01 57 19 - Environmental Controls
Transcript of 01 57 19 - Environmental Controls
-
8/9/2019 01 57 19 - Environmental Controls
1/84
Toronto Transit Commission
CONTRACT A29-1
1
DESCRIPTION
Section 1 57 9
ENVIRONMENTAL CONTROLS
Page
1.1
This Section covers Work for protection
of
the environment during construction, Site
preparation and demolition Work.
1.2 Provisions
of
this Section are in addition to requirements
of
other Sections
of the
Contrac
Documents.
2
DEFINITIONS
2.1
Alert Level: Monitored level specific for each individual environmental aspect at which
environmental contingency measures must be implemented.
2.2 Corrective Action: Action to eliminate the cause of a detected nonconformity.
2.3 Complaints Protocol: Jurisdiction specific (e.g. The City
of
Toronto) procedures to be
followed if a complaint is received from either the public
or
an affected third party (Refer to
Attachment 6 .
2.4 Comprehensive Environmental Controls and Methods Program (CECMP): Contractor s
specific approach to address environmental controls at each construction Site. The
Contractor s and its Subcontractor s management system shall be used to develop and
implement all environmental aspects.
2.5 Environment: Surroundings in which the Contractor and its Subcontractors operate
including air, water, land, natural resources, flora, fauna, humans and their interrelation.
2.6 Environmental Aspect: An element of the Contractor s activities, Products or services tha
can interact with the environment.
2. 7 Environmental Inspection Log ElL): Daily environmental reporting form prepared for each
construction Site (Refer to Attachment 1 .
2.8 Environmental Performance: The measurable results of the Contractor s and its
Subcontractors management of its environmental aspects.
2.9 Environmental Objectives: Toronto York Spadina Subway Extension Project s overal
environmental goals consistent with the approved environmental assessments nd those
referenced in the subsequent Articles of this Section.
2.10 Environmental Target: Detailed performance requirements applicable to this Contract as
described in subsequent Articles, as shown
on
Drawings and in applicable Appendices.
2.11
Incident Follow-Up Report Form: Form to be used to report all environmental incidents
occurring at any Site (Refer to Attachment 3).
2.12 Noise Monitoring Report Form: Form to be sued to report all noise monitoring records
throughout construction for each Site (Refer to Attachment 4).
2.13 Preventive Action: Action to eliminate the cause of potential non-conformity.
-
8/9/2019 01 57 19 - Environmental Controls
2/84
Section
01 57 19
ENVIRONMENTAL CONTROLS
Page2
Toronto
Transit Commission
CONTRACT A29-1
2.14 Proactive Mitigation: Means, methods and procedures instituted by the Contractor to
implement the environmental aspects of the CECMP.
2.15 Procedure: Specified way to carry out an activity or process.
2.16 Record: Document(s) stating results achieved or providing evidence of activities
performed. These will include, but are not limited to, the
Ell
(Refer to Attachment 1 , the
Weekly Summary Report (Refer to Attachment 2), the Incident Follow-up Report (Refer to
Attachment
3 ,
Construction Noise Monitoring Form (Refer to Attachment 4)
and
the
Construction Vibration Monitoring form (Refer to Attachment 5).
2.17 Thermal Effects Monitoring Form: Reporting form for thermal effects monitoring of
dewatering effluent and the discharge effects at creek outfalls (Refer to Attachment 8).
2.18 Trigger Level: Monitored level at which proactive mitigation specific to each environmental
aspect must be initiated and reported on in the Ell.
2.19 Vibration Monitoring Form: Reporting form for ongoing construction vibration monitoring
results at each Site to support Ell and Weekly Summary Report(s) (Refer to Attachment 5).
2.20 Weekly Summary Report: Reporting form to be used to summarize issues identif ied in the
daily Ell and report on status of remedies or corrective actions taken Refer to
Attachment 2).
3 CONTRACTOR S RESPONSIBILITIES
3.1 The Contract Documents detail the minimum environmental protection requirements,
specifications, monitoring, reporting, materials and construction staging that the Contractor
shall install and implement. The Contractor may, at its own expense, recommend the
implementation
of
other or additional measures to suit the Contractor s selected
means
and
methods in accordance with all regulatory permits and requirements. Proposed alternative
measures shall be provided to the Commission s Representative prior to commencing any
Work and be submitted in accordance with Section
01
33 00.
3.2 The Contractor shall install, implement and maintain in good working order, all
environmental controls and monitoring
as
set out in the Contract Documents, together with
any additional monitoring deemed necessary in order to perform the Work with Contractor s
selected means and methods.
4 SUBMITTALS
4.1
Unless noted otherwise, within thirty (30) calendar days
of
date
of
Notice to Proceed and as
agreed to by the Commission s Representative, submit a Comprehensive Environmental
Controls and Methods Program (CECMP) to the Commission s Representative for all
disciplines identified in this Section covering the first ninety (90) days of the Work, or as
required to confirm or establish any baseline monitoring requirements as detailed in the
Contract Documents. The Contractor shall make appropriate amendments to the plans as
requested by the Commission s Representative.
