1Long Range Planning Committee Meeting January 29, 2018
BLOCK G (Metro Market Square block)
CRYSTAL CITY BLOCK PLAN # CCBP- G – 1
01.29.18
2
1. Introduction
01.29.18
1. LRPC Meeting Purpose
Review of proposed Crystal City Block Plan G
Collectively work towards:
A) Determining whether there are major outstanding issues with the proposed Block Plan that should be addressed
B) Developing at least one Crystal City Block Plan Scenario Map including the envisioned uses and level of development associated with each site across the block
C) Developing guiding principles for the open space
3
01.29.18
1. Tonight’s Agenda
1. Introductory Remarks - Chair
2. Background - Staff
a. Overview of Block Plan Review Process
b. Preliminary Review Schedule
3. Sector Plan Guidance for the Block - Staff
4. Overview of Metro Entrance Project - Staff
5. Applicant Presentation on Proposed Block Plan Elements, Scenarios and Justification - Applicant
6. Preliminary Staff Assessment of Proposed Crystal City Block Plan - Staff
a. Sector Plan Deviation
b. Issues for Discussion at LRPC #2/Open House
7. LRPC Discussion - Chair
8. Public Comment - Chair
9. Concluding Remarks - Chair
4
01.29.18
5
2. Backgrounda. Overview of Block Plan Review Process
01.29.18
2. CCBP Background
• Crystal City Sector Plan calls for block-level planning analysis
- Specifically references “Phased-Development Site Plans (PDSPs)”
• In developing “C-O Crystal City” zoning, major obstacles with using PDSPs to implement Sector Plan were identified
- Fragmented parcel ownership- Inability to condition property of others- Uncertainty regarding consent
• Crystal City Block Plan (CCBP) process was developed to address these issues
• CCBPs help to ensure that:
- Crystal City develops consistent with Sector Plan vision
- Proposed new buildings do not preclude future planned improvements
- Systems and infrastructure continue to function during redevelopment
- Focus is maintained on timing of community improvements
6
01.29.18
2. CCBP Overview
7
What is a CCBP? - A general, guiding long-range plan for a single block in Crystal City,
east of Route 1, depicting existing and proposed general building locations, land use mix, tower coverage, public open space and facilities, transportation and other infrastructure, etc..
When is a CCBP needed? – Rezoning to C-O Crystal City.
How is it finalized? - Adopted by County Board as supplemental guidance to Crystal City Sector Plan. Does not create new entitlements. 2 CCCBPs adopted to date.
What will the LRPC review encompass? - LRPC review will focus on the Crystal City Block Plan Document.
• Base maps, analyses, and supporting information
• Culminates in proposed Block Plan scenario map(s) showing how the block could ultimately develop in the future and how it and the final site plan would achieve Sector Plan goals for the block.
* Submission also includes Block Development Document, (with civil, technical, legal drawings), primarily
reviewed by staff
01.29.18
2. CCBP Community Services/Amenities
8
• Review of the CCBP also informed by Crystal City Community Services and Amenities Inventory
• Provides continual awareness on progress made towards meeting community-oriented service and amenity goals from a Crystal City perspective, as opposed to a block level perspective
• Inventory provides additional context for Planning Commission and community review of CCBPs and Final Site Plans; helps identify opportunities for achieving certain needs on a block
01.29.18
2. CCBP Review Process
9
LRPC• Block Plan is reviewed by the LRPC for consistency with the Sector Plan.
SPRC• SPRC typically reviews the Final Site Plan after the Bock Plan review. The Block
Plan and any proposed refinements are used as a guide for reviewing the final site plan.
PC• Following SPRC process, the Site Plan and Block Plan are presented to the full
Planning Commission at a public hearing.
CB• County Board then holds a public hearing to consider: 1) adoption of the Block
Plan and 2) approval of the Final Site Plan, and any associated re-zonings.
• Adopted Block Plan would serve as the most current plan for the block, until the next site plan on the block necessitates an updated Block Plan.
01.29.18
10
2. Backgroundb. Preliminary Review Schedule
01.29.18
11
2. Preliminary Schedule
Note: Dates subject to change.
Initial Staff Observations of CCBP
01.29.18
12
3. Sector Plan Guidance for the Block
01.29.18
13
3. Sector Plan Guidance for the Block
01.29.18
14
3. Sector Plan Guidance for the BlockExisting Conditions
15
th S
t.
