01- Rigid pavement Manual

download 01- Rigid pavement Manual

of 24

Transcript of 01- Rigid pavement Manual

  • 8/14/2019 01- Rigid pavement Manual

    1/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 1

    1. INTRODUCTION

    The purpose of this Pavement Design Manual - Volume II is to give specific guidance

    and recommendations to the engineers responsible for the design of rigid pavements in

    Ethiopia. It is one of the series of Design manuals, Standard Contract Documents andSpecifications The preparation of this rigid pavement design manual is part of the

    framework initiated by ERA to upgrade the highway network in Ethiopia.

    This volume contains :

    o A description of rigid pavements : their characteristics, their components and

    their function, the different types of slabs and joints, including drawing details.

    o A description of the factors influencing the pavement type selection and the

    design process.

    o A design procedure for the different types of pavement, slab reinforcement, joint

    details and joint layout.

    The design method is a directly utilizable one, based mainly on empirical results and full

    scale experiments. Although an analytical, comprehensive approach to the design is

    possible, based on the stresses and strains induced in the pavement by an applied wheel

    loading, it is very complicated, rarely used, leads to minor changes and as such is not

    covered in these pages.

  • 8/14/2019 01- Rigid pavement Manual

    2/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 2

    2. RIGID PAVEMENTS

    2.1 General Characteristics

    Rigid pavements (also called concrete pavements), as the name implies, are rigid and

    very strong in compression. The strength of the pavement is contributed mainly by a

    concrete slab, unlike flexible pavements where successive layers of the pavement

    contribute cumulatively. The rugose surface required for an adequate resistance to

    skidding in wet conditions can be provided by dragging stiff brooms transversely across

    the newly-laid concrete or by cutting shallow randomly spaced grooves in the surface of

    the hardened concrete slab.

    This constitution implies the following advantages :

    o It is feasible to design rigid pavements for longer design lives, up to 60 years.

    o Little maintenance is generally requiredo Rigid pavement do not deform under traffic

    o A relatively thin pavement slab distributes the load over a wide area due to its

    high rigidity. Localized low strength subgrade materials can be overcome due to

    this wider distribution area.

    o Concrete is very resistant to abrasion making the anti-skidding surface texture

    last longer.

    o In the absence of deleterious materials (either in the aggregate or entering the

    concrete in solution from an external source), unlike with flexible pavements,

    concrete does not suffer deterioration from weathering. Neither its strength nor

    its stiffness are materially affected by temperature changes.

    The main disadvantages compared to flexible pavements are as follows :

    o The initial investment is often more costly.

    o If badly designed or not properly constructed, they tend to be more troublesome

    and reconstruction or repair is more difficult.

    Until now, concrete pavements have not been extensively used in most tropical countries

    and in Ethiopia in particular, mainly due to a lack of tradition and experience in their

    design and construction. One characteristic of concrete pavements is that either they

    prove to be extremely durable, lasting for many years with little attention andmaintenance, or they give troubles from the start, sometimes because of faults in design,

    but more often because of mistakes in construction.

    2.2 Types of Rigid Pavements

    Depending on the level of reinforcement, the rigid pavements are categorized into three

    basic types:

    o Jointed Unreinforced Concrete Pavements (JUCP)

    o Jointed Reinforced Concrete Pavements (JRCP)

    o Continuously Reinforced Concrete Pavements (CRCP)

  • 8/14/2019 01- Rigid pavement Manual

    3/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 3

    2.2.1 JOINTEDUNREINFORCEDCONCRETEPAVEMENT

    In Jointed Unreinforced Concrete Pavements (JUCP), the pavement consists in an

    unreinforced concrete slab cast in place continuously and divided into bays of

    predetermined dimensions by the construction of joints. The bays dimensions are made

    sufficiently short so as to ensure that they do not crack. The bays are linked together by

    tie bars, the main function of which is to prevent horizontal movement (i.e. the opening

    of warping joints) and thus ensure load transfer through aggregate interlock.