-
8/9/2019 01 57 19 - Environmental Controls
3/84
Toronto
Transit Commission
CONTRACT A29-1
Section 01 57
9
ENVIRONMENTAL CONTROLS
Page3
4.2
5
5 1
5 2
5 3
1
Within sixty (60) calendar days of date of Notice to Proceed submit for the Commission s
Representative s review a set of CECMPs for all disciplines identified in this Section
covering the entire schedule of the Work for each construction Site. The Contractor sha
make appropriate changes to the plans as requested by the Commission s Representative
and issue.
CONTRACTOR S COMPREHENSIVE ENVIRONMENTAL CONTROLS
AND
METHODS
PROGRAM {CECPM)
The Contractor shall provide a CECMP comprising Site specific environmental controls and
methods, monitoring, testing implementation and record keeping as applicable to the
environmental aspect of the Work for each construction Site in a
manner
generall
consistent with the IS014001 :2004 Environmental Management Systems. The CECPM
shall address all phases of the Work, including temporary works design and construction
materials procurement and construction.
The CECMP shall establish, document, implement, maintain and continually improve the
CECMP in accordance with the requirements of these Contract Documents, all applicable
regulations and requirements, and the conditions of all permits associated
with
this Wor
and determine how it will fulfill tt)ese requirements.
At a minimum the Contractor s CECMP shall include the following categories describing the
Contractor s commitment to
and
procedures covering:
General Requirements:
1 Control of the Comprehensive Environmental Controls and Methods Program .
.2 Project Environmental Commitment:
1 The environmental philosophy to be followed on the Work and provide direction to
action in order to avoid delays in identifying and addressing environmental impact
arising from the Work
.2 The applicable mitigation measures and follow-up requirements during
the
Work
.3 The contingency and response procedures related to the discovery of unexpected
Site conditions .
4 The roles and responsibilities for the Contractor and Subcontractor(s), including Wor
accountability and institution of reporting protocols with respect to environmenta
aspects .
. 5 Implement an Environmental Awareness Training Program (EATP} to
ensure
that a
on-Site personnel understand the importance
of
environmental protection, the cause
of environmental damage, proper environmental protection practices and the
Contractor and Subcontractor( s) obligations to ensure that the environment is
protected .
.6 Implement an adaptive monitoring and management program to verify that a
environmental protection measures required in this Section are being properly
implemented and maintained and are effective
.7 Collection and maintenance of records are maintained to monitor the effectiveness o
environmental controls.
-
8/9/2019 01 57 19 - Environmental Controls
4/84
-
8/9/2019 01 57 19 - Environmental Controls
5/84
Toronto
Transit
Commission
CONTRACT A29-1
Section
1 57 9
ENVIRONMENTAL
CONTROLS
Page 5
3 Guidance on Sampling and Analytical Methods for use at Contaminated Sites in
Ontario, Dec 1996
.4 Guideline for Implementing Spill Prevention and Contingency Plan Regulatory
Requirements {O.Reg. 224/07)
.4 Ministry of Transportation Ontario {MTO), MTO Drainage Management Manual
{DMM), {1997) .
.5 Ontario Regulations, standards and guidelines pertaining to waste effluen
monitoring, erosion and sediment control, air, polychlorinated biphenyls {PCBs)
spills, 3 R regulations {Reduce, Reuse, Recycle) and any other regulations affecting
the environment.
6
Ontario Provincial standards where specifically identified
in
the Contract Document.
1 Ontario Provincial Standard Specification {OPSS)
.2 Ontario Provincial Standard Drawing (OPSD)
.7 Municipal by-laws pertaining to sewer use, sediment and erosion control, noise and
vibration, and any other environmental requirements from the applicable jurisdiction
depending
on
the location
of
the construction component activities .
.8 Toronto and Region Conservation Authority (TRCA), Regulation
of
Development
Interference with Wetlands and Alterations to Shorelines and Watercourses {Ontario
Regulation 166/06)
.9 Greater Golden Horseshoe Area Conservation Authorities Erosion and Sedimen
Control Guidelines for Urban Construction, December 2006 .
. 1
0 The Contractor shall identify any additional regulations or requirements that must
be
met
.2 Execution, Implementation and Operation:
1
Establish baseline, conditions trigger and alert levels and approach for each
environmental aspect
.2 Establish and implement program for each environmental aspect.
3
Establish and implement reporting and communication protocols using reporting tools
appended herein
.3 Resources, Roles, Responsibility and Authority:
1 Define Contractor's responsibilities and management commitment for environmenta
aspects
.2 Identify personnel and authorities for all Work associated with environmental aspects
.1 The Contractor shall ensure the availability of resources essential
to
establish
implement, maintain and improve the CECMP. Resources include human
resources and specialized skills organization infrastructure, technology and
financial resources .
.2 The Contractor shall employ a full time qualified Environmental Manager to be
responsible for the monitoring, data collection, inspections, and reporting
o
compliance with all Contract Environmental requirements and permit conditions
The Contractor shall implement and operate the CECMP and ensure the
availability
of
resources essential to establish, implement, maintain and improve
the CECMP.
-
8/9/2019 01 57 19 - Environmental Controls
6/84
Section
1
57 19
ENVIRONMENTAL CONTROLS
Page
Toronto Transit Commission
CONTRACT A29 1
.3 Contact information for
the
Environmental Manager shall be provided, including
business phone, after hours phone, fax, email and mailing address
4 All plans, monitoring programs and reports shall be reviewed, stamped and
sealed by a Professional Engineer or Professional Geoscientist licensed in the
Province of Ontario .