1770
Water Park
Future
Metro
Market
Square
01.29.18
15
3. Sector Plan Guidance for the BlockExisting Conditions
1770
Future Metro
Market Square
01.29.18
16
3. Sector Plan Guidance for the BlockExisting Conditions
Future Metro
Market
Square
1770
01.29.18
17
3. Sector Plan Guidance for the Block
01.29.18
18
3. Sector Plan Guidance for the Block
BULK PLANE ANGLE DIAGRAM Figure 3.8.6
01.29.18
19
3. Sector Plan Guidance for the Block
01.29.18
20
3. Sector Plan Guidance for the Block
Tower Coverage is defined as the sum of the
largest single floor of all buildings on the block,
above the fifth floor, divided by the site’s net
buildable area.
01.29.18
21
3. Sector Plan Guidance for the Block
01.29.18
22
3. Sector Plan Guidance for the Block
1770
Water Park
Center Park
View Looking East
01.29.18
23
3. Sector Plan Guidance for the Block
01.29.18
24
3. Sector Plan Guidance for the Block
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
1770
View Looking North
01.29.18
25
3. Sector Plan Guidance for the Block
01.29.18
26
3. Sector Plan Guidance for the Block
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
1770
1770
View Looking East View Looking West
01.29.18
27
3. Sector Plan Guidance for the Block
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
• Target size of Metro Market Square is 43,900 square feet.
• The space will provide for and celebrate a new entrance to the Metro Station at the east end of the
plaza and will be a primary center of retail activity.
• The ground plane of Metro Market Square will be finished primarily in hard surfaces which will
allow for market uses, temporary pushcart retail, public gatherings, outdoor entertainment, and a
variety of related uses.
• Metro Market Square could also create an opportunity for crafting a permanent market building
arcade along the length of the plaza which could be used for a local farmer’s market, arts and
crafts festivals, and/or carnivals.
• The head house on the east end of the market arcade could be the new entry to the Metro Station.
• A major connection across 18th Street to the Center Park should be emphasized in the plaza
design.
• Small water features, benches, cafe seating, larger interactive sculptures, chess tables, bosques of
trees, and similar features should be incorporated into the overall design.
• Pervious paving, artistic wind turbines, and/or solar panels on the roof of the market building could all
be incorporated into the design.
01.29.18
28
3. Sector Plan Guidance for the Block
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
• 110’ between build-to lines
• 19’ wide sidewalk on park edge
• Assumes full build out with
parking/loading moving to Clark-Bell
View Looking East
01.29.18
29
3. Sector Plan Guidance for the Block
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
• 100’ between build-to lines
• 17.5’ wide sidewalk on west
side of Crystal Dr.
• Assumes full redevelopment
1770
1770
01.29.18
30
3. Sector Plan Guidance for the Block
• Street Network – re-alignment of Clark-Bell and introduction of alleys
• Tower Coverage – 75% for block excluding public open space
• Land Use Mix –Residential, Commercial, Hotel or Mixed-Use: Minimum 40% Residential
or Hotel on the northern portion, with the southern portions being designated as
Residential, Commercial, Hotel or Mixed-Use: Minimum 70% Office
• Retail Frontage and Underground – on southwest corner of Clark-Bell, south edge facing
park, and entire block frontage on Crystal Drive.
• Base Density – 3.8 FAR for commercial and 4.8 FAR for residential
• Architectural Features – Coordinated frontage on south edge facing park, and
architectural features on Block G-1 at existing CC Metro plaza, and on Block G-2 where
1770 Crystal Dr. exists today.
• Surface Transitway – Transit stops on Clark-Bell near existing CC Metro plaza, and on
Crystal Dr. near new Metro entrance and Water Park.
• Service and Loading – preferred locations along Clark-Bell
• Parking- between 1 space/ 750 square feet and 1 space/1,000 square feet (office), or
1.125 spaces/ dwelling unit (residential)
SUMMARY
01.29.18
31
3. Area Wide Sector Plan Guidance
Appendix 3 – County Board Guidance for the Implementation and
Elaboration of the Crystal City Sector Plan
Additional Area-Wide Goals to Consider:
• Housing | 800 additional committed or market rate affordable units
above projected 1,200 units in/near Crystal City
• Public Space | 14 to 15 total acres of publicly-available open space east of
Route 1
• Connectivity | Additional cross-streets and pedestrian passageways east of
Route 1
• Energy | Design and construction with a preference for easy
conversion to district energy systems
01.29.18
32
4. Overview of Metro Entrance Project
01.29.18
33
4. East Metro Entrance
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
• Second full entrance at east end of Metro station
• Elevators, stairs, fare gates, fare machines, kiosk
• Improves pedestrian access; provides additional ADA elevator access
• Improves access from Crystal Dr. and connections to VRE Station and Transitway station (Metroway stop)
• To be built on northwest corner of Crystal Dr. and 18th St. S.
