/2 HP pump is suitable for thisapplication

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    5/26

    CASE 18. Determine Panel Requirements and Settings

    A simplex control panel with programmable timeris the standardmethod for controlling dosing to the treatment modules. Panel and pump

    electrical requirements must be compatible with each other and with theproposed power supply.

    Calculate the timer settings as follows:Dose volume should be between 7 to 12 gallons per moduleAssume 12 doses per day (typical); therefore, a daily design flow of 360gallons will require 12 doses of (360/12) 30 gallons which is 10 gallons permodule per dose (within range). From above pump calculations, a 27 gpmpump delivery rate is expected; therefore, the timer ON cycle should beset for;

    30 (gal.) / 27 (gpm) = 1.11 minutes or 67 seconds (realistically say 1minute)The timer OFF cycle should be set for;24 (hrs. per day) / 12 (doses per day) = 2 hours per dose

    Timer Settings: 1 Min. ON and 2 Hrs. OFF

    9. Determine Septic Tank SizeSize per current regulations (2 times daily design flow or greater)

    Specify a 1,000 gallon septic tank for this 3 bedroom applicationSpecify a Zabel filter, Model A300 for installation in septic tank

    [SEE SEPTIC TANK DETAIL]

    10. Determine Pump Tank SizeGenerally recommend a 1,000 gallon pump tank for 4 bedrooms or less

    Specify a 1,000 gallon pump tank[SEE PUMP TANK DETAIL]

    11. Specify Sampling OptionFor Type A pad systems, samples are taken via the pre-molded samplingchamber [SEE SAMPLE CHAMBER DETAIL]. (For Type B systems, a

    drop box can be used.)

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    6/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    7/26

    CASE 1

    NOTES

    General

    1 All construction materials and methods must conform to applicable Local and State SewageHandling and Disposal Regulations

    2 All pressure joints shall be primed and chemically fused

    3 Pumps shall be a Zoeller, 1/2 HP effluent pump with a capacity of 25 gpm at 20' of TDH or itsequivalent

    4 Any deviation from this design must be approved by the designer prior to installation

    5 The contractor shall contact the Bord na Mona prior to construction for a pre-constructionconference

    6 Electrical wiring to be installed under the direct supervision of a licensed electrical contractor,according to NEC, State and Local Electrical Codes, as applicable

    7 Contractor is to install concrete tanks on uniformly firm and stable compacted ground, crushedstone is recommended to provide uniform support to tank bottom

    8 Septic and pump tanks should be water-tight and conform to applicable Local and State SewageHandling and Disposal Regulations

    9 Contractor must contact the appropriate UTILITY AUTHORITY prior to any digging on site

    Biofibrous Peat Specifications

    1 Peat fiber is residue of Eriophorum (cotton grass) plants, carefully extracted from raised bogpeats (other natural residues and peat fines are present in small quantities)

    2 Moisture content on wet basis is 50-70%

    3 Min. organic content on anhydrous basis is 95%

    4 Water adsorption capacity, 72 hr. test, is 400-700%

    5 Average air filled porosity(AFP) is 51%

    Site Preparation Work:

    1 Hand clear wooded sites

    2 Machinery should not traverse the percolation area

    3 Machinery must never traverse excavated/exposed percolation area

    4 Contractor must provide adequate access for correct installation

    5 Avoid installation under wet site conditions

    Design:

    1 Design LTAR/PERC = 50 MPI

    2 Design flow = 600 gpd

    3 Depth to SHWT = 30+ inches (see soil report)

    4 Percolation area provided = Six 45' L trenches 3' W (18" max. install'n depth)5 Number of treatment modules = 5

    Percolation Area:

    1 Install trenches level and along contour where applicable

    3 Cover stone in trench/pad with filter fabric

    4 Min. distance between trenches = 3 times trench width (approx.)

    5 Do not smear trench/pad base or sides during excavation

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    8/26

    CASE 1

    Site Restoration:

    1 Min. cover of fill over stone is 4" (6" in NC)

    2 Backfill with suitable loose material free of large or damaging objects

    3 Straw and seed backfilled areas (or sod when required)

    4 Provide erosion protection for backfill material in accordance with Local and County standardsand maintain until permanent protection is established

