01 57 19 - Environmental Controls

download 01 57 19 - Environmental Controls

of 35

Transcript of 01 57 19 - Environmental Controls

  • 8/9/2019 01 57 19 - Environmental Controls

    1/84

    Toronto Transit Commission

    CONTRACT A29-1

    1

    DESCRIPTION

    Section 1 57 9

    ENVIRONMENTAL CONTROLS

    Page

    1.1

    This Section covers Work for protection

    of

    the environment during construction, Site

    preparation and demolition Work.

    1.2 Provisions

    of

    this Section are in addition to requirements

    of

    other Sections

    of the

    Contrac

    Documents.

    2

    DEFINITIONS

    2.1

    Alert Level: Monitored level specific for each individual environmental aspect at which

    environmental contingency measures must be implemented.

    2.2 Corrective Action: Action to eliminate the cause of a detected nonconformity.

    2.3 Complaints Protocol: Jurisdiction specific (e.g. The City

    of

    Toronto) procedures to be

    followed if a complaint is received from either the public

    or

    an affected third party (Refer to

    Attachment 6 .

    2.4 Comprehensive Environmental Controls and Methods Program (CECMP): Contractor s

    specific approach to address environmental controls at each construction Site. The

    Contractor s and its Subcontractor s management system shall be used to develop and

    implement all environmental aspects.

    2.5 Environment: Surroundings in which the Contractor and its Subcontractors operate

    including air, water, land, natural resources, flora, fauna, humans and their interrelation.

    2.6 Environmental Aspect: An element of the Contractor s activities, Products or services tha

    can interact with the environment.

    2. 7 Environmental Inspection Log ElL): Daily environmental reporting form prepared for each

    construction Site (Refer to Attachment 1 .

    2.8 Environmental Performance: The measurable results of the Contractor s and its

    Subcontractors management of its environmental aspects.

    2.9 Environmental Objectives: Toronto York Spadina Subway Extension Project s overal

    environmental goals consistent with the approved environmental assessments nd those

    referenced in the subsequent Articles of this Section.

    2.10 Environmental Target: Detailed performance requirements applicable to this Contract as

    described in subsequent Articles, as shown

    on

    Drawings and in applicable Appendices.

    2.11

    Incident Follow-Up Report Form: Form to be used to report all environmental incidents

    occurring at any Site (Refer to Attachment 3).

    2.12 Noise Monitoring Report Form: Form to be sued to report all noise monitoring records

    throughout construction for each Site (Refer to Attachment 4).

    2.13 Preventive Action: Action to eliminate the cause of potential non-conformity.

  • 8/9/2019 01 57 19 - Environmental Controls

    2/84

    Section

    01 57 19

    ENVIRONMENTAL CONTROLS

    Page2

    Toronto

    Transit Commission

    CONTRACT A29-1

    2.14 Proactive Mitigation: Means, methods and procedures instituted by the Contractor to

    implement the environmental aspects of the CECMP.

    2.15 Procedure: Specified way to carry out an activity or process.

    2.16 Record: Document(s) stating results achieved or providing evidence of activities

    performed. These will include, but are not limited to, the

    Ell

    (Refer to Attachment 1 , the

    Weekly Summary Report (Refer to Attachment 2), the Incident Follow-up Report (Refer to

    Attachment

    3 ,

    Construction Noise Monitoring Form (Refer to Attachment 4)

    and

    the

    Construction Vibration Monitoring form (Refer to Attachment 5).

    2.17 Thermal Effects Monitoring Form: Reporting form for thermal effects monitoring of

    dewatering effluent and the discharge effects at creek outfalls (Refer to Attachment 8).

    2.18 Trigger Level: Monitored level at which proactive mitigation specific to each environmental

    aspect must be initiated and reported on in the Ell.

    2.19 Vibration Monitoring Form: Reporting form for ongoing construction vibration monitoring

    results at each Site to support Ell and Weekly Summary Report(s) (Refer to Attachment 5).

    2.20 Weekly Summary Report: Reporting form to be used to summarize issues identif ied in the

    daily Ell and report on status of remedies or corrective actions taken Refer to

    Attachment 2).

    3 CONTRACTOR S RESPONSIBILITIES

    3.1 The Contract Documents detail the minimum environmental protection requirements,

    specifications, monitoring, reporting, materials and construction staging that the Contractor

    shall install and implement. The Contractor may, at its own expense, recommend the

    implementation

    of

    other or additional measures to suit the Contractor s selected

    means

    and

    methods in accordance with all regulatory permits and requirements. Proposed alternative

    measures shall be provided to the Commission s Representative prior to commencing any

    Work and be submitted in accordance with Section

    01

    33 00.

    3.2 The Contractor shall install, implement and maintain in good working order, all

    environmental controls and monitoring

    as

    set out in the Contract Documents, together with

    any additional monitoring deemed necessary in order to perform the Work with Contractor s

    selected means and methods.

    4 SUBMITTALS

    4.1

    Unless noted otherwise, within thirty (30) calendar days

    of

    date

    of

    Notice to Proceed and as

    agreed to by the Commission s Representative, submit a Comprehensive Environmental

    Controls and Methods Program (CECMP) to the Commission s Representative for all

    disciplines identified in this Section covering the first ninety (90) days of the Work, or as

    required to confirm or establish any baseline monitoring requirements as detailed in the

    Contract Documents. The Contractor shall make appropriate amendments to the plans as

    requested by the Commission s Representative.

  • 8/9/2019 01 57 19 - Environmental Controls

    3/84

    Toronto

    Transit Commission

    CONTRACT A29-1

    Section 01 57

    9

    ENVIRONMENTAL CONTROLS

    Page3

    4.2

    5

    5 1

    5 2

    5 3

    1

    Within sixty (60) calendar days of date of Notice to Proceed submit for the Commission s

    Representative s review a set of CECMPs for all disciplines identified in this Section

    covering the entire schedule of the Work for each construction Site. The Contractor sha

    make appropriate changes to the plans as requested by the Commission s Representative

    and issue.

    CONTRACTOR S COMPREHENSIVE ENVIRONMENTAL CONTROLS

    AND

    METHODS

    PROGRAM {CECPM)

    The Contractor shall provide a CECMP comprising Site specific environmental controls and

    methods, monitoring, testing implementation and record keeping as applicable to the

    environmental aspect of the Work for each construction Site in a

    manner

    generall

    consistent with the IS014001 :2004 Environmental Management Systems. The CECPM

    shall address all phases of the Work, including temporary works design and construction

    materials procurement and construction.

    The CECMP shall establish, document, implement, maintain and continually improve the

    CECMP in accordance with the requirements of these Contract Documents, all applicable

    regulations and requirements, and the conditions of all permits associated

    with

    this Wor

    and determine how it will fulfill tt)ese requirements.

    At a minimum the Contractor s CECMP shall include the following categories describing the

    Contractor s commitment to

    and

    procedures covering:

    General Requirements:

    1 Control of the Comprehensive Environmental Controls and Methods Program .

    .2 Project Environmental Commitment:

    1 The environmental philosophy to be followed on the Work and provide direction to

    action in order to avoid delays in identifying and addressing environmental impact

    arising from the Work

    .2 The applicable mitigation measures and follow-up requirements during

    the

    Work

    .3 The contingency and response procedures related to the discovery of unexpected

    Site conditions .

    4 The roles and responsibilities for the Contractor and Subcontractor(s), including Wor

    accountability and institution of reporting protocols with respect to environmenta

    aspects .

    . 5 Implement an Environmental Awareness Training Program (EATP} to

    ensure

    that a

    on-Site personnel understand the importance

    of

    environmental protection, the cause

    of environmental damage, proper environmental protection practices and the

    Contractor and Subcontractor( s) obligations to ensure that the environment is

    protected .

    .6 Implement an adaptive monitoring and management program to verify that a

    environmental protection measures required in this Section are being properly

    implemented and maintained and are effective

    .7 Collection and maintenance of records are maintained to monitor the effectiveness o

    environmental controls.

  • 8/9/2019 01 57 19 - Environmental Controls

    4/84

  • 8/9/2019 01 57 19 - Environmental Controls

    5/84

    Toronto

    Transit

    Commission

    CONTRACT A29-1

    Section

    1 57 9

    ENVIRONMENTAL

    CONTROLS

    Page 5

    3 Guidance on Sampling and Analytical Methods for use at Contaminated Sites in

    Ontario, Dec 1996

    .4 Guideline for Implementing Spill Prevention and Contingency Plan Regulatory

    Requirements {O.Reg. 224/07)

    .4 Ministry of Transportation Ontario {MTO), MTO Drainage Management Manual

    {DMM), {1997) .

    .5 Ontario Regulations, standards and guidelines pertaining to waste effluen

    monitoring, erosion and sediment control, air, polychlorinated biphenyls {PCBs)

    spills, 3 R regulations {Reduce, Reuse, Recycle) and any other regulations affecting

    the environment.

    6

    Ontario Provincial standards where specifically identified

    in

    the Contract Document.

    1 Ontario Provincial Standard Specification {OPSS)

    .2 Ontario Provincial Standard Drawing (OPSD)

    .7 Municipal by-laws pertaining to sewer use, sediment and erosion control, noise and

    vibration, and any other environmental requirements from the applicable jurisdiction

    depending

    on

    the location

    of

    the construction component activities .

