    SECTION PROJECT

  • 8/11/2019 01-Section Project Rev00

    2/12

    SECTION -PROJECT

    Clause No. PARTICULARS Page

    No.

    1.0 GENERAL 1

    2.0 PROJECT DESCRIPTION 1

    3.0 SCOPE 1

    4.0 SCHEDULE OF QUANTITIES 2

    5.0 BASIC REFERENCE DRAWINGS 3

    6.0 ORDER OF PRECEDENCE OF DIFFERENT PARTS OF

    TECHNICAL SPECIFICATION

    3

    7.0 SPARES 4

    8.0 SPECIAL TOOLS AND TACKLES 4

    9.0 FACILITIES TO BE PROVIDED BY THE OWNER 4

    10.0

    11.0

    SPECIFIC REQUIREMENT

    SPECIFIC EXCLUSIONS

    4

    5

    ANNEXURE I LIST OF DRAWINGS 6

  • 8/11/2019 01-Section Project Rev00

    3/121

    SECTION-PROJECT

    1.0 GENERAL

    1.1 Power Grid Corporation of India Ltd. (POWERGRID), Govt. of India Enterprise

    is responsible for bulk Power transmission and distribution of electrical energy

    from various Central Govt. Power Projects to various utilities/beneficiaries andinterconnecting regional grids, operating and maintaining the National electrical

    grid of India. It is established with mandate of "Establishment and operation of

    regional and national power grids to facilitate transfer of power within and

    across the regions with reliability, security and economy on sound commercial

    principles, as its mission.

    1.2 POWERGRID is implementing Process Bus Technology with Integration of

    Optical Current transformer at 400/220kV Bhiwadi S/s.

    2.0 PROJECT DESCRIPTION

    2.1 At present, Power Grid has adopted Substation Automation through Station Bus

    Technology. In this scheme, Protection relays & Bay control devices (Bay level)

    are connected to each other and to the substation gateway (Substation Level)

    and local Human Machine Interface (HMI) through a communication network

    known as Station Bus. Here, Point to point connection is provided between

    various process equipments and Protection relays & Bay control devices.

    2.2 To further enhance the system reliability & efficiency, POWERGRID is looking

    for Process Bus Technology. Process Bus shall facilitate time critical

    communication between Control & Protection system (Bay Level) to the primary

    process equipment (Process Level). Data gathered at the Process Level shall

    be sampled, digitalized, formatted and transmitted through the process bus LAN

    to Bay/Unit Level.

    2.3 Fibre Optic Ethernet link shall be provided for communication between Bay

    Level & Process level.

    2.4 In the proposed scheme, all the input signals which are extended to the existing

    protection scheme shall be duplicated. No tripping would be extended from the

    proposed scheme. Parallel meter shall assess the accuracy of metering

    thorough Optical Current Transformer.

    3.0 SCOPE

    3.1 Design, Engineering, Manufacturing, Testing, Supply, Storage & handing,

    Erection and commissioning of

    A. 1 no. Pilot Bay consisting of

    i. 400kV Optical Current Transformer alongwith necessary support

    insulators, structures etc.

  • 8/11/2019 01-Section Project Rev00

    4/12Y:\Process Bus\Pilot Project\01-Section project_rev00.doc

    2

    ii. C&R Panel and HMI: Electronic & Protection panel with IEC 61850

    compatible Distance Protection Relay with Ethernet module to accept

    inputs from merging unit along with HMI PC

    iii. Merging Unit

    iv. Cable management boxv. All Power & Control cables and Cable terminations

    vi. All Communication cables including Fibre optic cables

    vii. Installation hardware equipment, connectors, jumpers, spacers,

    grounding material etc. required for pilot bay.

    3.2 Civil Works - The scope of work shall include but shall not be limited to the

    following based on Owner supplied drawings to be provided during detailed

    engineering:-

    i. Foundation for Optical Current Transformer

    ii. Foundation of BPI

    iii. Cable Trench/other miscellaneous works required for installation of the

    proposed system

    3.3 POWERGRID SCOPE: POWERGRID shall provide the meter of the same

    make as their existing meter (at Bhiwadi S/s) and integration of the same with

    the existing metering workstation.