    2.2.2 JOINTEDREINFORCED CONCRETEPAVEMENT

    In Jointed Reinforced Concrete Pavements (JRCP) the pavement consists generally in a

    cast in place concrete slab divided in reinforced concrete bays separated by joints. The

    reinforcement is made to prevent developing cracks from opening. This allows to design

    much larger bays than with JUCP. The bays are linked together by tie bars to prevent

    horizontal movement and thus ensure load transfer through aggregate interlock. The

    longitudinal reinforcement is the main reinforcement. A transverse reinforcement though

    not absolutely necessary in most cases is usually added to facilitate the placing of

    longitudinal bars.

    2.2.3 CONTINUOUSLYREINFORCED CONCRETEPAVEMENT

    Continuously Reinforced Concrete Pavements (CRCP) are made of a cast in place

    reinforced concrete slab without joint. The expansion and contraction movements are

    prevented by a high level of sub-base restraint. The frequent transverse cracks are held

    tightly closed by a large amount of continuous high tensile steel longitudinal

    reinforcement.

  • 8/14/2019 01- Rigid pavement Manual

    4/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 4

    3. PAVEMENT STRUCTURE

    Rigid pavements generally consist of, as shown in Figure 1 below, a subbase, and aconcrete slab constructed above the subgrade. (With a capping layer if required)

    Figure 1 Rigid Pavement structure

    The capping layer consists of selected fill and is provided in cases of low strength

    subgrade. It allows to increase the bearing capacity of the subgrade and thus enables a

    lesser pavement thickness to be adopted.

    The subbase of a rigid pavement structure consists of one or more compacted layers of

    material placed between the subgrade and the concrete slab. In some cases the materialcan be cement stabilized to increase its quality. If the subgrade materials quality is

    acceptable and if the design traffic is low (less than one million equivalent standard axles

    (ESAs)), a subbase layer may not be necessary between the prepared subgrade and the

    concrete slab.

    A subbase is provided under a concrete pavement for the following reasons:

    o to provide a stable working platform for the construction equipment;

    o to prevent pumping at joints and slab edges.

    The concrete slab consists of Portland cement concrete, reinforcing steel (When

    required), load transfer devices and joint sealing materials.

    Transverse reinforcement is provided to ensure that the longitudinal bars remain in the

    correct position during the construction of the slab. It also helps to control any

    longitudinal cracking that may develop.

    The details regarding the design of the pavement slab thickness and the amount of

    reinforcement required are discussed in Chapter 7.

    Concrete Slab

    Subbase

    Capping Layer

    ( If required)

    Natural ground or

    embankment

    Subgrade

    Ri id Pavement

  • 8/14/2019 01- Rigid pavement Manual

    5/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 5

    4. JOINTS

    Joints are placed in concrete pavements, whether reinforced or not to permit expansion,

    contraction and warping of the slab, thereby relieving stresses due to environmental

    changes (Temperature and moisture) and friction, and to facilitate construction. Jointsare classified according to their direction, either transverse or longitudinal and upon their

    function. They are either contraction, expansion, warping or construction joints and in

    most cases , they combine several of these functions.

    Typical details of the different types of joints are presented in Appendix B (adapted from

    Ref. 8).

    4.1 Transverse Joints

    Transverse Joints are the joints perpendicular to the centerline of the road. They are

    designed to prevent contraction and expansion stresses which develop over long

    distances. In some specific places like around in-pavement objects or at junctions,

    transverse joints are also required to limit warping stresses.

    4.1.1 CONTRACTIONJOINTS

    Contraction joints are the main type of transverse joints. They are provided in JRCP and

    JUCP to relieve the tensile stresses due to temperature or moisture changes and friction.

    They provide weakened sections between bays to induce tension cracking at preferred

    locations in the concrete after it has been placed. If contraction joints were not installed,

    random and uncontrolled cracking would occur on the surface of the pavement. They

    also contribute to the limitation of the warping stresses.

    Load transfer between bays is provided by dowels.

    Contraction joints shall consist of:

    o a sawn joint groove

    o dowel bars

    o a sealing groove

    The groove and sealant shall be as specified. The dowel bars shall be 20 mm in diameter

    at 300 mm spacing, 400 mm long for slabs up to 239 mm thick, and 25 mm in diameter

    for slabs 240 mm thick or more.

    4.1.2 EXPANSIONJOINTS

    The primary function of an expansion joint is to provide space for the expansion of the

    slab, thereby preventing the development of compressive stresses, which may cause the

    slab to buckle. Expansion joints are also contraction joints. Transverse expansion joints

    are used at the limit between CRCP and other types of pavement or structures andsometimes at regular intervals in JUCP and JRCP.