.5 The Environmental Manager shall assess the effectiveness of Project
environmental protection measures to ensure that:
1
Environmental protection measures are adequate for need and
functioning as intended .
.2 All required monitoring and testing equipment is checked regularly and is
in working order. All failed devices are replaced within twenty-four (24) to
forty-eight ( 48) hours, depending on
individual monitoring requirements .
.3 Deficiencies are corrected immediately
.4 All daily, weekly, and monthly records, logs, and reports are established,
reported, and maintained on Site
.5 Monitoring reports are prepared and submitted in accordance with
Section 01 33 00 .
.6 The Environmental Manager shall have the following qualifications:
1 A degree or diploma from a recognized university or college in a natural
or physical science with specialization in fisheries biology, aquatic
biology, ecology, or another related discipline, and
2 Minimum of five (5) years related work experience, and
3 Minimum o three (3) years experience in monitoring construction
activities in and around fish habitat, and
.4 The Contractor shall define, document and communicate roles,
responsibilities and authorities in order to facilitate effective management
of environmental aspects in the CECMP
.7 The Contractor shall retain air, water, noise and vibration monitoring
professionals to establish and conduct baseline and monitoring requirements,
as well as reporting for construction noise and vibration in accordance with the
applicable City construction noise by-laws and construction vibration by-laws.
The noise monitoring professional must demonstrate that he/she has a current
certificate of competency in environmental acoustics technology issued by an
accredited program of an Ontario Community College, or other approved
consulting agency, or is otherwise suitably qualified and acceptable to the
Commission s Representative. The Contractor shall demonstrate that the air
quality monitoring professional has a competency in air quality monitoring and
reporting .
.8 The Contractor shall retain a qualified avian biologist to assess the potential for
and development o mitigation plan(s) if nesting birds are found on the Site(s) in
accordance with the Migratory Bird Convention Act.
-
8/9/2019 01 57 19 - Environmental Controls
7/84
Toronto Transit
Commission
CONTRACT A29-1
Section 01 57 19
ENVIRONMENTAL CONTROLS
Page7
.3 Communication including a Rapid Response Protocol as follows:
1 Immediate environmental concerns with respect to construction activities o
associated with Site activities are identified:
1 The Contractor s Environmental Manager shall immediately report the
incident directly to the Contractor and the Commission s Representative
.2 The Commission s Representative shall immediately contact the relevan
stakeholder agencies, per Section 5.35
or
the Spill Response
Contingency Plan as applicable,
in
Section 18
.3 The Contractor s Environmental Manager shall work with the Contracto
to ensure the cause of the incident is quickly addressed and a plan is
developed to prevent a re-occurrence (i.e. mitigative measure
implemented). Mitigative measures shall include, but not be limited to
the following:
1 Changes to Work protocols that led to the incident.
2 Further training of personnel.
3 Implementation of additional engineering controls; and
4 Increased frequency
of
monitoring and ongoing maintenance
4
The Contractor s Environmental Manager shall verify whether prope
procedures had been followed prior to the incident.
.5 The Contractor s Environmental Manager shall record the incident on an
Ell attach a description of the mitigation measures program that will be
implemented in response to the incident, and submit the l l and
mitigative measures plan directly to the Commission s Representative
.6 The Contractor s Environmental Manager shall also submit
an
Inciden
Follow-up Summary report to the Commission s Representative, verifying
that the proposed mitigation measures program was implemented
successfully and noting the condition of the identified area o
environmental concern. If the issue is not resolved in a reasonable period
of time, per the mitigation measures program developed, the
Commission s Representative shall take further action to ensure
mitigation measures are implemented as required .
.7 The Commission s Representative will liaise with affected stakeholde
agencies throughout the incident resolution, as required, to ensure that al
relevant mitigation measures requested by said agencies, to
the
greates
extent practicable, are implemented .
.2 The Contractor must ensure that brief daily discussions are held with its
Environmental Manager to address any shortfalls identified during the
implemented monitoring programs. A daily review of any identified potentia
concerns will allow the implementation of mitigative measures before any
negative environmental impacts result.
3 To update the Commission s Representative
of
the ongoing status
of
the
monitoring program on a regular frequency
4
In
the event that a dust, noise, vibration or other exceedance is detected
.5 To respond to complaints if they are received.
-
8/9/2019 01 57 19 - Environmental Controls
8/84
Section
1
57 9
ENVIRONMENTAL CONTROLS
Page 8
Toronto Transit Commission
CONTRACT A29 1
4 Establish and Implement Documentation and Procedures for the Control of
Documents
.5 Establish and implement Operational Controls .
.4 Measuring, Analysis and Improvement:
.1
Evaluation of compliance
.2 Continued improvement.
.3 Nonconformity, corrective action(s)
.4 Preventive action(s).
5.5 The CECMP shall include a Site plan for each construction Site indicating locations
of
all
construction facilities, wet and dry storage areas, trailers, environmental controls equipment
and facilities, waste materials storage, erosion and sediment control areas, including wheel
wash, mud mats and all other elements of the Site.