    5 Backfill should be graded to prevent the infiltration of surface water and divert storm water run-offaway from the system

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    9/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    10/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    11/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    12/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    13/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    14/26

    CASE 1

    Friction Pressure Head Table for 2'' Diameter Pipe

    PRESSURE AND FRICTION LOSSES FOR 1 MODULE SYSTEM

    Q (gpm) hf+ hp (ft) for Various Values of Equivalent Length in Feet

    1 50 100 150 200 250 300 350 400 450 500 550 600

    0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    10 10.63 10.74 10.84 10.95 11.06 11.16 11.27 11.38 11.48 11.59 11.70 11.81

    20 42.52 42.95 43.38 43.80 44.23 44.66 45.09 45.51 45.94 46.37 46.79 47.22

    30 95.68 96.64 97.60 98.56 99.52 100.48 101.44 102.40 103.36 104.33 105.29 106.25

    40 170.09 171.80 173.51 175.22 176.93 178.63 180.34 182.05 183.76 185.47 187.18 188.88

    50 265.77 268.44 271.11 273.78 276.45 279.12 281.79 284.46 287.12 289.79 292.46 295.13

    60 382.71 386.55 390.40 394.24 398.08 401.93 405.77 409.62 413.46 417.30 421.15 424.99

    70 520.91 526.14 531.37 536.60 541.84 547.07 552.30 557.53 562.76 568.00 573.23 578.46

    80 680.37 687.20 694.04 700.87 707.70 714.54 721.37 728.20 735.04 741.87 748.71 755.54

    PRESSURE AND FRICTION LOSSES FOR 2 MODULE SYSTEM

    Q (gpm) hf+ hp (ft) for Various Values of Equivalent Length in Feet

    2 50 100 150 200 250 300 350 400 450 500 550 600

    0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    10 2.74 2.84 2.95 3.06 3.16 3.27 3.38 3.49 3.59 3.70 3.81 3.91

    20 10.95 11.38 11.81 12.23 12.66 13.09 13.51 13.94 14.37 14.80 15.22 15.65

    30 24.64 25.60 26.56 27.52 28.48 29.44 30.41 31.37 32.33 33.29 34.25 35.21

    40 43.80 45.51 47.22 48.93 50.64 52.35 54.05 55.76 57.47 59.18 60.89 62.60

    50 68.44 71.11 73.78 76.45 79.12 81.79 84.46 87.13 89.80 92.47 95.14 97.81

    60 98.56 102.40 106.25 110.09 113.94 117.78 121.62 125.47 129.31 133.16 137.00 140.84

    70 134.15 139.38 144.61 149.85 155.08 160.31 165.54 170.77 176.01 181.24 186.47 191.70

    80 175.22 182.05 188.88 195.72 202.55 209.39 216.22 223.05 229.89 236.72 243.55 250.39

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    15/26

    CASE 1

    PRESSURE AND FRICTION LOSSES FOR 3 MODULE SYSTEM

    Q (gpm) hf+ hp (ft) for Various Values of Equivalent Length in Feet

    3 50 100 150 200 250 300 350 400 450 500 550 600

    0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    10 1.28 1.38 1.49 1.60 1.70 1.81 1.92 2.02 2.13 2.24 2.34 2.45

    20 5.10 5.53 5.96 6.39 6.81 7.24 7.67 8.09 8.52 8.95 9.38 9.80

    30 11.48 12.45 13.41 14.37 15.33 16.29 17.25 18.21 19.17 20.13 21.09 22.06

    40 20.42 22.13 23.83 25.54 27.25 28.96 30.67 32.38 34.08 35.79 37.50 39.21

    50 31.90 34.57 37.24 39.91 42.58 45.25 47.92 50.59 53.26 55.93 58.60 61.27

    60 45.94 49.78 53.63 57.47 61.32 65.16 69.00 72.85 76.69 80.54 84.38 88.22

    70 62.53 67.76 72.99 78.23 83.46 88.69 93.92 99.15 104.39 109.62 114.85 120.08

    80 81.67 88.50 95.34 102.17 109.01 115.84 122.67 129.51 136.34 143.17 150.01 156.84