    The construction of this type of joints is relatively costly and they require high levels of

    maintenance. If not well maintained and not functioning properly, they tend to stay

    closed after expansion of the slab, which induces excessive opening of the adjacent

    contraction joints, thus being a cause of failure. They are consequently avoided as far aspossible and it is often preferred to accept to maintain localized failures due to expansion

    stresses than to run the risk of serious distress at the expansion joints.

  • 8/14/2019 01- Rigid pavement Manual

    6/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 6

    They are generally not required if the slab is cast during the hottest time of the year.

    In expansion joints, complete separation between the two adjacent concrete bays is

    required, and a compressible joint is used to fill the void.

    Load transfer between bays is provided by dowels.

    Expansion joints shall consist of :

    o a joint filler board

    o dowel bars

    o a sealing groove

    The joint filler board and sealing groove shall be as per the Specifications. The dowel

    bars shall be 25 mm in diameter at 300 mm spacing, 600 mm long for slabs up to 239

    mm thick, and 32 mm in diameter for slabs 240 mm thick or more.

    Warping Joints

    Warping joints allow a slight relative rotation of the bays and reduce the stresses due to

    warping.

    Transverse warping joints are used for special cases, such as extra joints at manhole

    positions, or when unreinforced slabs are alongside reinforced slabs, or in long and

    narrow or tapered (odd-shaped) JUCP slabs between normal joint positions, to reduce the

    length/width ratio of the bays to 2 or less, and in other similar situations.

    Warping joints shall consist of:

    o a sawn groove

    o tie barso a sealing groove

    The sealant shall be as per the Specifications. The tie bars shall be 12 mm in diameter at

    300 mm spacing, and 1000 mm long.

    4.2 Longitudinal Joints

    Longitudinal joints are warping joints, allowing a slight relative rotation of the slab

    portions and reducing the stresses due to warping. They are required at such a spacing

    that they will reduce the combination of thermal warping stresses and loading stresses to

    a minimum, they also reduce the risk of longitudinal random cracking, and often serve atthe same time as construction joints. These joints allow a slight rotation, but differential

    lateral displacements between adjacent bays are prevented by tie bars provided at mid-

    depth of the slab.

    These tie bars also prevent the opening of the cracks and thus the Load transfer is

    achieved through aggregate interlock.

    Longitudinal joints shall consist of :

    o bottom crack inducer

    o a sawn groove

    o tie barso a sealing groove

  • 8/14/2019 01- Rigid pavement Manual

    7/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 7

    The sealant shall be as per the Specifications. The tie bars for all longitudinal joints,

    except where transverse reinforcement is permitted in lieu, shall be 12 mm in diameter at

    600 mm spacing, and 1000 mm long.

    4.3 Construction Joints

    Construction joints are required to facilitate construction, especially when concreting is

    stopped.

    In JUCP and JRCP, they shall be coupled with other joints

    Additional reinforcement shall be placed when dealing with transverse construction

    joints for CRCP. This can be achieved by providing for each longitudinal bar, a 700mm

    long reinforcement bar (Dia. 20mm ) centered on the joint as shown in Figure 2 below.

    Figure 2 Transverse construction joint for CRCP slabs

  • 8/14/2019 01- Rigid pavement Manual

    8/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 8

    5. SELECTION OF THE PAVEMENT TYPE

    The highway engineer or administrator does not have at his disposal an absolute or

    indisputable method for determining the type of pavement which should be selected for a

    given set of conditions.

    First a judgment must be made on many varying factors such as traffic, soil, weather,

    materials, construction, maintenance and environment. In some cases overriding factors

    can dictate pavement type. For instance, for heavily traveled facilities in congested

    locations, the need to minimize the disruptions and hazard to traffic may dictate the

    selection of CRCP.

    When there is no overriding factor, which may often be the case, it is standard practice to

    design typical sections of the road using each of the available options and then to

    compare them on an economical point of view.

    Unavoidably, there will be instances where financial circumstances are such to make firstcost the dominate factor in selection, even though higher maintenance or repair costs may

    be involved at a later date.