5.6 The Contractor shall establish a co-ordinated monitoring and reporting program that
provides daily, weekly and monthly reporting as required for the various disciplines defined
in this Section. This program shall manage the individual inspection and reporting
requirements of each component plan, together with electronic and paper monitoring
reports. A copy of all reports shall be maintained on Site(s) and be maintained and
available for immediate inspection by the Commission s Representative and any
enforcement agency representative. Provide a copy of these reports to the Commission s
Representative.
5.7 The condition of all environmental controls shall be reported on the daily Environmental
Inspection Log Ell) (Refer to Attachment 1) of each Site, the Weekly Summary Report
(Refer to Attachment 2) and the Incident Follow-up Report (Refer to Attachment 3). A
sample copy
of
each form is appended to this Section.
5.8 Monitoring and reporting documentation shall also be maintained electronically and shall be
provided to the Commission s Representative on CD/DVD in a format to be mutually agreed
upon.
5.9 The Contractor shall maintain a record of any enforcement actions (Refer to Attachment 3)
that occur on-Site including, but not limited
to
any citation(s), requirements to correct and
any follow-up reports from the enforcement agency. The Contractor shall report all
enforcement actions immediately to the Commission s Representative and make available
a copy of complaints and notices received from the enforcement agency. The Contractor
shall make available any records
of
remedial action taken by the Contractor of any
violations associated with all permits obtained by the Commission for this Work.
5.10 The Contractor shall prepare all monitoring and implementation programs, schedules, site
plans, photo logs and drawings of affected areas. Plan elements, baseline, trigger and
alarm levels, and frequencies are described in subsequent Articles.
-
8/9/2019 01 57 19 - Environmental Controls
9/84
Toronto Transit
Commission
CONTRACT A29-1
Section
01
57
9
ENVIRONMENTAL
CONTROLS
Page9
5.11
1
The Contractor shall develop and include in the CECMP and implement an Environmenta
Awareness and Training Plan (EATP).
The EATP will include the following training components:
1 Decontamination Procedures
.2 Materials Handling Procedures
.3 Spill and Fire Response/Emergency and Response Protocols
4 Discovery of Unexpected Site Conditions (i.e. dewatering, soil contaminations, etc.)
.5 Erosion and Sediment Control Measure Awareness .
.6 Dust Prevention and Control.
.7 Noise Prevention Awareness .
.8 Communications Protocols.
5.12 The Contractor is responsible for administering the EATP to all on-Site personnel and mus
ensure that Subcontractor(s), hired consultants and all other individuals in Project Work
areas receive training prior to entering the Site. The EATP must provide
for
a once
pe
year update training for all personnel. All new personnel must be trained
prior
to entering
the Site and receive up-date training annually thereafter.
5.13 The Contractor shall submit five copies of the ETAP to the Commission s Representative
prior to the initial training. The Contractor shall make any revisions requested by the
Commission s Representative.
5.14 The Contractors Communications Protocols shall reflect procedures set forth in the TYSSE
Complaints Protocol as outlined in the Toronto-York Spadina Subway Extension
Downsview Station to Steeles Avenue Environmental, Complaints Protocol, dated Februar
2008 (Refer to Attachment 6).
6 PRODUCTS AND EQUIPMENT
6 1 The Contractor shall provide all noise and vibration, air quality, water quality, sampling and
testing equipment, materials, and recording devices necessary to conduct all required
monitoring, testing and reporting for the environmental monitoring for the duration o
construction at each Site.
6.2 The Contractor shall provide on Site all materials necessary to implement all environmenta
controls, including contingency measures specified in the Contractor s Environmenta
Controls and Methods Program.
6.3 The Contractor shall obtain the services of off-Site testing laboratories and shall provide the
necessary test results associated with the various monitoring plans.
7 MONITORING/AUDITING
BY
COMMISSION S REPRESENTATIVE
7 1 The Commission s Representative will monitor/audit Contractor compliance with al
environmental requirements in accordance with Section
01
40 00.
-
8/9/2019 01 57 19 - Environmental Controls
10/84
Section
1
57
9
ENVIRONMENTAL CONTROLS
Page 10
Toronto Transit Commission
CONTRACT A29 1
8 DUST AND AIR QUALITY CONTROL DURING DEMOLITION AND CONSTRUCTION
8.1 The Contractor shall prepare and submit for approval a plan for dust and air quality
monitoring. The plan shall include a Site plan showing:
.1 The pre-construction and construction monitoring locations of sensitive receptors {e.g. in
the public right-of-way adjacent or ajdacent to or across the street from each construction
Site of this Contract) including: on the York University Campus - at mulitple locations within
the Harry W. Arthur Common area at York University and including the Harry Sherman
Crowe Co-op and based on the locations and extents of the construction area{ s )
.2 The locations
of
construction Site{ s) sources of total dust, Total Suspended Particulates
{TSP), Particulate Matter of 2.5 microns or smaller {PM
2
.
5
,
crystalline silica and other
contaminants as applicable within the construction Sites .
.3 The locations of major excavations and soil stock piles
.4 Location
of
on-Site roads to
be
utilized during construction. Indicate
if
roads are to be
paved
or
unpaved .
.5 Location
of
Site entrances and exits, including location of wheel wash facilities .
.6 Location of truck staging area{s)
.7 Location
of
areas of special concern (on-Site and off-Site) such as fresh air intakes, air
conditioners and windows of adjacent buildings and residences.