    4.0 SCHEDULE OF QUANTITIES

    The requirement of various items/equipments and civil works are indicated in

    Bid price Schedules.

    All equipments/items and civil works for which bill of quantity has been indicated

    in BPS (Bid price Schedules) shall be payable on unit rate basis. During actual

    execution, any variation in such quantities shall be paid based on the unit rate

    under each item incorporated in Letter of award.

    Wherever the quantities of items/works are not indicated, the bidder is required

    to estimate the quantity required for entire execution and completion of works

    and incorporate their price in respective Bid price schedules. For erectionhardware items, Bidders shall estimate the total requirement of the works and

    indicate module-wise lump sum price bay wise and include the same in relevant

    Bid price schedules. For module identification, Bidder may refer typical drawings

    enclosed with the specifications. Any material/works for the modules not

    specifically mentioned in the description in BPS, as may be required shall be

    deemed to be included in the module itself.

  • 8/11/2019 01-Section Project Rev00

    5/12Y:\Process Bus\Pilot Project\01-Section project_rev00.doc

    3

    Bidder should include all such items in the bid proposal sheets, which are not

    specifically mentioned but are essential for the execution of the contract. Item

    which explicitly may not appear in various schedules and required for successful

    commissioning of substation shall be included in the bid price and shall be

    provided at no extra cost to Owner.

    5.0 BASIC REFERENCE DRAWINGS

    5.1 Single line diagram and general arrangements are enclosed with the bid

    documents for reference at Annexure-I, which shall be further engineered by the

    bidder. The bidder shall maintain phase to earth clearance, phase to phase

    clearance and sectional clearances as per IE rules.

    5.2 The enclosed drawings give the basic scheme, layout of substation, proposed

    scheme. In case of any discrepancy between the drawings and text of

    specification, the requirements of text shall prevail in general. However, the

    Bidder is advised to get these clarified from Owner.

    6.0 ORDER OF PRECEDENCE OF DIFFERENT PARTS OF TECHNICAL

    SPECIFICATION

    For the purpose of present scope of work, technical specification shall consist of

    following parts and they should be read in conjunction with each other.

    1. Section : Project Rev 00

    2. Section : General technical Requirement Rev 12

    3. Section : Power & Control Cable Rev 05

    4. Section : Switchyard Erection Rev 07

    5. Section : Structure Rev 04

    6. Section Civil Works Rev 07

    7. Section : Control & Relay Panels for

    Process Bus Technology

    Rev 00

    8. Section : Substation Automation System Rev 03

    In case of any discrepancy between Section-PROJECT, Section-GTR and othertechnical specifications on scope of works, Section-PROJECT shall prevail over

    all other sections.

    In case of any discrepancy between Section-GTR and individual sections for

    various equipments, requirement of individual equipment section shall prevail.

    7.0 SPARES

  • 8/11/2019 01-Section Project Rev00

    6/12Y:\Process Bus\Pilot Project\01-Section project_rev00.doc

    4

    Mandatory Spares

    The Mandatory Spares shall be included in the bid proposal by the bidder. The

    prices of these spares shall be given by the Bidder in the relevant schedule of

    BPS and shall be considered for evaluation of bid. It shall not be binding on the

    Owner to procure all of these mandatory spares.

    The bidder is clarified that no mandatory spares shall be used during the

    commissioning of the equipment. Any spares required for commissioning

    purpose shall be arranged by the Contractor. The unutilized spares if any

    brought for commissioning purpose shall be taken back by the contractor.

    8.0 SPECIAL TOOLS AND TACKLE

    The bidder shall include in his proposal the deployment of all special tools and

    tackles required for erection, testing, commissioning and maintenance of

    equipment. The special tools and tackles shall only cover items which are

    specifically required for the equipment offered and are proprietary in nature.

    However a list of all such devices should be indicated in the relevant scheduleprovided in the BPS. In addition to this the Contractor shall also furnish a list of

    special tools and tackles for the various equipment in a manner to be referred

    by the Employer during the operation of these equipment. The scope of

    special tools and tackles are to be decided during detail engineering and the list

    of special tools and tackles, if any shall be finalized.