    .8 Toronto and Region Conservation Authority (TRCA), Regulation

    of

    Development

    Interference with Wetlands and Alterations to Shorelines and Watercourses {Ontario

    Regulation 166/06)

    .9 Greater Golden Horseshoe Area Conservation Authorities Erosion and Sedimen

    Control Guidelines for Urban Construction, December 2006 .

    . 1

    0 The Contractor shall identify any additional regulations or requirements that must

    be

    met

    .2 Execution, Implementation and Operation:

    1

    Establish baseline, conditions trigger and alert levels and approach for each

    environmental aspect

    .2 Establish and implement program for each environmental aspect.

    3

    Establish and implement reporting and communication protocols using reporting tools

    appended herein

    .3 Resources, Roles, Responsibility and Authority:

    1 Define Contractor's responsibilities and management commitment for environmenta

    aspects

    .2 Identify personnel and authorities for all Work associated with environmental aspects

    .1 The Contractor shall ensure the availability of resources essential

    to

    establish

    implement, maintain and improve the CECMP. Resources include human

    resources and specialized skills organization infrastructure, technology and

    financial resources .

    .2 The Contractor shall employ a full time qualified Environmental Manager to be

    responsible for the monitoring, data collection, inspections, and reporting

    o

    compliance with all Contract Environmental requirements and permit conditions

    The Contractor shall implement and operate the CECMP and ensure the

    availability

    of

    resources essential to establish, implement, maintain and improve

    the CECMP.

  • 8/9/2019 01 57 19 - Environmental Controls

    6/84

    Section

    1

    57 19

    ENVIRONMENTAL CONTROLS

    Page

    Toronto Transit Commission

    CONTRACT A29 1

    .3 Contact information for

    the

    Environmental Manager shall be provided, including

    business phone, after hours phone, fax, email and mailing address

    4 All plans, monitoring programs and reports shall be reviewed, stamped and

    sealed by a Professional Engineer or Professional Geoscientist licensed in the

    Province of Ontario .

    .5 The Environmental Manager shall assess the effectiveness of Project

    environmental protection measures to ensure that:

    1

    Environmental protection measures are adequate for need and

    functioning as intended .

    .2 All required monitoring and testing equipment is checked regularly and is

    in working order. All failed devices are replaced within twenty-four (24) to

    forty-eight ( 48) hours, depending on

    individual monitoring requirements .

    .3 Deficiencies are corrected immediately

    .4 All daily, weekly, and monthly records, logs, and reports are established,

    reported, and maintained on Site

    .5 Monitoring reports are prepared and submitted in accordance with

    Section 01 33 00 .

    .6 The Environmental Manager shall have the following qualifications:

    1 A degree or diploma from a recognized university or college in a natural

    or physical science with specialization in fisheries biology, aquatic

    biology, ecology, or another related discipline, and

    2 Minimum of five (5) years related work experience, and

    3 Minimum o three (3) years experience in monitoring construction

    activities in and around fish habitat, and

    .4 The Contractor shall define, document and communicate roles,

    responsibilities and authorities in order to facilitate effective management

    of environmental aspects in the CECMP

    .7 The Contractor shall retain air, water, noise and vibration monitoring

    professionals to establish and conduct baseline and monitoring requirements,

    as well as reporting for construction noise and vibration in accordance with the

    applicable City construction noise by-laws and construction vibration by-laws.

    The noise monitoring professional must demonstrate that he/she has a current

    certificate of competency in environmental acoustics technology issued by an

    accredited program of an Ontario Community College, or other approved

    consulting agency, or is otherwise suitably qualified and acceptable to the

    Commission s Representative. The Contractor shall demonstrate that the air

    quality monitoring professional has a competency in air quality monitoring and

    reporting .

    .8 The Contractor shall retain a qualified avian biologist to assess the potential for

    and development o mitigation plan(s) if nesting birds are found on the Site(s) in

    accordance with the Migratory Bird Convention Act.

  • 8/9/2019 01 57 19 - Environmental Controls

    7/84

    Toronto Transit

    Commission

    CONTRACT A29-1

    Section 01 57 19

    ENVIRONMENTAL CONTROLS

    Page7

    .3 Communication including a Rapid Response Protocol as follows:

    1 Immediate environmental concerns with respect to construction activities o

    associated with Site activities are identified:

    1 The Contractor s Environmental Manager shall immediately report the

    incident directly to the Contractor and the Commission s Representative

    .2 The Commission s Representative shall immediately contact the relevan

    stakeholder agencies, per Section 5.35

    or

    the Spill Response

    Contingency Plan as applicable,

    in

    Section 18

    .3 The Contractor s Environmental Manager shall work with the Contracto

    to ensure the cause of the incident is quickly addressed and a plan is

    developed to prevent a re-occurrence (i.e. mitigative measure

    implemented). Mitigative measures shall include, but not be limited to

    the following:

    1 Changes to Work protocols that led to the incident.

    2 Further training of personnel.

    3 Implementation of additional engineering controls; and

    4 Increased frequency

    of

    monitoring and ongoing maintenance

    4

    The Contractor s Environmental Manager shall verify whether prope

    procedures had been followed prior to the incident.

    .5 The Contractor s Environmental Manager shall record the incident on an

    Ell attach a description of the mitigation measures program that will be

    implemented in response to the incident, and submit the l l and

    mitigative measures plan directly to the Commission s Representative

    .6 The Contractor s Environmental Manager shall also submit

    an

    Inciden

    Follow-up Summary report to the Commission s Representative, verifying

    that the proposed mitigation measures program was implemented

    successfully and noting the condition of the identified area o

    environmental concern. If the issue is not resolved in a reasonable period

    of time, per the mitigation measures program developed, the

    Commission s Representative shall take further action to ensure

    mitigation measures are implemented as required .

    .7 The Commission s Representative will liaise with affected stakeholde

    agencies throughout the incident resolution, as required, to ensure that al

    relevant mitigation measures requested by said agencies, to

    the

    greates

    extent practicable, are implemented .

    .2 The Contractor must ensure that brief daily discussions are held with its

    Environmental Manager to address any shortfalls identified during the

    implemented monitoring programs. A daily review of any identified potentia

    concerns will allow the implementation of mitigative measures before any

    negative environmental impacts result.

    3 To update the Commission s Representative

    of

    the ongoing status

    of

    the

    monitoring program on a regular frequency

    4

    In

    the event that a dust, noise, vibration or other exceedance is detected

    .5 To respond to complaints if they are received.

  • 8/9/2019 01 57 19 - Environmental Controls

    8/84

    Section

    1

    57 9

    ENVIRONMENTAL CONTROLS

    Page 8

    Toronto Transit Commission

    CONTRACT A29 1

    4 Establish and Implement Documentation and Procedures for the Control of

    Documents

    .5 Establish and implement Operational Controls .

    .4 Measuring, Analysis and Improvement:

    .1

    Evaluation of compliance

    .2 Continued improvement.

    .3 Nonconformity, corrective action(s)

    .4 Preventive action(s).

    5.5 The CECMP shall include a Site plan for each construction Site indicating locations

    of

    all

    construction facilities, wet and dry storage areas, trailers, environmental controls equipment

    and facilities, waste materials storage, erosion and sediment control areas, including wheel

    wash, mud mats and all other elements of the Site.

    5.6 The Contractor shall establish a co-ordinated monitoring and reporting program that

    provides daily, weekly and monthly reporting as required for the various disciplines defined

    in this Section. This program shall manage the individual inspection and reporting

    requirements of each component plan, together with electronic and paper monitoring

    reports. A copy of all reports shall be maintained on Site(s) and be maintained and

    available for immediate inspection by the Commission s Representative and any

    enforcement agency representative. Provide a copy of these reports to the Commission s

    Representative.

    5.7 The condition of all environmental controls shall be reported on the daily Environmental

    Inspection Log Ell) (Refer to Attachment 1) of each Site, the Weekly Summary Report

    (Refer to Attachment 2) and the Incident Follow-up Report (Refer to Attachment 3). A

    sample copy

    of

    each form is appended to this Section.

    5.8 Monitoring and reporting documentation shall also be maintained electronically and shall be

    provided to the Commission s Representative on CD/DVD in a format to be mutually agreed

    upon.

    5.9 The Contractor shall maintain a record of any enforcement actions (Refer to Attachment 3)

    that occur on-Site including, but not limited

    to

    any citation(s), requirements to correct and

    any follow-up reports from the enforcement agency. The Contractor shall report all

    enforcement actions immediately to the Commission s Representative and make available

    a copy of complaints and notices received from the enforcement agency. The Contractor

    shall make available any records

    of

    remedial action taken by the Contractor of any

    violations associated with all permits obtained by the Commission for this Work.

    5.10 The Contractor shall prepare all monitoring and implementation programs, schedules, site

    plans, photo logs and drawings of affected areas. Plan elements, baseline, trigger and

    alarm levels, and frequencies are described in subsequent Articles.

  • 8/9/2019 01 57 19 - Environmental Controls

    9/84

    Toronto Transit

    Commission

    CONTRACT A29-1

    Section

    01

    57

    9

    ENVIRONMENTAL

    CONTROLS

    Page9

    5.11

    1

    The Contractor shall develop and include in the CECMP and implement an Environmenta

    Awareness and Training Plan (EATP).

    The EATP will include the following training components:

    1 Decontamination Procedures

    .2 Materials Handling Procedures

    .3 Spill and Fire Response/Emergency and Response Protocols

    4 Discovery of Unexpected Site Conditions (i.e. dewatering, soil contaminations, etc.)

    .5 Erosion and Sediment Control Measure Awareness .