8.2 A description
of
the monitoring
Jocation{s ,
monitoring methods and equipment, approach,
provision of power to the monitors, sample handling procedures, and data collection
frequency for Total Suspended Particulates (TSP) and Particulate Matter
Jess
than 2.5
microns in diameter {PM
2
5
, crystalline silica, other contaminants as applicable to the
demolition and any materials stored on-Site.
8.3 The results of the monitoring shall be compared to relevant guidelines including, but not
limited
to,
their respective standards, guidelines, and time weighted average exposure
value {TWAEV) as indicated in 0. Reg.
419/05
Schedule 3 and OHSA Regulation 833, or
as directed by the Commission s Representative.
8.4 A listing of standard operating procedures {SOPs) for standard techniques
in
accordance
with best practices for the reduction
of
air emission from construction and demolition
activities within the construction industry. One {1) SOP is required for each mitigation
technique and shall be included as an appendix to the plan.
8.5 A preliminary schedule for pre-construction, construction, and post-construction monitoring,
including expected work day durations and identification of major construction activities that
are expected to generate airborne contaminants.
-
8/9/2019 01 57 19 - Environmental Controls
11/84
Toronto
Transit Commission
CONTRACT A29-1
Section
01 57
ENVIRONMENTAL CONTROLS
Page
1
8.6 During progress of the Work, implement the approved plan, monitoring, reporting, complain
response and contingency program to the satisfaction of the Commission s Representative.
8
7 The Contractor shall provide/complete air monitoring of crystalline sil ica, airborn
particulate and weather during pre-construction and construction.
8.8 A minimum of
one
(1) air monitoring locations shall be utilized at each discrete area
of
th
overall construction Site.
8.9 A minimum of two (2) full weeks of pre-construction monitoring shall be completed.
8.10 Air monitoring shall occur during construction and shall match the Contractor s Wor
schedule in terms of days per week and hours per day.
8 11 Continuous sampling methods shall be utilized for monitoring TSP, PM10 and PM2.5
Acceptable continuous monitoring methods include the following:
1
Tapered element oscillating microbalance (TEOM)
.2 Portable laser photometers with internal data loggers, with weatherproof environmenta
enclosure
.3 Portable aerosol monitors with detectors using Turnkey laser nephelometer
.4
Portable programmable mass flow controlled
PM
reference samplers
.5 Others as approved by the Commission s Representative.
8.12 Acceptable manufacturers for the above instrumentation are:
1
TSI.
2 BGI.
.3 Thermo Scientific
.4 Met One Instruments
.5 Others as approved by the Commission s Representative.
8.13 Continuous monitors shall be set up to alert the Environmental Manager in
the
event tha
any
of
the limits are exceeded. On the detection
of
an exceedance, the Commission
Representative shall be notified verbally as soon as possible and followed by notification in
writing within two (2) days, including the time of occurrence, duration
of
the exceedance
magnitude
of
the exceedance, mitigation measures taken, wind speed and wind direction a
the time of the exceedance. To start, the instantaneous alert level shall be equal to th
twenty-four (24) averaging time values. After two (2) months of construction, the Contracto
may propose
to
reduce the instantaneous alert level to a value higher than the twenty-fou
(24) hour averaging time value based on the data collected.
-
8/9/2019 01 57 19 - Environmental Controls
12/84
Section 1 57 9
ENVIRONMENTAL CONTROLS
Page 2
Toronto Transit Commission
CONTRACT A29 1
8.14 Data from the continuous monitors shall
be
logged with a time resolution of minimum one
{1) minute. Data shall
be
maintained on electronic storage media on Site throughout the
Contract. An electronic copy of all data shall be provided to the Commission's
Representative
in
a format mutually agreed upon between the Contractor and the
Commission's Representative.
8.15 Continuous monitors must
be
active and collecting valid data for 95 of the Contractor's
working hours {on a monthly basis). Contractor shall arrange
for
adequate provision of
spares, provision of reliable power sources, and scheduling of required calibration and
maintenance to achieve this requirement.
8.16 For the monitoring of crystalline silica, sampling shall be carried out using a combination of
a cyclone and pump assembly. Each sample length {duration) shall be a minimum of eight
{8) hours and the sampling shall, at a minimum, be carried out on a one-in-six
{1
in 6 day
sample regime. If the Contractor is working more than eight {8) hours during the sampling
day, the number of samples taken that day shall be adjusted to ensure that sampling results
are gathered for the entire working day. The intent
of
the one-in-six {1 in 6) day rotation is
to gather information over the construction period over different days
of
the week.
8.17 The Contractor shall provide notification to the Commission's Representative verbally as
soon as possible and followed
by
notification
in
writing within two {2) days of receiving the
non-continuous results from the laboratory, including the time of occurrence, magnitude of
the exceedance, mitigation measures taken.
8.18 The Contractor shall control dust and debris through the use of standard techniques and in
accordance with best practices for the reduction of air emission from construction and
demolition activities within the Work Site which include, but are not limited to, the following:
1 Cover or wet down dry materials to prevent blowing dust and debris
.2 Prevent dust from blowing across the Site(s) and from leaving the Site(s), in particular by
frequently wetting paved and unpaved temporary roads and excavated areas .