    Where circumstances permit, a more realistic economical evaluation has to take into

    account all expected costs including the initial cost of construction, the cost of

    subsequent stages or corrective works, anticipated life, maintenance cost and salvage

    value. Costs to road users during periods of reconstruction or maintenance operations are

    also appropriate for consideration.

    Although pavement structures are based on an initial design period, few are abandoned at

    the end of this period and continue to serve as part of the future pavement structure. For

    this reason, the analysis period should be of sufficient duration to include a representativereconstruction of all pavement types.

    Figure 3 Pavement type selection process

  • 8/14/2019 01- Rigid pavement Manual

    9/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 9

    If the analysis of the above given factors does not show a far higher interest of one option

    rather than another, a second set of factors can be considered such as the performance of

    similar pavements in the area or the skills of contractors.

    Basically, the use of the different types of rigid pavement is as follows:

    o JUCP is suitable for all levels of traffic, whenever the risk of subgrade

    movement is low.

    o JRCP is suitable for all levels of traffic and is used when the risk of settlements

    of the subgrade can not be neglected.

    o CRCP shall basically be considered only for rather high design traffic (>30

    msa). They can also be included for less heavily trafficked schemes where the

    advantage of lower maintenance throughout the design life may be worthwhile.

    they are particularly suitable were settlement of the sub-soil is expected.

  • 8/14/2019 01- Rigid pavement Manual

    10/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 10

    6. STRESS DEVELOPMENT AND DESIGN CRITERIA

    6.1 Stress Development

    The concrete slabs in concrete pavement are subjected to two main types of stresses :

    o The stresses developed because of changes of the environment (moisture and

    temperature) and closely depending upon the intrinsic properties of the concrete.

    In Ethiopia, though the annual range of temperature is small, the daily range of

    temperature is high, varying from 20C to 40 C (Ref. 1), and hence thermal

    stresses deserve special attention.

    o The stresses coming from the traffic loads.

    Both types of stresses can not be prevented from developing, but the design of concrete

    pavement shall take them into account in order to keep them in acceptable ranges of

    values. Analytical methods have been developed aiming at computing accurately the

    stresses developed in concrete pavements for a theoretical design. But they are rather

    complicated and necessitate strong hypothesis on the quality and the evolution of the

    different layers composing the subgrade. That is why the approach of this manual is

    limited to a qualitative description of the phenomena which justify the pragmatic design

    procedure exposed in section 7.

    6.1.1 HORIZONTAL TENSILE STRESSES

    While hardening and later depending on external humidity, the moisture rate of the

    concrete decreases, thus inducing tensile stresses in the material.

    When the temperature drops after hardening, thermal tensile stresses are also induced,

    depending on the thermal coefficient of the concrete.

    Since the movements of the lower face of the pavement are limited by the friction with

    the subbase, cracks appear as soon as the sum of these tensile stresses exceed the

    concrete tensile strength. When cracks become too wide, they enable water infiltration or

    slabs and subgrade vertical movements thus accelerating the degradation of the

    pavement.

    Depending on the type of slab this issue is coped with differently:

    In JUCP

    The development of cracks is controlled by placing joints at regular intervals and a

    separation membrane between the slab and the subbase. The limited lengths of the bays

    and the increased possibility of horizontal movements limit the tensile stresses and thus

    prevent the slabs from cracking between joints.

    In JRCP

    The transverse cracks which are expected to develop between transverse joints are held

    tightly closed by the longitudinal reinforcement that is incorporated into the slab.

  • 8/14/2019 01- Rigid pavement Manual

    11/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 11

    In CRCP:

    The continuous reinforcement causes the cracking to occur at regular and little spaced

    locations thus limiting the opening of cracks to acceptable values.

    6.1.2 HORIZONTAL COMPRESSIVE STRESSES

    If the temperature rises after hardening, thermal compressive stresses are induced,

    depending on the thermal coefficient of the concrete. If they become too high, this may

    cause the slab to buckle.

    According to the type of slab, this issue is treated as follows:

    In JUCP and JRCP:

    The placing of expansion joints and the increased possibility of movement through the

    use of the separation membrane permit the expansion of the concrete and the dissipation

    of compressive stresses. Nevertheless, the issue is avoided as far as possible in casting

    the concrete at the hottest period of the year.