    .6 Dust Prevention and Control.

    .7 Noise Prevention Awareness .

    .8 Communications Protocols.

    5.12 The Contractor is responsible for administering the EATP to all on-Site personnel and mus

    ensure that Subcontractor(s), hired consultants and all other individuals in Project Work

    areas receive training prior to entering the Site. The EATP must provide

    for

    a once

    pe

    year update training for all personnel. All new personnel must be trained

    prior

    to entering

    the Site and receive up-date training annually thereafter.

    5.13 The Contractor shall submit five copies of the ETAP to the Commission s Representative

    prior to the initial training. The Contractor shall make any revisions requested by the

    Commission s Representative.

    5.14 The Contractors Communications Protocols shall reflect procedures set forth in the TYSSE

    Complaints Protocol as outlined in the Toronto-York Spadina Subway Extension

    Downsview Station to Steeles Avenue Environmental, Complaints Protocol, dated Februar

    2008 (Refer to Attachment 6).

    6 PRODUCTS AND EQUIPMENT

    6 1 The Contractor shall provide all noise and vibration, air quality, water quality, sampling and

    testing equipment, materials, and recording devices necessary to conduct all required

    monitoring, testing and reporting for the environmental monitoring for the duration o

    construction at each Site.

    6.2 The Contractor shall provide on Site all materials necessary to implement all environmenta

    controls, including contingency measures specified in the Contractor s Environmenta

    Controls and Methods Program.

    6.3 The Contractor shall obtain the services of off-Site testing laboratories and shall provide the

    necessary test results associated with the various monitoring plans.

    7 MONITORING/AUDITING

    BY

    COMMISSION S REPRESENTATIVE

    7 1 The Commission s Representative will monitor/audit Contractor compliance with al

    environmental requirements in accordance with Section

    01

    40 00.

  • 8/9/2019 01 57 19 - Environmental Controls

    10/84

    Section

    1

    57

    9

    ENVIRONMENTAL CONTROLS

    Page 10

    Toronto Transit Commission

    CONTRACT A29 1

    8 DUST AND AIR QUALITY CONTROL DURING DEMOLITION AND CONSTRUCTION

    8.1 The Contractor shall prepare and submit for approval a plan for dust and air quality

    monitoring. The plan shall include a Site plan showing:

    .1 The pre-construction and construction monitoring locations of sensitive receptors {e.g. in

    the public right-of-way adjacent or ajdacent to or across the street from each construction

    Site of this Contract) including: on the York University Campus - at mulitple locations within

    the Harry W. Arthur Common area at York University and including the Harry Sherman

    Crowe Co-op and based on the locations and extents of the construction area{ s )

    .2 The locations

    of

    construction Site{ s) sources of total dust, Total Suspended Particulates

    {TSP), Particulate Matter of 2.5 microns or smaller {PM

    2

    .

    5

      ,

    crystalline silica and other

    contaminants as applicable within the construction Sites .

    .3 The locations of major excavations and soil stock piles

    .4 Location

    of

    on-Site roads to

    be

    utilized during construction. Indicate

    if

    roads are to be

    paved

    or

    unpaved .

    .5 Location

    of

    Site entrances and exits, including location of wheel wash facilities .

    .6 Location of truck staging area{s)

    .7 Location

    of

    areas of special concern (on-Site and off-Site) such as fresh air intakes, air

    conditioners and windows of adjacent buildings and residences.

    8.2 A description

    of

    the monitoring

    Jocation{s ,

    monitoring methods and equipment, approach,

    provision of power to the monitors, sample handling procedures, and data collection

    frequency for Total Suspended Particulates (TSP) and Particulate Matter

    Jess

    than 2.5

    microns in diameter {PM

    2

     

    5

      , crystalline silica, other contaminants as applicable to the

    demolition and any materials stored on-Site.

    8.3 The results of the monitoring shall be compared to relevant guidelines including, but not

    limited

    to,

    their respective standards, guidelines, and time weighted average exposure

    value {TWAEV) as indicated in 0. Reg.

    419/05

    Schedule 3 and OHSA Regulation 833, or

    as directed by the Commission s Representative.

    8.4 A listing of standard operating procedures {SOPs) for standard techniques

    in

    accordance

    with best practices for the reduction

    of

    air emission from construction and demolition

    activities within the construction industry. One {1) SOP is required for each mitigation

    technique and shall be included as an appendix to the plan.

    8.5 A preliminary schedule for pre-construction, construction, and post-construction monitoring,

    including expected work day durations and identification of major construction activities that

    are expected to generate airborne contaminants.

  • 8/9/2019 01 57 19 - Environmental Controls

    11/84

    Toronto

    Transit Commission

    CONTRACT A29-1

    Section

    01 57

    ENVIRONMENTAL CONTROLS

    Page

    1

    8.6 During progress of the Work, implement the approved plan, monitoring, reporting, complain

    response and contingency program to the satisfaction of the Commission s Representative.

    8

    7 The Contractor shall provide/complete air monitoring of crystalline sil ica, airborn

    particulate and weather during pre-construction and construction.

    8.8 A minimum of

    one

    (1) air monitoring locations shall be utilized at each discrete area

    of

    th

    overall construction Site.

    8.9 A minimum of two (2) full weeks of pre-construction monitoring shall be completed.

    8.10 Air monitoring shall occur during construction and shall match the Contractor s Wor

    schedule in terms of days per week and hours per day.

    8 11 Continuous sampling methods shall be utilized for monitoring TSP, PM10 and PM2.5

    Acceptable continuous monitoring methods include the following:

    1

    Tapered element oscillating microbalance (TEOM)

    .2 Portable laser photometers with internal data loggers, with weatherproof environmenta

    enclosure

    .3 Portable aerosol monitors with detectors using Turnkey laser nephelometer

    .4

    Portable programmable mass flow controlled

    PM

    reference samplers

    .5 Others as approved by the Commission s Representative.

    8.12 Acceptable manufacturers for the above instrumentation are:

    1

    TSI.

    2 BGI.

    .3 Thermo Scientific

    .4 Met One Instruments

    .5 Others as approved by the Commission s Representative.

    8.13 Continuous monitors shall be set up to alert the Environmental Manager in

    the

    event tha

    any

    of

    the limits are exceeded. On the detection

    of

    an exceedance, the Commission

    Representative shall be notified verbally as soon as possible and followed by notification in

    writing within two (2) days, including the time of occurrence, duration

    of

    the exceedance

    magnitude

    of

    the exceedance, mitigation measures taken, wind speed and wind direction a

    the time of the exceedance. To start, the instantaneous alert level shall be equal to th

    twenty-four (24) averaging time values. After two (2) months of construction, the Contracto

    may propose

    to

    reduce the instantaneous alert level to a value higher than the twenty-fou

    (24) hour averaging time value based on the data collected.

  • 8/9/2019 01 57 19 - Environmental Controls

    12/84

    Section 1 57 9

    ENVIRONMENTAL CONTROLS

    Page 2

    Toronto Transit Commission

    CONTRACT A29 1

    8.14 Data from the continuous monitors shall

    be

    logged with a time resolution of minimum one

    {1) minute. Data shall

    be

    maintained on electronic storage media on Site throughout the

    Contract. An electronic copy of all data shall be provided to the Commission's

    Representative

    in

    a format mutually agreed upon between the Contractor and the

    Commission's Representative.

    8.15 Continuous monitors must

    be

    active and collecting valid data for 95 of the Contractor's

    working hours {on a monthly basis). Contractor shall arrange

    for

    adequate provision of

    spares, provision of reliable power sources, and scheduling of required calibration and

    maintenance to achieve this requirement.

    8.16 For the monitoring of crystalline silica, sampling shall be carried out using a combination of

    a cyclone and pump assembly. Each sample length {duration) shall be a minimum of eight

    {8) hours and the sampling shall, at a minimum, be carried out on a one-in-six

    {1

    in 6 day

    sample regime. If the Contractor is working more than eight {8) hours during the sampling

    day, the number of samples taken that day shall be adjusted to ensure that sampling results

    are gathered for the entire working day. The intent

    of

    the one-in-six {1 in 6) day rotation is

    to gather information over the construction period over different days

    of

    the week.

    8.17 The Contractor shall provide notification to the Commission's Representative verbally as

    soon as possible and followed

    by

    notification

    in

    writing within two {2) days of receiving the

    non-continuous results from the laboratory, including the time of occurrence, magnitude of

    the exceedance, mitigation measures taken.

    8.18 The Contractor shall control dust and debris through the use of standard techniques and in

    accordance with best practices for the reduction of air emission from construction and

    demolition activities within the Work Site which include, but are not limited to, the following:

    1 Cover or wet down dry materials to prevent blowing dust and debris

    .2 Prevent dust from blowing across the Site(s) and from leaving the Site(s), in particular by

    frequently wetting paved and unpaved temporary roads and excavated areas .

    .3 Comply with Provincial regulations regarding the minimization

    of

    dust and airborne

    pollution .

    .4 Wash down the streets within the Work Site(s) on a daily basis,

    or

    more frequently as

    required .

