Course Technology 2001 1 Chapter 2: The Project Management Context and Processes

Transcript of 02ch

Page 1: 02ch

Course Technology 2001 1

Chapter 2:The Project Management

Context and Processes

Page 2: 02ch

Course Technology 2001 2

Projects Cannot Be Run In Isolation

• Projects must operate in a broad organizational environment

• Project managers need to take a holistic or systems view of a project and understand how it is situated within the larger organization

• See example in opening and closing case to illustrate this concept

Page 3: 02ch

Course Technology 2001 3

A Systems View of Project Management

• A systems approach emerged in the 1950s to describe a more analytical approach to management and problem solving

• Three parts include:– Systems philosophy: View things as systems, interacting

components working within an environment to fulfill some purpose

– Systems analysis: problem-solving approach

– Systems management: Address business, technological, and organizational issues before making changes to systems

Page 4: 02ch

Course Technology 2001 4

Figure 2-1. Three Sphere Model for Systems Management

Page 5: 02ch

Course Technology 2001 5

Project Phases and the Project Life Cycle

• A project life cycle is a collection of project phases

• Project phases vary by project or industry, but some general phases include– concept– development– implementation– support

Page 6: 02ch

Course Technology 2001 6

Figure 2-2. Phases of the Project Life Cycle

Page 7: 02ch

Course Technology 2001 7

Product Life Cycles

• Products also have life cycles

• The Systems Development Life Cycle (SDLC) is a framework for describing the phases involved in developing and maintaining information systems

• Typical SDLC phases include planning, analysis, design, implementation, and support

Page 8: 02ch

Course Technology 2001 8

Sample SDLC Models

• Waterfall model: has well-defined, linear stages of systems development and support

• Spiral model: shows that software is developed using an iterative or spiral approach rather than a linear approach

• Incremental release model: provides for progressive development of operational software

• RAD model: used to produce systems quickly without sacrificing quality

• Prototyping model: used for developing prototypes to clarify user requirements

Page 9: 02ch

Course Technology 2001 9

Figure 2-3. Spiral Model of Software Development (Boehm, 1988)

Page 10: 02ch

Course Technology 2001 10

Distinguishing Project Life Cycles and Product Life Cycles

• The project life cycle applies to all projects, regardless of the products being produced

• Product life cycle models vary considerably based on the nature of the product

• Most large IT products are developed as a series of projects

• Project management is a done is all of the product life cycle phases

Page 11: 02ch

Course Technology 2001 11

Why Have Project Phases and Management Reviews?

• A project should successfully pass through each of the project phases in order to continue on to the next

• Management reviews (also called phase exits or kill points) should occur after each phase to evaluate the project’s progress, likely success, and continued compatibility with organizational goals

Page 12: 02ch

Course Technology 2001 12

What Went Right?"The real improvement that I saw was in our ability toin the words of Thomas Edisonknow when to stop beating a dead horse.…Edison's key to success was that he failed fairly often; but as he said, he could recognize a dead horse before it started to smell...as a result he had 14,000 patents and was very successful…In IT we ride dead horsesfailing projectsa long time before we give up. But what we are seeing now is that we are able to get off them; able to reduce cost overrun and time overrun. That's where the major impact came on the success rate.”

Cabanis, Jeannette, "'A Major Impact': The Standish Group's Jim Johnson On Project Management and IT Project Success," PM Network, PMI, September 1998, p. 7

Page 13: 02ch

Course Technology 2001 13

Understanding OrganizationsStructural frame: Focuses on roles and responsibilities, coordination and control. Organization charts help define this frame.

Human resources frame: Focuses on providing harmony between needs of the organization and needs of people.

Political frame: Assumes organizations are coalitions composed of varied individuals and interest groups. Conflict and power are key issues.

Symbolic frame: Focuses on symbols and meanings related to events. Culture is important.

Page 14: 02ch

Course Technology 2001 14

What Went Wrong?Many data warehousing projects are side-tracked or derailed completely by politics. Data warehousing projects are always potentially political because they cross departmental boundaries, change both the terms of data ownership and data access, and affect the work practices of highly autonomous and powerful user communities. Many organizations fail to admit that many data warehousing projects fail primarily because management and project teams do not understand and manage politics. Marc Demarest found over 1200 articles on the topic of data warehousing based on a journal search he did from July 1995 to July 1996. Many of those articles offer advice on how to run successful data warehousing projects and focus on the importance of design, technical, and procedural factors, when, in fact, political factors are often the most important in helping these projects succeed.