.3 Comply with Provincial regulations regarding the minimization
of
dust and airborne
pollution .
.4 Wash down the streets within the Work Site(s) on a daily basis,
or
more frequently as
required .
.5 Securely cover excavated material being removed from the Site(s) and all fill materials
being delivered to the Site(s) to prevent blowing of dust and suspended particulate matter
into the streets and haul routes as required
in
Section 02
6 1
00 - Impacted Soils Handling
.6 Application of calcium chloride shall be kept to minimum and shall be restricted to vehicle
right-of-way. In close proximity to watercourses, frequent applications of water shall be the
preferred method. Obtain the Commission's Representative's approval before chemicals
for dust control are used.
-
8/9/2019 01 57 19 - Environmental Controls
13/84
Toronto Transit Commission
CONTRACT A29-1
Section
01 57 19
ENVIRONMENTAL CONTROLS
Page
13
7
8.19
1
2
3
8.20
.1
Provide wheel wash facilities at all Site exits as shown on erosion and sediment contro
Drawings.
Emissions from Construction Equipment:
The Contractor shall establish truck-staging zones for vehicles waiting to load or unload
material at the Work Site. Such zones shall be located where diesel emissions have the
least impact on abutting properties and the general public.
Idling time for delivery trucks, dump trucks and all other internal combustion powered
equipment shall be reduced as appropriate.
The Contractor shall ensure that internal combustion powered engines are located away
from fresh air intakes, air conditioners and windows.
Reporting:
The Contractor shall provide the Commission s Representative with a monthly summary ai
quality report. The report shall include the following:
.1 For the continuous monitors: A summary of the statistics (mean, median, maximum
minimum, 75, 80, 85, 90 95, 99th percentiles) for the period, listing of exceedances
percentage of time exceeding, for all averaging times
.2 Continuous monitor uptime percentage as a percentage of the Contractor s working
hours
.3 Results from the non-continuous samplers
.4 Comparison of the monitored airborne contaminants to their respective regulator
limits and time weighted average exposure values (TWAEV) as indicated in OHSA
Regulation 833. The limits below are based on corresponding standards, criteria, and
guidelines and may be updated from time to time,
or
as directed by the Commission s
Representative.
Contaminant Source Averaging Time Value
(pglm3)
PM-TSP
0
Reg. 419/05, Schedule 3 24 hours
120
PM2.5 Canada Wide Standard 24 hours
30
PM10 MOE Interim Reference Level 24 hours
50
Crystalline Silica OHSA Regulation 833 Time-Weighted Average
100
Limit
(TWA)-
8 hours
Crystalline Silica MOE Guideline
hour
15
Crystalline Silica MOE Guideline 24 hours
5
.5 Copies of all written notices of exceedances submitted during the month
.6 Copies of all written complaint reports received during the month
.7 Summary of actions taken to address any exceedances and complaints (if any) and
their current status
.8 Summary of any changes and modifications to the Air Quality and Dust Controls and
Methods component of the CECMP
.9 Statement of compliance with the measures to control dust and debris through the
use of standard techniques and
in
accordance with best practices
. 10 Statement
of
compliance with the measures to control emissions
from
constructio
equipment.
-
8/9/2019 01 57 19 - Environmental Controls
14/84
Section
01 57 19
ENVIRONMENTAL CONTROLS
Page 14
Toronto
Transit ommission
CONTRACT A29-1
.2 The Contractor shall submit the monthly summary report in draft form to the Commission's
Representative within three (3) weeks
of
the end of each month
.3 The Contractor shall submit five (5) copies
of
each final monthly summary report to the
Commission's Representative within one ( 1) week
of
receiving the Commission's
Representative review
of
the draft report.
8.21 Final Close-Out Report:
1 Provide five (5) copies of a final close out report to the Commission's Representative
summarizing the dust control Work of all construction sites and an electronic copy of all
records made during the Work.
9 NOISE AND VIBRATION MONITORING AND CONTROL
9 1
The maximum allowable exposure to noise for a Commission employee (in accordance with
Ontario Occupational Health and Safety Act, Ont. Reg. 851) is:
Sound Level in Decibels Duration Allowed in Hours per day
85 8
86 6
88
4
89
3
91
2
92
1 5
94 1
95
0 75
97
0 5
100 0 25
103
0 12
Over103
No exposure
9.2 The Contractor shall comply with all applicable noise and vibration by-laws, preparing all
required baseline monitoring and reporting. The Contractor shall prepare this information in
a Noise and Vibration Monitoring Plan and provide five (5) copies
of
the plan, and
subsequent reporting results to the Commission's Representative monthly throughout the
construction period.
9.3 The Contractor shall be responsible for the cost
of
monitoring the noise and vibration on
Site and at sensitive receptors off Site.
9.4 In addition to requirements
of
the noise by-laws, the Contractor shall take special
precautions and apply noise abatement measures to reduce public exposure to noise.
These shall be identified in the Noise and Vibration Plan.
9.5 Shields
or
other physical barriers to restrict the transmission of noise: Barriers should have
sufficient mass such that noise passing through the barrier does not affect the net sound
level by more than 1dB at the receiver.
9.6 Pile drivers used for construction at the Station areas shall be of the quiet hydraulic
vibratory type, rather than the noisier drop weight type, unless such equipment is required
for other identified reasons by the Commission's Representative.