    .5 Securely cover excavated material being removed from the Site(s) and all fill materials

    being delivered to the Site(s) to prevent blowing of dust and suspended particulate matter

    into the streets and haul routes as required

    in

    Section 02

    6 1

    00 - Impacted Soils Handling

    .6 Application of calcium chloride shall be kept to minimum and shall be restricted to vehicle

    right-of-way. In close proximity to watercourses, frequent applications of water shall be the

    preferred method. Obtain the Commission's Representative's approval before chemicals

    for dust control are used.

  • 8/9/2019 01 57 19 - Environmental Controls

    13/84

    Toronto Transit Commission

    CONTRACT A29-1

    Section

    01 57 19

    ENVIRONMENTAL CONTROLS

    Page

    13

    7

    8.19

    1

    2

    3

    8.20

    .1

    Provide wheel wash facilities at all Site exits as shown on erosion and sediment contro

    Drawings.

    Emissions from Construction Equipment:

    The Contractor shall establish truck-staging zones for vehicles waiting to load or unload

    material at the Work Site. Such zones shall be located where diesel emissions have the

    least impact on abutting properties and the general public.

    Idling time for delivery trucks, dump trucks and all other internal combustion powered

    equipment shall be reduced as appropriate.

    The Contractor shall ensure that internal combustion powered engines are located away

    from fresh air intakes, air conditioners and windows.

    Reporting:

    The Contractor shall provide the Commission s Representative with a monthly summary ai

    quality report. The report shall include the following:

    .1 For the continuous monitors: A summary of the statistics (mean, median, maximum

    minimum, 75, 80, 85, 90 95, 99th percentiles) for the period, listing of exceedances

    percentage of time exceeding, for all averaging times

    .2 Continuous monitor uptime percentage as a percentage of the Contractor s working

    hours

    .3 Results from the non-continuous samplers

    .4 Comparison of the monitored airborne contaminants to their respective regulator

    limits and time weighted average exposure values (TWAEV) as indicated in OHSA

    Regulation 833. The limits below are based on corresponding standards, criteria, and

    guidelines and may be updated from time to time,

    or

    as directed by the Commission s

    Representative.

    Contaminant Source Averaging Time Value

    (pglm3)

    PM-TSP

    0

    Reg. 419/05, Schedule 3 24 hours

    120

    PM2.5 Canada Wide Standard 24 hours

    30

    PM10 MOE Interim Reference Level 24 hours

    50

    Crystalline Silica OHSA Regulation 833 Time-Weighted Average

    100

    Limit

    (TWA)-

    8 hours

    Crystalline Silica MOE Guideline

    hour

    15

    Crystalline Silica MOE Guideline 24 hours

    5

    .5 Copies of all written notices of exceedances submitted during the month

    .6 Copies of all written complaint reports received during the month

    .7 Summary of actions taken to address any exceedances and complaints (if any) and

    their current status

    .8 Summary of any changes and modifications to the Air Quality and Dust Controls and

    Methods component of the CECMP

    .9 Statement of compliance with the measures to control dust and debris through the

    use of standard techniques and

    in

    accordance with best practices

    . 10 Statement

    of

    compliance with the measures to control emissions

    from

    constructio

    equipment.

  • 8/9/2019 01 57 19 - Environmental Controls

    14/84

    Section

    01 57 19

    ENVIRONMENTAL CONTROLS

    Page 14

    Toronto

    Transit ommission

    CONTRACT A29-1

    .2 The Contractor shall submit the monthly summary report in draft form to the Commission's

    Representative within three (3) weeks

    of

    the end of each month

    .3 The Contractor shall submit five (5) copies

    of

    each final monthly summary report to the

    Commission's Representative within one ( 1) week

    of

    receiving the Commission's

    Representative review

    of

    the draft report.

    8.21 Final Close-Out Report:

    1 Provide five (5) copies of a final close out report to the Commission's Representative

    summarizing the dust control Work of all construction sites and an electronic copy of all

    records made during the Work.

    9 NOISE AND VIBRATION MONITORING AND CONTROL

    9 1

    The maximum allowable exposure to noise for a Commission employee (in accordance with

    Ontario Occupational Health and Safety Act, Ont. Reg. 851) is:

    Sound Level in Decibels Duration Allowed in Hours per day

    85 8

    86 6

    88

    4

    89

    3

    91

    2

    92

    1 5

    94 1

    95

    0 75

    97

    0 5

    100 0 25

    103

    0 12

    Over103

    No exposure

    9.2 The Contractor shall comply with all applicable noise and vibration by-laws, preparing all

    required baseline monitoring and reporting. The Contractor shall prepare this information in

    a Noise and Vibration Monitoring Plan and provide five (5) copies

    of

    the plan, and

    subsequent reporting results to the Commission's Representative monthly throughout the

    construction period.

    9.3 The Contractor shall be responsible for the cost

    of

    monitoring the noise and vibration on

    Site and at sensitive receptors off Site.

    9.4 In addition to requirements

    of

    the noise by-laws, the Contractor shall take special

    precautions and apply noise abatement measures to reduce public exposure to noise.

    These shall be identified in the Noise and Vibration Plan.

    9.5 Shields

    or

    other physical barriers to restrict the transmission of noise: Barriers should have

    sufficient mass such that noise passing through the barrier does not affect the net sound

    level by more than 1dB at the receiver.

    9.6 Pile drivers used for construction at the Station areas shall be of the quiet hydraulic

    vibratory type, rather than the noisier drop weight type, unless such equipment is required

    for other identified reasons by the Commission's Representative.

  • 8/9/2019 01 57 19 - Environmental Controls

    15/84

    Toronto Transit Commission

    CONTRACT A29 1

    Section

    1

    57 19

    ENVIRONMENTAL CONTROLS

    Page 15

    9.7 Soundproof housings

    and

    enclosures for noise producing machinery, such as compressors,

    pumps, motors and generators. All equipment shall meet NPC115 guidelines t a

    minimum.

    9.8 Provide efficient intake

    and

    exhaust mufflers on internal combustion engines.

    9.9 Provide efficient intake and exhaust silencers on air equipment.

    9.10 Provide sound deadening lining material

    on

    hoppers and storage bins.

    9.11 Conduct truck loading, unloading

    and

    hauling operations so that noise

    is

    kept to a

    minimum.

    9.12

    9.13

    9.14

    9.15

    9.16

    1

    All vehicles and equipment employed continuously on any Site for extended periods (in

    excess of two (2) days) shall be fitted with sound reducing, broadband, multi-frequency

    back-up (reversing) alarms, such as bbs-tek heavy duty model BBS-107, as distributed by

    Walker Aggregates

    Inc.

    (Tel: 905-680-3747),

    or

    similar and approved. All such vehicles wil

    be subject to inspection by the Environmental Manager for compliance with this

    requirement. Any original factory installed vehicle and equipment back-up alarm units, no

    complying with the sound level of the BBS-107 unit will not be permitted on such vehicles

    and the Commission s Representative will have the right to order that they be removed and

    replaced with the specified units.

    Use electric, rather than internal combustion engine power, on chain saws, hoisting

    equipment

    in

    fixed locations and other equipment, where electric power is available.

    Position stationary noise producing equipment at maximum distance from public areas.

    Provide any other effective noise control measure proposed by the Contractor and

    approved by the Commission s Representative.

    The Contractor shall design and establish a Noise and Vibration Monitoring Program within

    the CECMP to document existing noise and vibration levels at each Site and t sensitive

    receptors e.g. adjacent or across the street from each construction Site of this Contrac

    including, but not limited to,

    on

    the York University Campus - at mulitple locations within the

    Commons area at York University and including the Harry Sherman Crowe Co-op and

    based on the locations and extents of the construction area( s . Notwithstanding the above

    work shall be carried out as required by the City of Toronto noise and vibration construction

    by-laws, to provide ongoing noise monitoring and reporting during construction that can be

    used

    to

    substantiate the effects on nearby sensitive receptors. This Work may

    be

    the same

    as that done to meet the noise and vibration requirements of the applicable City

    construction by-laws, but must at a minimum provide:

    A map of the location(s) of and list of adjacent and nearby sensitive receptor(s) fo

    pre-condition monitoring (in the public right-of-way as described herein), that is likely to

    experience noise and vibration effects from the construction activities. Noise nd vibration

    levels for nearby sensitive properties shall

    be

    measured prior to the commencement

    o

    construction.

  • 8/9/2019 01 57 19 - Environmental Controls

    16/84

  • 8/9/2019 01 57 19 - Environmental Controls

    17/84

    Toronto Transit Commission

    CONTRACT A29 1

    Section 1 57 9

    ENVIRONMENTAL CONTROLS

    Page 7

    .3 Additional locations for continuous noise monitoring may be added as required .

    4 Continuous noise monitoring shall be measured and reported in one (1) hour intervals ove

    twenty-four {24) hour periods for the duration of construction at each Site

    .5 Continuous noise measurements during construction activity shall be reported to the

    Commission s Representative in weekly monitoring reports (Refer to Attachment 4)

    Reports shall include noise level data (Leq, L90 and L 10) in A-weighted values dBA) in on

    (1) hour intervals; with associated weather conditions (wind speed, temperature, conditions

    etc.) to be provided for each one (1) hour interval. Construction activities shall also be

    documented for each one ( 1) hour interval to be correlated with the noise level data fo

    reference purposes.

    9.20 Noise Data Analysis:

    .1 Noise data measured during inclement weather conditions shall be discounted from th

    data set. Inclement weather conditions shall include conditions where the wind

    is

    in exces

    of 20 km/hr and any type of precipitation .