    PRESSURE AND FRICTION LOSSES FOR 4 MODULE SYSTEMQ (gpm) hf+ hp (ft) for Various Values of Equivalent Length in Feet

    4 50 100 150 200 250 300 350 400 450 500 550 600

    0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    10 0.76 0.87 0.98 1.08 1.19 1.30 1.41 1.51 1.62 1.73 1.83 1.94

    20 3.06 3.49 3.91 4.34 4.77 5.19 5.62 6.05 6.47 6.90 7.33 7.76

    30 6.88 7.84 8.80 9.76 10.72 11.69 12.65 13.61 14.57 15.53 16.49 17.45

    40 12.23 13.94 15.65 17.36 19.07 20.77 22.48 24.19 25.90 27.61 29.32 31.02

    50 19.11 21.78 24.45 27.12 29.79 32.46 35.13 37.80 40.47 43.14 45.81 48.48

    60 27.52 31.37 35.21 39.05 42.90 46.74 50.59 54.43 58.27 62.12 65.96 69.81

    70 37.46 42.69 47.93 53.16 58.39 63.62 68.85 74.09 79.32 84.55 89.78 95.01

    80 48.93 55.76 62.60 69.43 76.26 83.10 89.93 96.76 103.60 110.43 117.27 124.10

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    16/26

    CASE 1

    PRESSURE AND FRICTION LOSSES FOR 5 MODULE SYSTEM

    Q (gpm) hf+ hp (ft) for Various Values of Equivalent Length in Feet

    5 50 100 150 200 250 300 350 400 450 500 550 600

    0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    10 0.53 0.63 0.74 0.85 0.95 1.06 1.17 1.28 1.38 1.49 1.60 1.70

    20 2.11 2.54 2.97 3.39 3.82 4.25 4.67 5.10 5.53 5.95 6.38 6.81

    30 4.75 5.71 6.67 7.63 8.59 9.55 10.52 11.48 12.44 13.40 14.36 15.32

    40 8.44 10.15 11.86 13.57 15.28 16.99 18.69 20.40 22.11 23.82 25.53 27.24

    50 13.19 15.86 18.53 21.20 23.87 26.54 29.21 31.88 34.55 37.22 39.89 42.56

    60 19.00 22.84 26.69 30.53 34.37 38.22 42.06 45.91 49.75 53.59 57.44 61.28

    70 25.86 31.09 36.32 41.55 46.79 52.02 57.25 62.48 67.71 72.95 78.18 83.41

    80 33.78 40.61 47.44 54.28 61.11 67.94 74.78 81.61 88.44 95.28 102.11 108.94

    PRESSURE AND FRICTION LOSSES FOR 6 MODULE SYSTEM

    Q (gpm) hf+ hp (ft) for Various Values of Equivalent Length in Feet

    6 50 100 150 200 250 300 350 400 450 500 550 600

    0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    10 0.40 0.51 0.61 0.72 0.83 0.93 1.04 1.15 1.25 1.36 1.47 1.57

    20 1.60 2.02 2.45 2.88 3.30 3.73 4.16 4.59 5.01 5.44 5.87 6.29

    30 3.59 4.55 5.51 6.47 7.44 8.40 9.36 10.32 11.28 12.24 13.20 14.16

    40 6.39 8.09 9.80 11.51 13.22 14.93 16.64 18.34 20.05 21.76 23.47 25.18

    50 9.98 12.65 15.32 17.99 20.66 23.32 25.99 28.66 31.33 34.00 36.67 39.34

    60 14.37 18.21 22.06 25.90 29.74 33.59 37.43 41.28 45.12 48.96 52.81 56.65

    70 19.56 24.79 30.02 35.25 40.48 45.72 50.95 56.18 61.41 66.64 71.88 77.11

    80 25.54 32.38 39.21 46.04 52.88 59.71 66.54 73.38 80.21 87.05 93.88 100.71

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    17/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    18/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    19/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    20/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    21/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    22/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    23/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    24/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    25/26

    CASE 1

    ENVIRONMENTAL PRODUCTS U.S. INC.

    (800) 787-2356 www.bnm.us.com

  • 8/7/2019 03 Design Example Case 1

    26/26

    CASE 1