Page 15: 02ch

Course Technology 2001 15

Many Organizations Focus on the Structural Frame

• Most people understand what organizational charts are

• Many new managers try to change organizational structure when other changes are needed

• 3 basic organization structures– functional– project– matrix

Page 16: 02ch

Course Technology 2001 16

Figure 2-4. Functional, Project, and Matrix Organizational Structures

Page 17: 02ch

Course Technology 2001 17

Table 2-1. Organizational Structure Influences on Projects

Matrix Organization TypeProjectCharacteristics

Functional Weak Matrix BalancedMatrix

Strong Matrix Projectized

Project Manager'sAuthority

Little orNone

Limited Low toModerate

ModerateTo High

High toAlmost Total

Percent of PerformingOrganization'sPersonnel Assigned Full-time to Project Work

VirtuallyNone

0-25% 15-60% 50-95% 85-100%

Project Manager's Role Part-time Part-time Full-time Full-time Full-timeCommon Title forProject Manager's Role

ProjectCoordinator/Project Leader

ProjectCoordinator/Project Leader

ProjectManager/Project Officer

ProjectManager/Program Manager

ProjectManager/Program Manager

Project ManagementAdministrative Staff Part-time Part-time Part-time Full-time Full-time

The organizational structure influences the project manager’s authority, but remember to address the human resources, political,and symbolic frames, too.

PMBOK Guide, 2000, p. 19

Page 18: 02ch

Course Technology 2001 18

Recognize the Importance of Project Stakeholders

• Recall that project stakeholders are the people involved in or affected by project activities

• Project managers must take time to identify, understand, and manage relationships with all project stakeholders

• Using the four frames of organizations can help meet stakeholder needs and expectations

• Senior executives are very important stakeholders

Page 19: 02ch

Course Technology 2001 19

Table 2-2. What Helps Projects Succeed?

According to the Standish Group’s report CHAOS 2001: A Recipe for Success, the following items help IT projects succeed, in order of importance:– Executive support– User involvement– Experience project manager– Clear business objectives– Minimized scope– Standard software infrastructure– Firm basic requirements– Formal methodology– Reliable estimates

Page 20: 02ch

Course Technology 2001 20

Need for Top Management Commitment

• Several studies cite top management commitment as one of the key factors associated with project success

• Top management can help project managers secure adequate resources, get approval for unique project needs in a timely manner, receive cooperation from people throughout the organization, and learn how to be better leaders

Page 21: 02ch

Course Technology 2001 21

Need for Organizational Commitment to Information Technology (IT)

• If the organization has a negative attitude toward IT, it will be difficult for an IT project to succeed

• Having a Chief Information Officer (CIO) at a high level in the organization helps IT projects

• Assigning non-IT people to IT projects also encourage more commitment

Page 22: 02ch

Course Technology 2001 22

Need for Organizational Standards

• Standards and guidelines help project managers be more effective

• Senior management can encourage– the use of standard forms and software for project

management– the development and use of guidelines for writing

project plans or providing status information– the creation of a project management office or center

of excellence

Page 23: 02ch

Course Technology 2001 23

• Define scope of project

• Identify stakeholders, decision-makers, and escalation procedures

• Develop detailed task list (work breakdown structures)

• Estimate time requirements

• Develop initial project management flow chart

• Identify required resources and budget

• Evaluate project requirements• Identify and evaluate risks

Prepare contingency plan• Identify interdependencies• Identify and track critical

milestones• Participate in project phase

review• Secure needed resources• Manage the change control

process• Report project status

Table 2-3. Fifteen Project Management Job Functions*

*Northwest Center for Emerging Technologies, "Building a Foundation for Tomorrow: Skills Standards for Information Technology,"Belleview, WA, 1999

Page 24: 02ch

Course Technology 2001 24

Suggested Skills for aProject Manager

Communication skills: listening, persuading Organizational skills: planning, goal-setting,

analyzing Team Building skills: empathy, motivation, esprit

de corps Leadership skills: sets example, energetic, vision

(big picture), delegates, positive Coping skills: flexibility, creativity, patience,

persistence Technological skills: experience, project

knowledge

Page 25: 02ch

Course Technology 2001 25

Table 2-3. Most Significant Characteristics of Effective and Ineffective Project Managers

• Leadership by example

• Visionary

• Technically competent

• Decisive

• Good communicator

• Good motivator

• Stands up to upper management when necessary

• Supports team members

• Encourages new ideas

• Sets bad example

• Not self-assured

• Lacks technical expertise

• Poor communicator

• Poor motivator

Effective Project Managers Ineffective Project Managers

Page 26: 02ch

Course Technology 2001 26

Project Management Process Groups

• Project management can be viewed as a number of interlinked processes

• The project management process groups include– initiating processes– planning processes– executing processes– controlling processes– closing processes

Page 27: 02ch

Course Technology 2001 27

Figure 2-5. Overlap of Process Groups in a Phase (PMBOK Guide, 2000, p. 31)

Page 28: 02ch

Course Technology 2001 28

Table 2-5. Relationships Among Process Groups, Activities, and Knowledge Areas

Page 29: 02ch

Course Technology 2001 29

Table 2-5. Relationships Among Process Groups, Activities, and Knowledge Areas

Page 30: 02ch

Course Technology 2001 30

Developing an IT Project Management Methodology

• Just as projects are unique, so are approaches to project management

• Many organizations develop their own project management methodologies, especially for IT projects

• Blue Cross Blue Shield of Michigan used the PMBOK as a guide in developing their IT project management methodology

Page 31: 02ch

Course Technology 2001 31

Figure 2-6. IT PM MethodologySee figure in text. Note thatmany parts of this approachmap to the PMBOK, but some activities have beenchanged to meet the needsof the organization.