    .2 Hourly sound data shall be presented for each for each

    of

    the A-weighted values, Leq, L90

    and L10. Sound levels shall be sampled at a minimum rate

    of

    1/sec. The meter shall be

    set to fast response .

    .3 Submit a graph depicting the hourly A-weighted Leq, L90 and L 10 values and wind speed

    against time.

    9.21 Long-Term Vibration Monitoring:

    .1 A vibration monitor shall be located at each construction Site to continuously monitor th

    vibration level from construction .

    .2 The closest sensitive receptor to the construction activity may be used as a location fo

    continuous monitoring

    .3 Additional locations for continuous vibration monitoring may be added as required

    4 Continuous vibration monitoring shall be measured and exceedences above the critica

    levels provided in the applicable City constriction bylaws logged and reported for the

    duration of construction at each Site

    .5 Commission s Representative shall be provided weekly monitoring reports (Refer t

    Attachment

    5 .

    Reports shall include vibration level data referenced in

    Peak

    Particle

    Velocity (mm/s) and associated frequency (5-100 Hz) specifically noting exceedance

    above the critical levels provided in the applicable City construction bylaws. Construction

    activities shall also be documented for each bylaw exceedance to be correlated with the

    vibration level data for reference purposes.

  • 8/9/2019 01 57 19 - Environmental Controls

    18/84

    Section 01 57

    19

    ENVIRONMENTAL CONTROLS

    Page 18

    Toronto Transit Commission

    CONTRACT

    A29-1

    9.22 Vibration Data Analysis. Submit a graph depicting the PPV against time for all logged

    events exceeding the criteria set out in the applicable City Construction By-law.

    9.23 Documentation of all noise and vibration alerts shall be recorded and provided within two

    (2) business days to the Commission's Representative, together with the corrective actions

    taken.

    9.24 The Contractor shall provide weekly monitoring reports (Refer to Attachment 5 for sample

    vibration monitoring forms) to the Commission's Representative prior to each progress

    meeting for the duration of the Work. Any alerts and corrective actions shall be reported on

    the daily Ell (Refer to Attachment 1) and on the Weekly Summary Form. Records of the

    monitoring program output shall be maintained

    on

    Site and provided in a weekly summary

    to the Commission's Representative on an

    Ell

    form with monitoring documentation

    provided in summary form both on paper and in electronic format.

    9.25 Noise and vibration monitoring reports shall provide the statistical noise level data

    described in paragraphs 9.20,

    and 9 21

    above. The full measurement data in one

    1)

    hour

    intervals, relevant weather data (precipitation and wind speed), summary charts and

    documentation regarding the specific location of monitoring are to be provided in an

    appendix to the monitoring reports.

    9.26 Provide five (5) copies of a final close-out report to the Commission's Representative

    summarizing the then current status of all indicators listed in paragraphs 9.20 and 9 21

    above and an electronic copy of

    all

    records made during the construction period.

    9.27 Should the Commission's Representative and/or the Contractor receive any complaint from

    the public, the Contractor shall verify that the general noise control measures agreed to

    are in effect. The Contractor shall investigate any noise concerns and shall report to the

    Commission's Representative within one ( 1) calendar day of the complaint on what actions

    have been taken to mitigate the issue. Complaints shall also

    be

    reported

    on

    the daily

    Ell

    form and actions to abate, mitigate or confirm no exceedance shall be recorded on the daily

    Ell and Weekly Summary forms

    9.28 The Noise and Vibration Monitoring Plan shall identify the Contractor's procedures to

    respond to public complaints in accordance with the projects-approved complaints protocols

    as referenced in the project's York Complaints Protocol, June 2010 and the Contractor's

    Rapid Response Protocol. Should the Commission and/or the Contractor receive any

    complaint from the public, the Contractor shall verify that noise limits of NPC115) have not

    been exceeded, and if they have, take immediate steps to ensure compliance.

    9.29 Documentation requirements for incident or complaint reports shall be prepared and

    forwarded immediately to the Commission's Representative and not later than within two {2)

    business days after the incident, or complaint is received. This shall be completed in

    accordance with the York Complaints Protocol (Refer to Attachment 6) for the York Region

    portions of the project as set forth in the CECMP's Rapid Response Protocol. Copies of

    plans, monitoring reports and incident or complaint reports shall be delivered to the

    Commission's Representative in accordance with Section 01 33 00.

  • 8/9/2019 01 57 19 - Environmental Controls

    19/84

    Toronto Transit Commission

    CONTRACT A29 1

    Section 1 57 9

    ENVIRONMENTAL CONTROLS

    Page 1

    9.30 If the general noise control measures are complied with, but the public still complain abou

    noise, the Commission's Representative will require the Contractor to investigate, and

    subject to the results of the field investigation, apply alternative noise control measures

    where these are reasonably available.

    9 31

    In selecting the appropriate alternative construction noise control and mitigation measures

    the Commission's Representative and the Contractor will give consideration to the

    technical, administrative, and economic feasibility

    of

    the various alternatives.

    9.32 Where timing constraints

    or

    any other provisions of the municipal by-laws

    may

    cause

    hardship to the Commission's Representative and the Contractor,

    an

    explanation of this wi

    be outlined in a submission to the local municipality and the Contractor shall obtain an

    exemption from such by-law directly from the local municipality in accordance with Section

    01 14 00

    10

    EROSION AND SEDIMENT CONTROL PLAN

    10 1 Erosion and sediment controls (ESC) at the York University Site are to be installed at the

    site by the A29-2 Contractor and then turned over to the Contractor. Upon mobilization

    Contractor will inspect and assume responsibility of these installed and/or remaining ESC

    measures for completion of the station site. Hand over will

    be

    supervised by the

    Commission's Representative.

    10.2 Mitigation measures identified in the Contract Documents listed below are in accordance

    with the OPSS, OPSD, and the Greater Golden Horseshoe Area Conservation Authorities

    (GGHACA) Erosion

    and

    Sedimentation Guideline for Urban Construction (December 2006)

    10.3 The purpose of the Erosion and Sediment Control Plan is to prevent sediment laden

    stormwater from entering either temporary or permanent storm drainage systems during

    construction by the following:

    1 Minimize the duration and extent of soil exposure .

    .2 Manage surface water to prevent contact with exposed soil surfaces

    .3 Implement erosion and sedimentation control measures on-Site to prevent sedimen

    migration off-Site

    4 Erosion and Sediment Control Plan measures shall be in place before construction

    commences .

    .5 Baseline ESC control monitoring results shall be collected within one 1) week

    o

    installation, documented and provided to the Commission's Representative on the daily El

    (Refer to Attachment 1) and Weekly Summary Forms (Refer to Attachment 2) for review

    .6 A copy of all records shall

    be

    maintained on Site for inspection by regulators and the

    Commission's Representative; a weekly summary shall be provided to the Commission's

    Representative (paper and electronic versions); Ells shall be provided daily, together with

    the weekly summary and for each incident/event that triggers an inspection.

  • 8/9/2019 01 57 19 - Environmental Controls

    20/84

    .

    Section

    01 5719

    ENVIRONMENTAL CONTROLS

    Page20

    Toronto

    Transit

    Commission

    CONTRACT A29-1

    10.4

    10.5

    10.6

    10.7

    7

    1

    . 1

    Provide five (5) copies of a final close-out report that coalesces individual Site reports to the

    Commission's Representative summarizing the then current status of all

    measures/indicators listed and used in paragraph 10.4 below and an electronic copy

    of

    all

    records made during the construction period.

    The Contractor shall design and establish a plan to address erosion and sediment control

    and monitoring on Site and on adjacent streets, for each construction Site associated with

    this Contract that reflects the Contractor's means and methods of construction. These shall

    be

    consistent with and based on the details shown on the on the following Drawings:

    Contract A29-1: Drawing No. A29-1 C5102 and C5504 Erosion and Sediment Control plan

    and details

    Where changes in construction staging, methods and/or the arrangement

    of

    construction

    Site(s) occur that change or modify the Contract details, a revised ESC Plan shall be

    prepared and submitted by the Contractor to the Commission's Representative

    for

    review

    prior to implementation.

    The ESC Plan shall include an inspection schedule including times, areas and personnel

    responsible. Reports on the inspections shall be included on the daily and weekly El l and

    Summary forms and provided to the Commission's Representative for review. The ESC

    Plan shall include from among the following ESC control measures and shall identify the

    following monitoring trigger levels and alert levels which identify when corrective action

    must be taken by the Contractor, as well as the corrective action to be taken under each

    condition:

    Measures/Indicators

    Monitoring

    fTrigger Level

    Action Level

    Heavv Dutv Silt Fence 30 full 50 full

    Jersey Barrier with Sil t Fence 30 full 50 full

    Staked Sediment Control Log 30

    of

    height

    50

    of

    height

    Truck Wash

    As specified by Manufacturer's

    As specified by Manufacturer's

    0

    Mmanual O Mmanual

    Mud Mat 50 coverage 75 coverage

    Concrete Wash-out Station

    30 full

    50 full

    Inlet Sediment Control Device

    15 full

    30 full

    Sediment Trap

    15 full

    30 full

    Temporary Rock Check

    Dam

    15 full

    30 full

    Sediment Control Pond

    15 full

    30 full

    Erosion Control Blanket 85 coverage

    <

    70 coverage

    Mulch

    85 o v e r ~ ~ e

    < 70 coveraQe

    Hydroseed 85 coverage

    < 70 coverage

    Sediment and erosion control measures shall be inspected and monitored

    by

    the

    Contractor:

    On a weekly basis .