    In CRCP:

    The continuous reinforcement increases the resistance of slabs but the compressive

    strength remain limited and the slab is prone to expansion failure. It is thus preferable to

    cast CRCP slabs during the hottest time of the year to limit the potential of thermal

    expansion.

    6.1.3 WARPING STRESSES

    Warping stresses occur in rigid pavement slabs when variations in moisture contentand/or temperature from the top to the bottom of the slab occur.

    In dry climate, or dry periods, the top of the slab is drier than the bottom, causing the

    edges of the slab to tend to heave as represented in Figure 4 below and inducing tensilestresses at the top of the slab and compressive stresses at the bottom. Permanent warping

    stresses also generally occur because the top of the slab cures faster and shrinks more

    than the bottom.

    Figure 4 Curling of concrete slab due to moisture gradients

    During daytime, the top of the slab tends to be warmer than the bottom, causing the

    middle of the slab to tend to heave and inducing tensile stresses at the bottom of the slaband compressive stresses at its top as represented in Figure 5 below.During nighttime, the opposite phenomenon occur.

    Drier

    Wettertension

    Base

    Concrete slab self

    weight and traffic loads

  • 8/14/2019 01- Rigid pavement Manual

    12/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 12

    Figure 5 Curling of concrete slab due to temperature gradients

    Warping stresses are limited in providing joints, either warping or contraction joints

    which allow a slight relative rotation of the bays.

    6.1.4 SHEAR AND BENDING STRESSES

    With a minimum concrete thickness of 150 mm and a theoretical continuous support on

    the subbase shear and bending stresses developed by the traffic loads are not prejudicial

    to rigid pavement except in case of punctual loss of support due to movements of thesubbase or of the subgrade. The continuous transmission of vertical loads along the

    pavement is essential because relative vertical movements of the bays create pumping

    mechanisms which accelerate dramatically the deterioration of the subbase.

    6.2 Design Criteria

    As above explained, the factors which shall intervene in the design of rigid pavements

    are as follows:

    o the subgrade quality

    o the quality of the steel and concrete composing the slabs

    o the traffic

    o the environment (Moisture and temperature)

    o the notional design life

    For the simplified experience-based design procedure exposed in this manual, the

    assumption is made that the materials used for construction meets the standard

    requirements as defined in section 3. Which means mainly a yield strength of 500 MPa

    for the steel reinforcement bars and a 28 day characteristic compressive strength of 40

    MPa for the concrete.

    As stated in the previous section, the accurate computation of the stresses in the concrete

    is not in the scope of this manual and thus, the proposed thickness design procedure and

    Cooler

    hottertension

    Base

    Concrete Slab self

    weight and traffic loadsNighttime

    hotter

    Cooler

    tension

    Base

    Concrete Slab self

    weight and traffic loadsDaytime

  • 8/14/2019 01- Rigid pavement Manual

    13/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 13

    joint layout for rigid pavement is suitable for the usual natural ranges of temperature and

    moisture rates.

    Consequently, the two parameters to be accounted for in the design procedure are the

    traffic data and the bearing capacity of the subgrade.

  • 8/14/2019 01- Rigid pavement Manual

    14/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 14

    7. DESIGN OF RIGID PAVEMENTS

    A general methodology of rigid pavement design is presented in Figure 9, page 20.

    7.1 Design life

    Due to the structural properties of concrete slabs, their durability is very good and they

    can be designed for periods of up to 60 years. If properly constructed, the pavement will

    last long with a good level of serviceability and low maintenance requirements.

    It is common practice to design concrete pavements for 40 years or more. Given that the

    required slab thickness varies linearly with the logarithm of the cumulated number of

    ESAs, designing for longer periods generally requires marginal additional slab thickness

    and reinforcement and proves to be more economical.

    This possibility to design rigid pavements for more than twice the maximum design lifeof flexible pavements and the lower associated maintenance costs make them generally

    more economical in the long term.

    7.2 Design Traffic Loading

    The method for computing Cumulative Equivalent Axle Load over the design life is

    described in in ERA Pavement Design Manual 2002, volume 1, Chapter 2. The same

    method is used for rigid pavement but the equivalency factors to be used are those given

    in table 1.