-
8/9/2019 01 57 19 - Environmental Controls
15/84
Toronto Transit Commission
CONTRACT A29 1
Section
1
57 19
ENVIRONMENTAL CONTROLS
Page 15
9.7 Soundproof housings
and
enclosures for noise producing machinery, such as compressors,
pumps, motors and generators. All equipment shall meet NPC115 guidelines t a
minimum.
9.8 Provide efficient intake
and
exhaust mufflers on internal combustion engines.
9.9 Provide efficient intake and exhaust silencers on air equipment.
9.10 Provide sound deadening lining material
on
hoppers and storage bins.
9.11 Conduct truck loading, unloading
and
hauling operations so that noise
is
kept to a
minimum.
9.12
9.13
9.14
9.15
9.16
1
All vehicles and equipment employed continuously on any Site for extended periods (in
excess of two (2) days) shall be fitted with sound reducing, broadband, multi-frequency
back-up (reversing) alarms, such as bbs-tek heavy duty model BBS-107, as distributed by
Walker Aggregates
Inc.
(Tel: 905-680-3747),
or
similar and approved. All such vehicles wil
be subject to inspection by the Environmental Manager for compliance with this
requirement. Any original factory installed vehicle and equipment back-up alarm units, no
complying with the sound level of the BBS-107 unit will not be permitted on such vehicles
and the Commission s Representative will have the right to order that they be removed and
replaced with the specified units.
Use electric, rather than internal combustion engine power, on chain saws, hoisting
equipment
in
fixed locations and other equipment, where electric power is available.
Position stationary noise producing equipment at maximum distance from public areas.
Provide any other effective noise control measure proposed by the Contractor and
approved by the Commission s Representative.
The Contractor shall design and establish a Noise and Vibration Monitoring Program within
the CECMP to document existing noise and vibration levels at each Site and t sensitive
receptors e.g. adjacent or across the street from each construction Site of this Contrac
including, but not limited to,
on
the York University Campus - at mulitple locations within the
Commons area at York University and including the Harry Sherman Crowe Co-op and
based on the locations and extents of the construction area( s . Notwithstanding the above
work shall be carried out as required by the City of Toronto noise and vibration construction
by-laws, to provide ongoing noise monitoring and reporting during construction that can be
used
to
substantiate the effects on nearby sensitive receptors. This Work may
be
the same
as that done to meet the noise and vibration requirements of the applicable City
construction by-laws, but must at a minimum provide:
A map of the location(s) of and list of adjacent and nearby sensitive receptor(s) fo
pre-condition monitoring (in the public right-of-way as described herein), that is likely to
experience noise and vibration effects from the construction activities. Noise nd vibration
levels for nearby sensitive properties shall
be
measured prior to the commencement
o
construction.
-
8/9/2019 01 57 19 - Environmental Controls
16/84
-
8/9/2019 01 57 19 - Environmental Controls
17/84
Toronto Transit Commission
CONTRACT A29 1
Section 1 57 9
ENVIRONMENTAL CONTROLS
Page 7
.3 Additional locations for continuous noise monitoring may be added as required .
4 Continuous noise monitoring shall be measured and reported in one (1) hour intervals ove
twenty-four {24) hour periods for the duration of construction at each Site
.5 Continuous noise measurements during construction activity shall be reported to the
Commission s Representative in weekly monitoring reports (Refer to Attachment 4)
Reports shall include noise level data (Leq, L90 and L 10) in A-weighted values dBA) in on
(1) hour intervals; with associated weather conditions (wind speed, temperature, conditions
etc.) to be provided for each one (1) hour interval. Construction activities shall also be
documented for each one ( 1) hour interval to be correlated with the noise level data fo
reference purposes.
9.20 Noise Data Analysis:
.1 Noise data measured during inclement weather conditions shall be discounted from th
data set. Inclement weather conditions shall include conditions where the wind
is
in exces
of 20 km/hr and any type of precipitation .
.2 Hourly sound data shall be presented for each for each
of
the A-weighted values, Leq, L90
and L10. Sound levels shall be sampled at a minimum rate
of
1/sec. The meter shall be
set to fast response .
.3 Submit a graph depicting the hourly A-weighted Leq, L90 and L 10 values and wind speed
against time.
9.21 Long-Term Vibration Monitoring:
.1 A vibration monitor shall be located at each construction Site to continuously monitor th
vibration level from construction .
.2 The closest sensitive receptor to the construction activity may be used as a location fo
continuous monitoring
.3 Additional locations for continuous vibration monitoring may be added as required
4 Continuous vibration monitoring shall be measured and exceedences above the critica
levels provided in the applicable City constriction bylaws logged and reported for the
duration of construction at each Site
.5 Commission s Representative shall be provided weekly monitoring reports (Refer t
Attachment
5 .
Reports shall include vibration level data referenced in
Peak
Particle
Velocity (mm/s) and associated frequency (5-100 Hz) specifically noting exceedance
above the critical levels provided in the applicable City construction bylaws. Construction
activities shall also be documented for each bylaw exceedance to be correlated with the
vibration level data for reference purposes.