    .2 After large rainfall events (>20 mm in twenty-four (24) hours)

    .3 After significant snowmelt events

    .4 Daily during extended rain or snowmelt periods.

  • 8/9/2019 01 57 19 - Environmental Controls

    21/84

    Toronto Transit Commission

    CONTRACT A29-1

    Section 1

    57 1

    ENVIRONMENTAL CONTROLS

    Page21

    5

    6

    10 8

    10 9

    10 10

    11

    11 1

    11 2

    1

    2

    3

    During inactive construction periods, where the Site is left inactive for thirty {30 days o

    longer, a monthly inspection shall be conducted and reported after to the Commission

    Representative to ensure that these measures are maintained in proper working order unt

    all areas are fully stabilized.

    Provide daily reports once a week to the Commission s Representative on l l form

    accompanied by required submittal documents.

    All damaged erosion and sediment control measures shall be repaired or replaced within

    forty-eight (48) hours of the inspection to the satisfaction of the Commission

    Representative. Repair and replacement actions and materials will be reported on Ell

    and Weekly Summary forms. Repair materials must be maintained on site

    for

    all installed

    ESC measures.

    The ESC plan shall also include provisions for monitoring and maintenance to ensure th

    ESC measures at each Site are functioning within their established discharge quality and

    quantity limits.

    Erosion and sediment controls shall be removed or retained at the end of the Contract a

    directed by the Commission s Representative. All remaining control materials shall be lef

    in good working order and all elements that will be dismantled shall

    be

    removed from the

    Site. Those ESC facilities/elements to be retained will be documented in the final closeou

    report and submitted

    to

    the Commission s Representative.

    SURFACE WATER MANAGEMENT PLAN

    The Contractor shall design and implement a Surface Water Management

    Plan

    (SWMP) a

    part of the CECMP for each Site and submit to the Commission s Representative fo

    review.

    The Contractor shall define in the SWMP procedures, monitoring and reporting to

    implement mitigation measures that ensure following surface water managemen

    objectives:

    Protection of local vegetation and surrounding properties from flooding and/or so

    saturation (the frequent or prolonged inundation of soil).

    Maintained proper Site drainage

    Protection of excavations and trenches against flooding and damage

  • 8/9/2019 01 57 19 - Environmental Controls

    22/84

    Section 1 57 19

    ENVIRONMENTAL CONTROLS

    Page

    Toronto Transit Commission

    CONTRACT A29 1

    11.3 Table 1 reflects the general elements of the SWMP.

    Table 1

    Monitoring

    of

    MonitorinQ Frequeno

    Parameter

    Method

    Baseline 1 During Contract

    Element

    locations

    Construction Completion

    Surface Water

    Total At sources

    Grab samples none In accordance none

    Quality

    suspended across the

    with analytic with the

    solids TSS)

    construction testing results discharge

    site s).

    permit and

    after every

    20 mm rain

    event or major

    snowfall.

    Dissolved

    At sources Field analysed

    none

    In accordance none

    Oxygen DO),

    across the

    with portable

    with the

    pH, construction

    meter

    discharge

    conductivity site s).

    permit and

    after every

    20 mm rain

    event or major

    snowfall.

    Surface Water

    Temperature

    At

    sources

    Continuous none Continuous none

    Temperature

    across the

    logger, field downloaded

    construction analyzed with bi-weekly.

    site s)

    if

    portable meter

    discharge is

    to the storm

    sewers.

    Water Quantity

    Calculated At each

    Continuous flow none Continuous, none

    Sewer input for discharge

    metre downloaded

    storm or

    location of bi-weekly,

    sanitary construction

    reported

    site s).

    monthly.

    11.4 The SWMP shall:

    1 Address the means and methods to control Site flooding and soil saturation at all

    construction Sites

    .2 Shall be executed on a Site by Site basis by the Contractor and reported

    in

    the daily EIL s),

    the Weekly Summary form and on the incident follow-up form for each Site

    .3 Shall describe and implement a program that establishes ongoing monitoring,

    implementation

    of

    control methods, establishes discharge trigger and alarm levels and lists

    pro-active mitigation to

    be

    implemented on site

    in

    accordance with Table 2 below

    .4 The Surface Water Management Plan shall include monitoring, control methods, trigger and

    alarm levels and pro-active mitigation

    in

    accordance with Table 2 and as appropriate to

    each construction Site and the activities therein, as well as appropriate to the potential for

    flooding

    at

    each construction Site. These methods may include:

    1 Frequent on-Site daily visual and odour observations

    of

    areas

    of

    collected surface

    water for spills and high turbidity levels.

  • 8/9/2019 01 57 19 - Environmental Controls

    23/84

    Toronto Transit

    Commission

    CONTRACT A29-1

    Section 01

    57

    1

    ENVIRONMENTAL

    CONTROLS

    Page

    23

    Table 2

    -

    1

    Baseline:

    No

    on

    site

    flooding

    SurfaceWater Ri.moft'

    Management

    (

    Monitor:

    surf

    ace

    water runoff

    for

    spills

    and

    turbidity,.met

    eo ro logical co nd

    it ons, o n site

    flooding

    and

    the surf

    ace

    water runoff collection system(s)

    I

    1 1 1 1 1

    Trigger:

    Trigger: Observed

    Alarm:

    2dmrnl24 hr rain

    Baseline:

    Alarm: Spill

    or

    areas

    of pooled

    On-site

    fall event (pre ,

    No

    evidence

    deleterious substance

    surface water or

    flooding

    during

    and

    post

    of spill

    is

    presentwithin

    aturated soils

    event) , thav.

    surface w ~ e r runoff

    I

    event

    1 l

    Action: Employ

    r

    Action: Inspect

    '

    Action: Employ Spill

    Contingency .Plan for

    surface drainage

    Canting encyPian

    Severe

    Weather

    and

    collection system(s)

    measures

    inspect surface water

    prior to, during and

    drainage system(s),

    postrain event

    to

    increase

    monitoring

    ensure

    proper

    frequencl

    function,

    ensure

    filter

    /settling components

    '

    are

    in good function to

    Action:

    I+

    reduce

    turbidity levels

    Implement

    Action:

    Inspect surface '

    prior

    to

    entry into

    the

    proactive

    Action:Take

    all

    storm sewer, ensure

    mitigative

    '

    water

    drainage

    system(s), take all

    necessary actions to

    sediment and erosion

    measures for

    ensure surf

    ace

    water

    controls

    are in

    good

    spills

    necessary

    steps to

    drainage

    system(s)

    is

    '

    function

    1

    nsure·

    the surface water

    runoff

    drainage

    system s

    functioning properly

    functioning property,

    I

    ncrease

    monitoring

    frequency

    .2

    Frequent daily visual observations for flooding

    or

    areas of surface

    water

    run-o

    collection on Site .

    .3 Frequent daily inspection of the surface water drainage collection system(s) to ensur

    proper maintenance and function as provided in the design specifications .

    4

    Daily monitoring

    of

    Environment Canada weather forecast to anticipate

    and

    plan

    fo

    rain and thaw events

    .5 Identify personnel by name, responsible for ensuring that the work Site (s) shall b

    maintained at all times, such that materials are contained during regularly foreseeabl

    weather conditions. Additional protocols must be identified for implementation if greate

    than a one-in ten (1 in 10)

    or

    one-in-one hundred years storm is forecasted .

    .6 Shall cause to be prepared and filed copies

    of

    all records which will be maintained

    at

    eac

    Site's construction office for inspection by regulators and the Commission's Representative

    including the daily Ells, the Weekly Summary Forms and records

    of

    each incident or even

    that triggers

    an

    inspection.

  • 8/9/2019 01 57 19 - Environmental Controls

    24/84

    Section 1

    57 9

    ENVIRONMENTAL CONTROLS

    Page24

    Toronto Transit Commission

    CONTRACT A29 1

    .7 Shall cause to report any exceedance of MOE water quality standards/City of Toronto

    discharge standards to the Commission s Representative and when required to the MOE.

    .8 Describe and cause to be implemented a program whereby site surface water wil l be

    sampled, tested

    and

    monitored for water quality including total oil and grease, Total

    Suspended Solids (TSS), general chemistry and total metals (e.g. copper, iron, zinc, and

    boron). Samples will be taken consistently from established post treatment discharge

    locations as approved in the Contractor obtained City o f Toronto s discharge permit (either

    storm or sanitary sewer). monitoring Sites at the same time in-situ (field) water quality

    measurements are taken. TSS may not exceed 5 ppm .

    .9 All measurements, as well as the date and time of sample collection are to be recorded and

    submitted by the Contractor to the Commission s Representative with corresponding

    analytical laboratory reports including original signed test results, four additional copies and

    an electronic version .

    .10 Specify that the Contractor must submit all laboratory results to the Commission s

    Representative within twenty-four (24) hours of receipt. An original signed laboratory result

    shall be provided. Laboratory results may be appended to the Ells and Weekly Summary

    Reports

    . Shall include a severe weather element that identifies all appropriate precautions to be

    taken by the Contractor to ensure that, in the event

    of

    severe weather, the integrity

    of

    each

    Site(s) and the safety of the workers will be maintained .