    Table 1

    Equivalency Factors for Different Axle Loads(Rigid Pavements)

    Wheel load (103

    kg)

    (single and dual)

    Axle load

    (103

    kg)

    Equivalency

    factor

    1.5 3.0 0.02

    2.0 4.0 0.05

    2.5 5.0 0.13

    3.0 6.0 0.28

    3.5 7.0 0.53

    4.0 8.0 0.934.5 9.0 1.53

    5.0 10.0 2.40

    5.5 11.0 3.63

    6.0 12.0 5.25

    6.5 13.0 7.33

    7.0 14.0 9.92

    7.5 15.0 13.1

    8.0 16.0 17.0

    8.5 17.0 21.6

    9.0 18.0 27.1

    9.5 19.0 33.7

    10.0 20.0 41.4

  • 8/14/2019 01- Rigid pavement Manual

    15/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 15

    These factors are marginally higher, when compared with the corresponding values from

    Table 2.3 of ERA Pavement Design Manual Volume 1, for loads up to the standard axle

    load. However, for heavier loads, the equivalency factors for rigid pavements are lower

    and the difference increases exponentially. This reflects the facts that rigid pavements are

    more resistant to heavy loads because of the capacity of the concrete slab to spread loads

    over a large surface of subbase.

    7.3 Thickness Design

    7.3.1 CAPPING AND SUBBASE

    A capping layer is required only if the CBR of the subgrade is 15% or less. The required

    thickness of a capping layer for a CBR value inferior to 15% can be obtained from Figure10, page 21.

    The subbase layer is required when the subgrade material doesnt comply with the

    requirement for a subbase (CBR is less than 30%) but it is almost always used tofacilitate the obtaining of surface levels with the tolerances required. Generally, the

    thickness of the subbase provided will be a constant 15 cm and can be cement stabilized.

    For subgrade CBR values inferior to 2%, the subgrade material needs to be treated either

    by replacement or in-situ stabilization. These methods of soil improvement are described

    in section 7 of the Pavement design manual- Vol. I2002.

    A separation membrane (such as a polythene sheet) is required between subbase and

    concrete slab, mainly in order to reduce the friction between the slab and the subbase in

    JUCP and JRCP pavements, and thus inhibits the formation of mid-bay cracks. It also

    reduces the loss of water from the fresh concrete. For CRCP pavements, a bituminousspray should be used on the subbase, instead of polythene, because a high degree of

    restraint is required.

    7.3.2 CONCRETESLAB THICKNESS ANDREINFORCEMENT

    Based on the design traffic volume expressed in Equivalent Standard Axle determined as

    per sub section 7.2 and project-specific characteristics, the thickness of pavement isdetermined.

    The following represents procedures for determining the thickness and reinforcement for

    each of the pavement types.

    Jointed Unreinforced Concrete Pavement (JUCP)

    For a given traffic volume in terms of ESAs, the thickness of JUCP concrete slab can be

    determined using Figure 12, page 22.Figure 4 assumes the presence of an effective lateral support to the edge of the most

    heavily-trafficked lane (i.e., the right lane), such as a shoulder with a pavement structure

    able to carry occasional loads. In the absence of such a shoulder adjacent to the most

    heavily trafficked lane, an additional slab thickness is required, and this additional

    thickness can be determined using Figure 14, page 23.JUCP pavements have no reinforcement. However, the longitudinal and transverse jointsare provided with dowels or tie bars depending upon the type of joint. The joint details

    are described in section 4.

  • 8/14/2019 01- Rigid pavement Manual

    16/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 16

    Jointed Reinforced Concrete Pavement (JRCP)

    For a given traffic volume in terms of ESAs, the thickness of a JRCP concrete slab can

    be determined using Figure 12, page 22. The figure can also be used to determine thelongitudinal reinforcement in terms of mm

    2/m for a given concrete slab thickness. Thus,

    several alternate combinations of thickness of concrete slab and amount of reinforcement

    can be compared.

    In the absence of an effective lateral support provided by the shoulder adjacent to the

    most heavily trafficked lane, an additional slab thickness is required and can be

    determined using Figure 14.In addition to the longitudinal reinforcement, JRCP pavements shall be provided with

    transverse reinforcement, consisting of 12 mm diameter steel bars at 600 mm spacing.