    9.0 FACILITIES TO BE PROVIDED BY THE OWNER

    9.1 Owner shall make available the auxiliary power supply on chargeable basis at a

    single point in the Sub-station. All further distribution from the same for

    construction and permanent auxiliary supply shall be made by the contractor.However, in case of failure of power due to any unavoidable circumstances, the

    contractor shall make his own necessary arrangements like diesel generator

    sets etc. at his own cost so that progress of work is not affected and Owner

    shall in no case be responsible for any delay in works because of non-

    availability of power.

    9.2 Owner shall make available construction water supply at a single point in the

    substation. All further distribution for the same shall be made by the Contractor.

    In case of non-availability or inadequate availability of water for construction

    work, the contractor shall make his own arrangement at his own cost and the

    Owner shall in no case be responsible for any delay in works because of non-

    availability or inadequate availability of water.

    10.0 SPECIFIC REQUIREMENT

    10.1 The Bidders are advised to visit Sub-stations site and acquaint themselves with

    the topography, infrastructure, etc.

    10.2 The bidder shall be responsible for safety of human and equipment during the

    working. It will be the responsibility of the Contractor to co-ordinate and obtain

  • 8/11/2019 01-Section Project Rev00

    7/12Y:\Process Bus\Pilot Project\01-Section project_rev00.doc

    5

    Electrical Inspectors clearance before commissioning. Any additional items,

    modification due to observation of such statutory authorities shall be provided

    by the Contractor at no extra cost to the Owner.

    10.3 The Relay protection panels shall be placed in switchyard panel room (AC

    Kiosk). The existing panel room (AC Kiosk) shall be used to house Relay

    protection panels in switchyard. The architecture drawing & details of aboveswitchyard panel room is enclosed at AnnexureI of section project of technical

    specification.

    10.4 Erection and commissioning of 1 no. pilot bay consisting optical current

    transformer. Erection, testing & commissioning of Control and protection Panels

    shall be done by the contractors under the supervision of respective equipment

    manufacturers. Charges for the above supervision shall be included by the

    bidder in the erection charges for the respective equipment in the BPS.

    10.5 In Section GTR and other Technical specifications, the term Purchaser and/or

    Employer may be read as Owner.

    10.6 The manufacturer(s) whose optical CTs are offered should have designed,

    manufactured, tested as per IEC/IS or equivalent standard and supplied the

    same for the 220kV or above system voltage and which are in satisfactory

    operation for at least 1 (one) year as on the date of bid opening.

    11.0 SPECIFIC EXCLUSIONS

    The following clauses of specification for C&R panel (for automated sub-station)

    are excluded for this project:

    10.10.2 Back-up Directional Over Current and Earth fault protection scheme

    11.0 Circuit Breaker Protection

    12.0 Line Over Voltage Protection Relay

    13.0 Reactor Protection

    14.0 Transformer Protection

    15.0 TEE Protection Differential Relay

    16.0 Tripping Relay

    17.0 DC Supply Supervision Relay

    18.0 Bus Bar Protection

    20.0 Disturbance Recording

    21.0 Distance to Fault Locator

    23.0 Relay Test Kit

  • 8/11/2019 01-Section Project Rev00

    8/12

  • 8/11/2019 01-Section Project Rev00

    9/12Y:\Process Bus\Pilot Project\01-Section project_rev00.doc

    7

    Annexure-I

    LIST OF DRAWINGS

    S. No. TITLE

    1. Single Line diagram of 400/220kV Bhiwadi S/s.

    2. Substation Layout of 400/220kV Bhiwadi S/s.

    3. Proposed Scheme for Implementation of Process Bus Technology

    4. Switchyard Panel Room of 400/220kV Bhiwadi S/s

  • 8/11/2019 01-Section Project Rev00

    10/12Y:\Process Bus\Pilot Project\01-Section project_rev00.doc

    8

    Annexure-I

  • 8/11/2019 01-Section Project Rev00

    11/12Y:\Process Bus\Pilot Project\01-Section project_rev00.doc

    9

    Bhiwadi S/s Layout

    Proposed

    NCIT

  • 8/11/2019 01-Section Project Rev00

    12/12

    10

    Proposed Scheme