    .12 The SWMP shall identify procedures to

    be

    followed to implement the following surface

    water run-off action plan including the listed trigger and alarm levels shown in Table 2

    above.

    11.5 Baseline stormwater discharge monitoring results shall

    be

    compiled into a report and five

    (5) paper copies and a PDF electronic copy shall be provided to the Commission s

    Representative for review within thirty (30) days of Notice to Proceed. The Contractor

    is

    provided the monitoring reports from design phase work (Refer to Attachment 6).

    Contractor shall provide monthly reports throughout the duration of the Contract.

    11.6 Final stormwater discharge monitoring results shall be compiled into a report and five (5)

    paper copies and a .pdf format electronic copy shall be provided to the Commission s

    Representative. The report shall summarize the results throughout construction and a final

    set

    of

    results for the Site shall be submitted prior to final payment.

    11.7 The Surface Water Management Plan shall implement and be consistent and compatible

    with the surface water handling requirements specified in Drainage of Excavated Areas of

    Section

    3

    23 19.

    11.8 The Contractor shall maintain all components of the surface water management system in

    good condition and ensure that all sediment and erosion control measures are functioning

    as designed. Replacement and repair of all facilities must

    be

    made no longer than 4 hours

    after identification of failure or shortfall.

  • 8/9/2019 01 57 19 - Environmental Controls

    25/84

    Toronto Transit Commission

    CONTRACT A29-1

    Section 01 57 19

    ENVIRONMENTAL CONTROLS

    Page 25

    11.9 The SWMP shall identify those responsible for ensuring that Work Sites shall be maintained

    at all times, such that materials are contained during regularly foreseeable weather

    conditions. Additional protocols must be identified for implementation i f greater than one-in

    ten

    1

    in 10) or one-in-one-hundred 1 in 100) years storms are forecast.

    12 TERRESTRIAL HABITAT MONITORING PROGRAM

    12.1 The Contractor shall define a Terrestrial Habitat monitoring program as

    part

    of the

    Comprehensive Controls and Methods Plan. The Terrestrial Habitat Monitoring Program

    (THMP) shall include:

    .1 Tree protection and monitoring in accordance with the local by-laws

    .2 Vegetation protection in accordance with Ontario Ministry

    of

    Natural Resource s (MNR

    provisions for the Species at Risk Act (SARA) listed species as applicable

    .3 Wildlife protection

    in

    accordance with MBCA (Migratory Bird Convention Act)

    .4 Reporting by the Environmental Manager in accordance with the reporting format as

    specified herein .

    .5 The Terrestrial Habitat Monitoring plan shall include the following baseline, threshold and

    remediation levels:

    Parameter Baseline

    Threshold

    Remediation

    Terrestrial Health

    Precondition Survey

    Deficiencies

    in tree

    Repair or replace

    protection materials

    immediately

    Preconstruction Nests (tree or ground)

    Bird Nests

    Survey

    located within Immediate Repair

    construction site

    Tree Protection

    Preconstruction Damage to or Failure

    Immediate Repair

    Survey

    of protection

    12.2 Establish tree protection plan(s) to implement City By-laws at all construction

    Sites

    . 1 The Contractor shall establish a tree protection plan in accordance with Section 3 01

    91

    .

    .2 Provide monitoring by a certified arborist twice (2) annually during the growing seasons and

    periodically year-round for the duration of dewatering and recovery to ensure that they are

    functioning as designed .

    .3 Address methods to correct deficiencies

    .4 Report and repair deficiencies within twenty-four (24) hours of identification.

  • 8/9/2019 01 57 19 - Environmental Controls

    26/84

    Section

    01

    57 19

    ENVIRONMENTAL CONTROLS

    Page 6

    Toronto

    Transit Commission

    CONTRACT

    A29 1

    5

    Specifically prohibit the following activities within Tree Protection Zones (TPZ)

    .1 Construction activities .

    .2 Altering of grade by adding fill, excavating, trenching, scraping, dumping, or

    disturbances of any kind .

    .3 Storage

    of

    construction materials, equipment, soil, construction waste,

    or

    debris

    .4 Disposal of any liquids (e.g. concrete wash-out, gas, oil, etc.)

    .5 Movement of vehicles and machinery.

    12.3 If temporary stock piling of materials is to be located near a TPZ, appropriate measures, as

    determined by a certified arborist, shall be installed to ensure no material enters the TPZ.

    12.4 Establish a Wildlife Protection Monitoring plan to implement the Migratory Bird protections.

    12.5 The Contractor

    shall establish a mitigation and monitoring plan to implement construction

    timing restrictions to avoid nesting/breeding periods for wildlife, including migratory birds.

    As a result, wildlife habitat shall not be removed, from April1 to July

    31

    annually, where

    possible.

    12.6 If construction occurs at any Site between March 15 and July 31, the Contractor shall use a

    qualified avian biologist to conduct a survey for migratory bird nesting sites.

    12.7 Inspection results shall be recorded and shall include photos

    of

    any nests identified during

    the inspection with locations of nests shown on a Project Site plan.

    12.8 If an active nest is found during the breeding season, the Contractor shall immediately

    notify the Commission s Representative and shall not disturb

    nor

    conduct Work that may

    adversely impact the active nests.

    12.9 If an active nest is found, the Contractor shall do the following:

    1

    The Contractor s avian biologist shall prepare a Site-specific mitigation plan in consultation

    with the Commission s Representative. The Commission s Representative will contact the

    Canadian Wildlife Service (CWS) to review and approve the Site-specific mitigation plan .

    .2 Prior to vegetation clearing, wildlife capture/relocation and dispersal techniques shall be

    used to protect wildlife from physical harm

    in

    accordance with the CWS approved

    Site-specific mitigation plan .

    .3 Establish procedures to ensure that vegetation with active nests and areas adjacent to the

    nest cannot be disturbed until the young have fledged.

    12.10 Where there are no active nests, vegetation clearing can occur within three (3) calendar

    days of the survey, between March 15th and July 31st breeding period. For clearing activity

    to occur outside of the three {3) calendar day window, the survey must be repeated.

    12 11

    The Contractor shall be responsible for the implementation of any Site-specific mitigation

    plan approved by the CWS for the identified nesting site.

  • 8/9/2019 01 57 19 - Environmental Controls

    27/84

    Toronto Transit Commission

    CONTRACT A29-1

    12.12 Reporting and Records:

    Section 01 57 9

    ENVIRONMENTAL

    CONTROLS

    Page27

    .1

    The Contractor shall provide a monthly report during nesting season of all

    surveys

    and

    findings of nesting birds and wildlife recorded at the Site

    .2 The Contractor shall maintain a copy of the Terrestrial Habitat Monitoring Plan,

    l l

    reports

    any mitigation plans prepared and all monitoring reports and records on Site for review b

    Federal and/or Provincial regulatory enforcement personnel .

    .3 The Contractor shall maintain a copy

    of

    any CWS mitigation plans on Site

    and make

    them

    available to the public upon request.

    12.13 Vegetation Protection

    and

    Predator Protection Plans:

    12.14 Landscape Contract Drawings identify additional plant materials to be protected

    Contractor shall install protections prior to on-Site activities, in accordance with the Contrac

    Documents,

    and

    shall inspect and maintain such protections as shown on the Contrac

    Drawings. ·

    12.15 Tree replacements and re-vegetation must be

    in

    accordance with requirements specified in

    the Contract Documents.

    12.16 The construction Site is located within the regulation area for both the Emerald Ash Bore

    and the Asian long-Horned Beetle. Vegetation Removal shall be

    in

    accordance with

    Canadian Food Inspection Agency (CFIA) requirements which include:

    12.17 All trees being monitored have a numbered metal tag affixed to the tree with a staple. An

    of these tagged trees that require removal must have CFIA inspect them prior to removal.

    .1

    All removed federal tags from removed trees must be returned to CFIA.

    13 DISCOVERY OF UNEXPECTED CONTAMINATION

    13.1 If unexpected contaminated materials are encountered, the Contractor shall immediatel

    stop work in the affected area, inform the Commission s Representative

    and

    proceed in

    accordance with the Commission Representative s direction.

    14 SOILS MANAGEMENT PLAN

    14.1

    Soils management at each construction Site shall be conducted in accordance with the

    relevant Sections of this Specification, including Sections 02 61 00 and 31 23 15, as

    applicable.

    14.2 The Contractor shall prepare a Soils Management Plan which implements the

    recommendations of the applicable Soil and Ground Water Management Strategy. The

    Contractor shall set out sampling and testing procedures for management

    of

    excavated soi

    according to all applicable regulatory requirements.

  • 8/9/2019 01 57 19 - Environmental Controls

    28/84

    Section 01 57 19

    ENVIRONMENTAL CONTROLS

    Page28

    Toronto Transit Commission

    CONTRACT

    A29 1

    14.3 The Contractor shall submit a proposed protocol to the Commission s Representative

    where soils confirmed to be contaminated are to be segregated on Site to allow for further

    testing by the Contractor. Contractor shall follow protocols for collection

    of

    samples, their

    testing and methods of handling in accordance with those set forth in Section 02 61 00 of

    this Contract, as applicable.

    14.4 For soils, which do not meet all of the MOE standards, handling and disposal requirements

    shall be determined based on thorough soil sample extraction and chemical analysis

    by

    the

    Contractor. Analytical results shall

    be

    evaluated and compared with the applicable generic

    standards, as provided in

    Soil, Groundwater and Sediment Standards for Use under Part

    XV.1 of the Environmental Protection Act (EPA) (dated March

    9

    2004). The standards are

    referenced in Ontario Regulation 153/04 (the Record

    of

    Site Condition Regulation),

    0.