    Continuously Reinforced Concrete Pavement (CRCP)

    CRCP pavement can withstand severe stresses induced by differential movements. For a

    given traffic volume, in terms of ESAs, the thickness of CRCP concrete slab can be

    obtained from Figure 13.Longitudinal reinforcement in CRCP pavements shall be 0.6% of the concrete slab cross-

    sectional area, consisting of 16 mm diameter deformed steel bars. Transverse

    reinforcement shall be provided at 600 mm spacing, consisting of 12 mm diameter

    deformed steel bars, to prevent the opening of any longitudinal cracks which may form.

    Transverse reinforcement is required for ease of construction.

    Similarly to JUCP and JRCP pavements, in the absence of effective shoulder support

    adjacent to the most heavily trafficked lane, the additional slab thickness required can be

    determined using Figure 14.As is evident from Figure 12 and Figure 13, the minimum thickness of concretepavement for JUCP and JRCP pavement is 150 mm and that for CRCP pavement is 200

    mm. Hence, the designer should carefully assess the necessity and requirements for such

    pavements, depending on the design traffic volume, and shall include flexible pavement

    as an alternate.

    A design example of rigid pavement design is presented in Appendix A.

    7.4 Design for Movement

    Joints shall be designed according to the general considerations of sub section 4 and

    using Drawings B2 to B8.

    The general layout of joints shall account for construction consideration and the

    following limitations concerning joint spacing and bays dimensions:

    7.4.1 TRANSVERSEJOINTSPACING

    Maximum transverse joint spacing for JUCP pavements is 4 m for slab thickness up to

    230 mm and is 5 m for slab thickness over 230 mm.

    For JRCP, contraction joints are generally at a standard distance of 25m.

  • 8/14/2019 01- Rigid pavement Manual

    17/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 17

    Expansion joint are required at the limit with other pavement types or with structures like

    bridges.

    In the current section, expansion joints shall be avoided in casting the concrete slab at the

    hottest period of the year. If required, expansion joints should replace every third

    contraction joint.

    7.4.2 LONGITUDINAL JOINT SPACING

    Longitudinal joints shall be placed at the edge of each traffic lanes.

    7.5 Design detailing

    7.5.1 BAY-LAYOUT

    In the current sections of the road, the longitudinal and transverse joints placed as

    described in the previous sub-sections divide the slabs in even rectangular bays. Atspecial locations, like crossings or junctions or when manholes or gulleys are fund,

    adapted layouts fitting the road geometry must be adopted, in order to prevent the

    development of warping stresses. The main principles for designing the joints layout at

    special locations are :

    o to avoid long, narrows bays with a length/width ratio greater than 2.

    o to avoid bays with acute angled corners.

    o to avoid bays with re-entrant angles.

    The sketches in Figure 6 below present a possible layout for bays at crossing andjunctions illustrating these principles.

    Intersection oftransverse joints

    Longitudinal joints Transverse joints

    Figure 6 Joints layout at junctions and crossings

    7.5.2 GULLIES AND MANHOLES

    When gullies, manholes and other in-pavement objects are found, it is essential to

    prevent the concrete slab from been supported by the structure. This shall be achieved in

  • 8/14/2019 01- Rigid pavement Manual

    18/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 18

    boxing out around the object, which means providing an expansion joint without load

    transfer device.

    Since the opening in the slab structure is likely to create a weakened section prone to

    cracking, it is necessary to locate it at the crossing of normal joints or with additional

    warping joints as shown in Figure 7 below.

    Figure 7 Box-out around in-pavement objects : layout of joints

    7.5.3 I NTEGRALCURBS

    Where sidewalks are required. Integral curbs shall be used and linked to the carriageway

    slab by a longitudinal joint.

    All transverse joints shall extend continuously through the pavement and curb.

    Figure 8 below shows typical dimensions and construction provisions for rigid pavementintegral curbs.

    Figure 8 Typical Integral Curb

  • 8/14/2019 01- Rigid pavement Manual

    19/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 19

    7.5.4 ENDANCHORAGE FOR CONTINUOUSLYREINFORCEDPAVEMENTSLABS

    At CRCP slabs ends (connection with flexible pavements, other concrete pavement types

    or structures) anchorage devices are required because the surface of friction is not

    sufficient to counterbalance the contraction and expansion stresses, which could provoke

    the formation of wide openings.

