    PROJECT REPORT

    OPERATIONS & MAINTENANCEFebruary 3, 2009

    AIRSIDE PROJECTS

    Future Runway 13R/31L Project

    Status of acquiring the right of way property has not changed since last month. By the end ofJanuary 2009, the Airport had acquired twenty two (22) of the required twenty-three (23)residential properties. Additionally, there is one piece of unimproved property and an easementleft to acquire. All property acquisitions have been made through the Hardship and VoluntaryLand Acquisition Program.

    Airfield Pavement Deicers

    Cryotech Deicing Technology (CDT) is currently receiving raw materials to resume productionof their E36 liquid runway deicing product. They plan to begin shipping E36 to customersin late February. The alternative liquid runway deicer, NX360, will continue to be availableuntil E36 deliveries begin.

    The Airport Board approved an additional $250,000 in this fiscal year's revised budget at aSpecial Board Meeting held January 21, 2009. The premature expenditure of monies for airfieldchemicals this season resulted from higher than normal winter precipitation in the form of bothsnow and ice. The National Weather Service's 90-day climatological outlook for Des Moines

    shows no significant trends for above or below normal temperatures or precipitation over thenext three months. This outlook suggests the most recent appropriation for deicing chemicalsshould be sufficient to cover expenditures through the remainder of this winter season.

    Taxiway P Reconstruction Project

    This project is currently on hold due to weather and temperatures. Once the temperatures start toclimb in March and April, project will resume. Two items are left to complete: Enhanced holdshort and centerline markings at each intersection, and signage at each intersection.

  • 8/8/2019 0203 2009 proj update

    2/4

    2

    Mesaba Maintenance Facility

    The office area of the Mesaba facility is complete. Waxing of the floors, final cleaning and

    punch list items have taken place.

    The hangar is complete, with just the punch list left to be finished. On January 20th, the foamdeluge test occurred and was very successful. The test required 3 of foam to cover the entire65,000 sq ft of the hangar in 3 minutes. Approximately 4.5 of foam was produced in roughly3 minutes.

    Mesaba has been making headway on installing their equipment once areas have been completedand turned over. The part shelving has been installed and is ready to accept parts the week ofFebruary 2nd. Shelving is approximately 11-12 feet tall, which uses rolling ladders to makeeasier access. Office equipment has been delivered and installed. The first planned overnight

    maintenance is scheduled for the week of February 9th

    .

    Removal of the temporary fencing is planned for February 3rd. This will set the date in which allsecurity systems will need to be fully functional. On February 4

    th, Mesaba will perform a dry

    run on fitting a plane at all four locations within the hangar.

    LANDSIDE PROJECTS

    Concourse Remodel Project

    At this February Board meeting, the Board will be asked for approval to receive bids on theConcourse Remodel project during the month of February. Design of this project includes aMaster Plan of the Fire Protection System for the Airport, to include current and futureinstallations. With acceptable bids, construction is scheduled to start in March. Coordination ofthis project and the Common Use project are intertwined, and management of both will becritical. Completion of the Concourse Remodel is estimated to occur in April 2010.

  • 8/8/2019 0203 2009 proj update

    3/4

    3

    Common Use Project

    Negotiation of the final contract was accomplished the last 2-3 weeks in January. The AirportBoard will be asked to approve the contract at this February Board meeting. Delivery andimplementation of equipment for this project will coincide with the Concourse Remodel project,

    in that the Common Use equipment will go live once each gate holding area is finished, allowingfor the gate to be operational as soon as possible. Phase I, which concerns the ConcourseRemodel, is estimated to be complete in August of 2009. Phase II, which coincides with theBaggage Handling project is estimated to be complete at the beginning of 2010.

    Rental Car Facility

    This project is in the design phase, with the City working with Design Alliance and PGAL. Boththe City Engineering staff and project Architects attended a pre-application meeting in January tohelp in determining code requirements. The first kick off meeting with all parties, including the

    rental car companies, took place on January 29

    th

    . This project is scheduled to be put out to bid inMay 2009. Estimated completion is scheduled for December 2009.

    Baggage Handling Project

    Design of this project is approximately 70% complete. The 70% developmental design wassubmitted to TSA on January 22nd. Meetings with the airline property representatives and localairline managers took place in January. Airport staff is working out a phasing plan ofconstruction to minimize the disturbance to the airlines. The estimated timeline for the project isfor the Board to authorize bid documentation in April 2009, and approve the bid in June 2009.Estimated completion of the project is February 2010.

    Parking Revenue Control Equipment Replacement

    On December 15th, the first phase rollout of the new Parking Revenue Control Equipment Projectwas conducted. The entry plaza for Long Term and Short Term parking has all five (5) entrylanes activated with new equipment and is accepting vehicles. At the exit plaza, three (3)cashier-staffed lanes are activated with new equipment. The last (3) exit lanes have beenequipped with self service equipment that accepts credit cards.

    Economy lot is currently left to be completed. Power to this location was completed on January22nd. Power, programming and equipment for the revenue system to these (4) lanes started theweek of January 26

    th. Estimated completion is the week of February 2

    nd, with operational use

    week of February 9th.

  • 8/8/2019 0203 2009 proj update

    4/4

    4

    North Employee Lot

    Progress on this project has been halted due to the winter weather. Approximately 95% of theconcrete slab is installed. Approximately 70% of the light bases and poles are installed.Progress on the lot will resume in the spring. Following are the items left to be completed:

    North end concrete slab and drive way Striping of stalls Sealing of joints East side light poles and bases Backfilling of curbs and final grades Rain garden installation Detention Area

    Parking Operator Mystery Parker Program

    As part of their contract to provide parking management services, Republic Parking has initiateda Mystery Parker Program. Designed to elicit the best in Customer Service from its employees,the Mystery Parker Program utilizes trained shopping professionals who are adept at evaluatingand documenting customer service performance.