    Reg. 153/04 as amended by

    0.

    Reg. 266/08) under the EPA.

    14.5 Prior to construction, the Commission will require the Contractor to submit the names,

    locations and types of licences, as issued by the MOE, of the designated soil disposal sites.

    15 DESIGNATED SUBSTANCES

    15.1 The Occupational Health and Safety Act (OHSA) imposes a duty on the Owner

    (Commission) to inform the Contractor

    of

    any designated substances present

    at

    the Work

    Site, where it is reasonable for the Commission to have known about the substance.

    15.2 There are currently eleven (11) substances designated. They are subject to special

    regulations under OHSA:

    .1

    Asbestos

    .2 Lead .

    .3 Ethylene oxide

    .4 Mercury

    .5 Silica (free crystalline silica)

    .6 Vinyl chloride monomer (not PVC)

    .7 Benzene

    .8 Arsenic

    .9

    Coke oven emissions

    . 10 Acrylonitrile .

    .

    11

    lsocyanates.

  • 8/9/2019 01 57 19 - Environmental Controls

    29/84

    Toronto Transit Commission

    CONTRACT A29-1

    15.3 Asbestos:

    Section 01 57

    19

    ENVIRONMENTAL CONTROLS

    Page 9

    .1

    Notify the Commission's Representative immediately if any material suspected

    to

    be

    asbestos-containing material is discovered during demolition/construction

    .2 Cease work in the area

    and

    barricade the area to prevent entry until such time as th

    Commission's Representative confirms the presence or non-presence of asbestos

    .3 Comply with all provisions of the Occupational Health and Safety Act and the Regulations

    Respecting Asbestos on Construction Projects and in Buildings and Repair

    Operations .

    15.4 Man-Made Mineral Fibre:

    .1 Comply with Synthetic Vitreous Fibres Guidelines for Construction , Construction Safet

    Association of Ontario Document DS036.

    15.5 Designated substances, other hazardous materials and PCBs survey report.

    15.6 In accordance with the requirements

    of

    the Ontario Occupational Health and Safety Act, no

    reports of Designated Substances for Contract A37

    1

    have been prepared.

    16 POLYCHLORINATED BIPHENYLS (PCBS)

    16.1 Conform to the EPA and Regulations made thereunder, Ontario Regulation as amended.

    16.2 In the event of unexpected discovery of PCBs immediately notify Commission'

    Representative orally and in writing and do not handle, disturb nor remove items containing

    PCBs. Commission's Representative will authorize remedial work, if any, in writing.

    17 ENVIRONMENTAL CONTROLS AND CONTINGENCY PLAN FOR

    CLEAN UP

    OF

    SPILLS

    17.1 A spill is defined in the Ontario Environmental Protection Act as a discharge into the

    natural environment, from or out

    of

    a structure, vehicle or other container, that

    is

    abnorma

    in quality or quantity in light of all the circumstances of the discharge .

    17.2 The Contractor is solely responsible and liable for, without being limited to, all testing

    documentation, clean up reporting, repairs, removal, damages and associated costs an

    any other actions arising from a spill.

    .1 Provide, at each Site, a Spill Response Kit for use by any Site personnel including, but no

    limited to, Subcontractors and Commission's Representative(s). The Spill Response Kit

    shall contain materials and equipment capable of containing and disposing

    any

    spill tha

    may occur during the course of this Contract.

    .2

    Provide all equipment specific for controlling spills directly into Black Creek Creek and

    tributaries at thel construction Site(s}, or into stormwater management facilities that drain

    into these creeks.

  • 8/9/2019 01 57 19 - Environmental Controls

    30/84

    Section 1 57 19

    ENVIRONMENTAL CONTROLS

    Page3

    Toronto Transit Commission

    CONTRACT A29 1

    .3 Contingency plans shall include, but not

    be

    limited to, provisions for spills of hazardous and

    unknown materials (i.e. puncturing an unmarked drain during excavation)

    4 o prevent spills during construction re-fuelling the Contractor shall:

    .1 Not permit refuelling within 30 m of a watercourse or catchbasin .

    .2 Have Emergency Response Plan in place before construction commences.

    17.3

    In

    event of a spill, the Contractor shall at its own expense:

    .1 Immediately report the spill to the MOE Spills Action Centre

    .2 Immediately report the spill to the municipality within boundaries ofwhich the spill occurred

    .3 Immediately communicate the details to the Commission s Representative. Report on the

    type

    of

    spill, the quantity

    of

    the material spilled, the exact location of the spill and whether or

    not the contaminant has entered any drain, or water course,

    or

    if the spill has occurred on

    unpaved ground. Advise if any contaminant has entered a sewer line, floor drain, or has

    affected any unpaved ground .

    4

    Contain the spill in a safe manner

    .5 Proceed to clean up the spill

    in

    accordance with the applicable regulations.

    17.4 The Contractor shall prepare and submit in accordance with Article 3 Site specific Spill

    Prevention and Contingency Plan( s) for the avoidance, control and clean-up of spills in

    accordance with 0 Reg. 224/07 and to meet the requirements of O.Reg 675/98 and other

    applicable regulations. The Contractor shall

    be

    responsible for preparing, implementing,

    directing and supervising the contingency plan(s). Submit for the Commission s

    Representative s review five (5) copies of the Spills Prevention and Contingency Cleanup

    Plan and make appropriate changes as requested. The plan shall include as a minimum:

    .1 Names and telephone numbers of persons

    in

    local municipalities and MOE to be notified

    immediately of a reportable spill

    .2 Names and telephone numbers

    of

    representatives

    of

    fire, police and health departments

    of

    local municipalities who are responsible to respond to emergency situations

    .3 Names and telephone numbers

    of

    companies experienced in control and clean-up

    of

    hazardous materials that will

    be

    called

    in

    an emergency involving a spill.

    .4 A Site plan for each construction Site that identifies: Pre-designated safe and secure

    Product storage areas at the materials staging areas; set-backs from any nearby

    watercourses, drainage ditches and catchbasins and the creek that each drains into;

    refuelling and equipment maintenance areas; diesel fuels and above ground storage tanks;

    and compressed gas cylinder storage.

  • 8/9/2019 01 57 19 - Environmental Controls

    31/84

    Toronto Transit Commission

    CONTRACT A29-1

    Section

    01 57

    ENVIRONMENTAL CONTROLS

    Page 31

    5 Shall require daily and weekly inspection of active and inactive storage areas

    and

    report th

    results in the

    Ell

    and Weekly Summary Log .

    .6 Procedures for monitoring and inspection to limit or reduce the potential for spills.

    17.5 Contingency plans shall include, but not be limited to, provisions for spills of hazardous an

    unknown materials (i.e. puncturing an unmarked drain during excavation). The contingenc

    plan shall include:

    1

    Proposal for immediate containment and control of spill, clean up procedures to be initiate

    immediately and any other action to be taken to mitigate potential environmental damag

    while awaiting additional assistance

    .2 Be responsible for preparing, implementing, directing and supervising the contingency plan

    17.6 Spill prevention training for each Site shall be documented and included in the ETAP. A

    personnel, including Contractor, Subcontractors and Commission s Representat ives sha

    be trained in the procedures for all construction Sites which each may access during th

    construction.

    END OF SECTION

  • 8/9/2019 01 57 19 - Environmental Controls

    32/84

  • 8/9/2019 01 57 19 - Environmental Controls

    33/84

    Toronto Transit

    Commission

    CONTRACT A29-1

    Section 1

    5719

    ENVIRONMENTAL CONTROLS

    ATTACHMENT 1: ENVIRONMENTAL INSPECTION LOG

    Environmental Inspection Log - Contract A29-1

    Site Location:

    Date D/MIY):

    Time 24hrs

    :

    Weather Conditions:

    Construction Status:

    Inspection Log Completed by printed name and signature):

    CHECKLIST ITEM: ACCEPTABLE

    1

    NOT ACCEPTABLE

    1

    * NOT APPLICABLE

    1.

    Sediment Control Structures

    Heavy Duty Sil t Fences IJ

    c

    c

    Jersey Barriers with Silt Fence IJ

    c c

    Staked Sediment Control Logs IJ

    IJ

    c

    Truck Wash IJ

    c c

    Mud Mat

    c IJ c

    Concrete Wash-Out Station

    c

    c c

    Storm Drain Inlet Protection

    IJ c c

    Sediment Traps

    c c c

    Temporary Rock Flow Check Dams

    IJ c c

    Other

    c

    c c

    2.

    Stabilization Areas

    Erosion Control Blankets

    c

    IJ c

    Mulch

    c c c

    Hydroseed IJ c c

    3.

    General Noise Control Measures IJ c c

    4.

    General Air Quality Control Measures IJ

    c c

    8

    Dewatering

    Discharge Quality

    c c c

    Discharge Filters/Treatment System IJ

    c c

    Groundwater Level excavations)

    c

    c

    c

    Groundwater Level ecological) IJ c

    c

    9. Environmental Monitoring Activities

    Soil Quality

    IJ c c

    Dryness Level of Spoils

    IJ

    c c

    Surface Water IJ

    c c

    Aquatic Environment

    c c

    c

  • 8/9/2019 01 57 19 - Environmental Controls