    This can be achieved in providing a succession of reinforced concrete lugs which anchor

    the slab in the soil. The lugs are typically bout 1 m deep, they cover the all width of the

    slab and are placed every 5 meters over the 30 last meters of the continuous reinforced

    pavement. Refer to drawing B6 in appendix B for the design details.

  • 8/14/2019 01- Rigid pavement Manual

    20/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 20

    Figure 9 Design Methodology flow diagram

    Check forRequirement ofCapping Layer

    No

    DetermineCappingLayer Thicknessfrom Figure 3.2

    DetermineConcrete SlabThickness and

    Reinforcement from Figure3.3.

    Determineslab thicknessfrom Figure 3.3.

    Check for Site Constraints,if any.

    Determine pavement type.

    Determine Concrete SlabThickness from Figure

    3.4.

    CRCP

    Check for requirement of

    transverse reinforcement (cf. 3.2).

    Determine joint type

    Determine additional slabthickness from Figure 3.5.

    Yes

    JRCP

    JUCPDetermine longitudinal

    reinforcement (cf. 3.2)

    Determine

    Design CBR

    Design ESAs

  • 8/14/2019 01- Rigid pavement Manual

    21/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 21

    Figure 10 Capping Layer and Subbase Thickness design(Adapted from Ref.5)

    Figure 11 Joint spacing for JUCP and JRCP Slabs

    18

    19

    20

    21

    22

    23

    24

    25

    26

    1 10 100 1000

    Design Traffic (millions of ESAs)

    3

    4

    5

    6

    7

    8

    9

    10

    11

    JUCP

    Type of

    Pavement2

    JRCP

    4

    5

    400

    Spacing of transverse

    Joints (m)

    -200

    -100

    0

    100

    200

    300

    400

    500

    0 5 10 15 20 25 30150

    ImproveSubgrade

    2

    Capping Layer

    Thickness

    Subbase Thickness

    Subgrade CBR ( %)

    CappingLayer and

    Subbase Thickness

  • 8/14/2019 01- Rigid pavement Manual

    22/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 22

    Figure 12 Design Thickness for JUCP and JRCP Slabs(Adapted from Ref. 5)

    Figure 13 Design Thickness for CRCP Pavement

    100

    150

    200

    250

    300

    350

    400

    1 10 100 1000

    Design Traffic (millions of ESAs)

    0 JUCP500

    600

    700

    800

    JRCP

    Longitudinal

    Reinforcement

    (mm2/m)

    0

    50

    100

    150

    200

    250

    300

    1 10 100 1000

    Design Traffic (Millions of ESAs)

    DesignThickn

    essofconcrete(mm)

  • 8/14/2019 01- Rigid pavement Manual

    23/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    Ethiopian Roads Authority Page 23

    Figure 14 Additional Concrete Slab Thickness for Rigid Pavements WithoutLateral Support

  • 8/14/2019 01- Rigid pavement Manual

    24/24

    Pavement Design Manual - 2002 ChapterErreur ! Style non dfini.Volume II - Rigid Pavements Erreur ! Style non dfini.

    REFERENCES

    1. ETHIOPIAN MAPPING AUTHORITY (1988). National Atlas of Ethiopia.

    2. ETHIOPIAN ROADS AUTHORITY (2000). Pavement Design Manual, Volume

    1, Flexible Pavements and Gravel Roads.

    3. TRANSPORT RESEARCH LABORATORY (1993). Road Building in the

    Tropics. State-of-the- Art Review, No. 9.

    4. AMERICAN ASSOCIATION OF STATE HIGHWAY and

    TRANSPORTATION OFFICIALS (1993). AASHTO Guide for Design of

    Pavement Structures.

    5. THE DEPARTMENT OF TRANSPORT, London (1997). Design Manual for

    Roads and Bridges.

    6. HIGHWAYS AGENCY, UK (1998). Manual of Contract Documents for

    Highway Works, Vol. 1: Specification for Highway Works.

    7. HIGHWAYS AGENCY, UK (1998). Manual of Contract Documents for

    Highway Works, Vol. 2: Notes for Guidance on the Specification for Highway

    Works.

    8. HIGHWAYS AGENCY, UK (1998). Manual of Contract Documents for

    Highway Works, Vol. 3: Highway Construction Details.