• Feasibility and alternatives study completed Spring 2014
• Concept design phase in final stage coordinated with WMATA and JBG Smith
• Included in County’s adopted FY17-FY26 Capital Improvement Plan; also in County’s adopted Transit Development Plan
01.29.18
34
4. East Metro Entrance
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
Planned Location for Crystal City Metro Station East Entrance
1770
01.29.18
35
5. Applicant Presentation of Proposed Block Plan Elements, Scenarios, and Justification
01.29.18
36
6. Preliminary Staff Assessment of Proposed Crystal City Block Plan
01.29.18
37
6. Existing ConditionsInitial Staff Observations of CCBPLand Use Mix
87%
53%
Land Use %
1770
01.29.18
Land Use %
38
6. Proposed Block Plan Scenario 1Initial Staff Observations of CCBPInterim - Land Use Mix
51%
49%1770
01.29.18
39
6. Proposed Block Plan Scenario 1 Initial Staff Observations of CCBP
• Residential FARs are below 4.8 FAR
• Commercial FARs are below 3.8 FAR
• Tower Coverage is below 75%
Interim - Density & Tower Coverage
01.29.18
Land Use %
40
6. Proposed Block Plan Scenario 2Initial Staff Observations of CCBPFinal Sector Plan- Land Use Mix
95%
81%
1770
01.29.18
41
6. Proposed Block Plan Scenario 2
• Commercial FARs are above 3.8 FAR in 4
buildings highlighted in table & plan
• Tower Coverage is below 75%
Final Sector Plan- Density & Tower CoverageInitial Staff Observations of CCBP
01.29.18
42
6. Building Placement Deviations
Sector Plan Applicant Proposal
• South and east facades of 1770 Crystal Dr.
building do not meet build-to lines in CCSP
• Corner building encroaches on open space &
build-to line for park space
Initial Staff Observations of CCBP
1770
18th St.
01.29.18
43
6. Building Placement/Street Deviations
Sector Plan
• Proposed build-to lines not achieved on 18th St. &
Crystal Dr.
• Sidewalk widths are not achieved on 18th St. &
Crystal Dr.
• Corner building encroaches on final sidewalk
dimensions per CCSP
Initial Staff Observations of CCBP
Applicant Proposal
SECTION A
SECTION B
B
A
18th St.
01.29.18
44
6. Bulk Plane Angle Deviations
• Bulk/plane angles could be
modified by County Board when
finding that site maintains
adequate sunlight to public open
spaces
• Plan calls for no more than 55 %
in shadow between 11am and
3pm on equinoxes
• Proposal is at 59% in the fall
Initial Staff Observations of CCBP
18th St.
01.29.18
45
6. Street Network DeviationsInitial Staff Observations of CCBP
• Access to the apartment
building (Dweck) provided
from 15th St. is a private
drive - not an alley
18th St.
01.29.18
46
6. Service and Loading DeviationsInitial Staff Observations of CCBP
• Vehicular access on 18th
St., Crystal Dr. & 15th St.
Sector Plan Applicant Proposal
Existing Entrance to Remain
New Entrance/Loading Access
18
thS
t.
18
thS
t.Crystal Dr.
01.29.18
47
6. Retail Frontage DeviationsInitial Staff Observations of CCBP
• Gaps in retail frontage facing 18th
St. & future park
• Corner building with inward facing
retail
Corner Building
Sector Plan Applicant Proposal
18th St.
01.29.18
48
6. Open Space Deviations
Sector Plan Renderings Applicant Proposal- Concept Landscape Plan
Initial Staff Observations of CCBP
1770
Considerations:
1. Market Square Theme
2. Size & Configuration
3. Design Character
4. Topography
5. Circulation/ Access
6. Retail Activation/ Corner
Building
1770
1770
Crystal Dr.
18
thS
t.
01.29.18
49
6. Open Space Deviations
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
• Target size of 43,900 square feet. Applicants’ proposal creates fragmented design
with three distinct spaces, as opposed to a contiguous 43,900sf. 17 ft. grade
change between upper & lower levels creates a visual & physical disconnect.
• The space will provide for and celebrate a new entrance to the Metro Station at the
east end of the plaza and will be a primary center of retail activity. This can be
achieved with proposed plan.
• The ground plane of Metro Market Square will be finished primarily in hard surfaces
which will allow for market uses, temporary pushcart retail, public gatherings,
outdoor entertainment, and a variety of related uses. An appropriate balance of
paving & landscape needs to be evaluated further.
• Metro Market Square could also create an opportunity for crafting a permanent
market building arcade along the length of the plaza which could be used for a
local farmer’s market, arts and crafts festivals, and/or carnivals. Discussion topic.
Sector Plan Concept Narrative for Metro Market Square p.83
01.29.18
50
6. Open Space Deviations
3D MODEL – BIRD’S EYE PERSPECTIVE VIEW (FROM SOUTHWEST)
• The head house on the east end of the market arcade could be
the new entry to the Metro Station. Current design includes new
Metro elevators housed in proposed corner building. Without
corner building, concept of “head house” is unknown. Metro
elevator may simply rise to sidewalk level at corner.
• A major connection across 18th Street to the Center Park should
be emphasized in the plaza design. Not provided.
• Small water features, benches, cafe seating, larger interactive
sculptures, chess tables, bosques of trees, and similar features
should be incorporated into the overall design. Discussion topic.
• Pervious paving, artistic wind turbines, and/or solar panels on the
roof of the market building could all be incorporated into the
design. Discussion topic.
Sector Plan Concept Narrative for Metro Market Square p.83
01.29.18
51
6. Open Space Deviations
Corner Building
Pros:
• Anchors the corner, houses new Metro,
and retail. Could be a focal point if well
designed on all sides.
• Retail could help activate public space.
• Building helps connect two open spaces
together while maintaining vehicular
access from 18th St..
• Could be retrofitted in the future for
public market uses.
• Building, elevator and wall could help
address topography challenges.
Cons:
• Changes configuration & character of
open space.
• Creates less desirable condition on 18th
St. sidewalk & west façade with sloping
landscape.
• Ancillary uses from corner building could
encroach on public space.
Applicant Proposal
Initial Staff Observations of CCBP
01.29.18
52
6. Open Space Deviations
Applicant Proposal
Initial Staff Observations of CCBP
Overall Park Design Comments:
1. Sloped landscape & steps could limit
flexible use of park for markets, events,
etc..
2. Promenade needs to remain clear for fire
lane; opportunity to provide space
between trees for pop-up market tents,
seating, etc.
3. Retail on corner building should also be
on upper terrace with activity.
4. Change in topography 17 ft. “step”
between spaces could provide a better
transition and connection to new Metro
entrance & Crystal Dr. Wall design will
need to be further evaluated.
5. Lower Metro plaza could be mostly paved
space with grove of trees, movable public
seating, water feature, public art, etc..
6. 18th St. sidewalk experience & façade
treatment is a concern.
2
1
3
4
5
6
01.29.18
53
6. Summary of Sector Plan Deviations
CCSP Map/ Item CCSPPage
Deviation (Y/N)
Description
Building Heights 95 N Heights are below maximums 250’ & 200’.
Bulk Plane Angle 97 Y Can be modified by County Board.
Build-to Lines 47 Y Corner building in park space. 1770 building not consistent on south and east sides.
Street Network 51 Y Only private access from 15th St. provided- no alleys proposed.
Tower Coverage 99 N Coverage is below 75%.
Land Use Mix 103 Y Commercial office below minimum 70% on south block.
Base Density 93 N Commercial & Residential FARs below 3.8 & 4.8
Architectural Features 119 TBD Final site plan review will determine if met.
Surface Transit 57 N Transit stops are consistent.
Service/Loading 111 Y Maintaining existing access- not relocating to Clark-Bell.
Public Open Space 79,83 Y Corner building & overall character, configuration not met.
Retail Frontage/Underground
107 Y Corner building with inward facing retail
Street Sections 63,66 Y Street ROW & sidewalk dimensions not met on 18th St. or Crystal Dr.
Parking 72,73 TBD Final site plan will determine calculations.
Scenario 1 - Interim Condition
01.29.18
54
6. Issues for LRPC #2/Open House
• Community Services and Amenities Inventory
• Framing Issues for Open Space – will help to develop Guiding Principles for
the Open Space during LRPC #2 and the Open House
• General Configuration
• Corner Building
• Market Theme
• Topography
• Access and Circulation
• Paving v. Landscaping
• Other Framing Issues Identified During LRPC #1
01.29.18
55
7. LRPC Discussion
01.29.18
56
7. Issues for LRPC #1
• Sector Plan Deviations
• Table on slide 53
• Questions for Staff or Applicant to Address at LRPC #2
• Identification of Framing Issues for Open Space Discussion at LRPC #2/Open House
01.29.18
57
8. Public Comment
01.29.18
58
9. Conclusion