-
8/9/2019 01 57 19 - Environmental Controls
18/84
Section 01 57
19
ENVIRONMENTAL CONTROLS
Page 18
Toronto Transit Commission
CONTRACT
A29-1
9.22 Vibration Data Analysis. Submit a graph depicting the PPV against time for all logged
events exceeding the criteria set out in the applicable City Construction By-law.
9.23 Documentation of all noise and vibration alerts shall be recorded and provided within two
(2) business days to the Commission's Representative, together with the corrective actions
taken.
9.24 The Contractor shall provide weekly monitoring reports (Refer to Attachment 5 for sample
vibration monitoring forms) to the Commission's Representative prior to each progress
meeting for the duration of the Work. Any alerts and corrective actions shall be reported on
the daily Ell (Refer to Attachment 1) and on the Weekly Summary Form. Records of the
monitoring program output shall be maintained
on
Site and provided in a weekly summary
to the Commission's Representative on an
Ell
form with monitoring documentation
provided in summary form both on paper and in electronic format.
9.25 Noise and vibration monitoring reports shall provide the statistical noise level data
described in paragraphs 9.20,
and 9 21
above. The full measurement data in one
1)
hour
intervals, relevant weather data (precipitation and wind speed), summary charts and
documentation regarding the specific location of monitoring are to be provided in an
appendix to the monitoring reports.
9.26 Provide five (5) copies of a final close-out report to the Commission's Representative
summarizing the then current status of all indicators listed in paragraphs 9.20 and 9 21
above and an electronic copy of
all
records made during the construction period.
9.27 Should the Commission's Representative and/or the Contractor receive any complaint from
the public, the Contractor shall verify that the general noise control measures agreed to
are in effect. The Contractor shall investigate any noise concerns and shall report to the
Commission's Representative within one ( 1) calendar day of the complaint on what actions
have been taken to mitigate the issue. Complaints shall also
be
reported
on
the daily
Ell
form and actions to abate, mitigate or confirm no exceedance shall be recorded on the daily
Ell and Weekly Summary forms
9.28 The Noise and Vibration Monitoring Plan shall identify the Contractor's procedures to
respond to public complaints in accordance with the projects-approved complaints protocols
as referenced in the project's York Complaints Protocol, June 2010 and the Contractor's
Rapid Response Protocol. Should the Commission and/or the Contractor receive any
complaint from the public, the Contractor shall verify that noise limits of NPC115) have not
been exceeded, and if they have, take immediate steps to ensure compliance.
9.29 Documentation requirements for incident or complaint reports shall be prepared and
forwarded immediately to the Commission's Representative and not later than within two {2)
business days after the incident, or complaint is received. This shall be completed in
accordance with the York Complaints Protocol (Refer to Attachment 6) for the York Region
portions of the project as set forth in the CECMP's Rapid Response Protocol. Copies of
plans, monitoring reports and incident or complaint reports shall be delivered to the
Commission's Representative in accordance with Section 01 33 00.
-
8/9/2019 01 57 19 - Environmental Controls
19/84
Toronto Transit Commission
CONTRACT A29 1
Section 1 57 9
ENVIRONMENTAL CONTROLS
Page 1
9.30 If the general noise control measures are complied with, but the public still complain abou
noise, the Commission's Representative will require the Contractor to investigate, and
subject to the results of the field investigation, apply alternative noise control measures
where these are reasonably available.
9 31
In selecting the appropriate alternative construction noise control and mitigation measures
the Commission's Representative and the Contractor will give consideration to the
technical, administrative, and economic feasibility
of
the various alternatives.
9.32 Where timing constraints
or
any other provisions of the municipal by-laws
may
cause
hardship to the Commission's Representative and the Contractor,
an
explanation of this wi
be outlined in a submission to the local municipality and the Contractor shall obtain an
exemption from such by-law directly from the local municipality in accordance with Section
01 14 00
10
EROSION AND SEDIMENT CONTROL PLAN
10 1 Erosion and sediment controls (ESC) at the York University Site are to be installed at the
site by the A29-2 Contractor and then turned over to the Contractor. Upon mobilization
Contractor will inspect and assume responsibility of these installed and/or remaining ESC
measures for completion of the station site. Hand over will
be
supervised by the
Commission's Representative.
10.2 Mitigation measures identified in the Contract Documents listed below are in accordance
with the OPSS, OPSD, and the Greater Golden Horseshoe Area Conservation Authorities
(GGHACA) Erosion
and
Sedimentation Guideline for Urban Construction (December 2006)
10.3 The purpose of the Erosion and Sediment Control Plan is to prevent sediment laden
stormwater from entering either temporary or permanent storm drainage systems during
construction by the following:
1 Minimize the duration and extent of soil exposure .
.2 Manage surface water to prevent contact with exposed soil surfaces
.3 Implement erosion and sedimentation control measures on-Site to prevent sedimen
migration off-Site
4 Erosion and Sediment Control Plan measures shall be in place before construction
commences .
.5 Baseline ESC control monitoring results shall be collected within one 1) week
o
installation, documented and provided to the Commission's Representative on the daily El
(Refer to Attachment 1) and Weekly Summary Forms (Refer to Attachment 2) for review
.6 A copy of all records shall
be
maintained on Site for inspection by regulators and the
Commission's Representative; a weekly summary shall be provided to the Commission's
Representative (paper and electronic versions); Ells shall be provided daily, together with
the weekly summary and for each incident/event that triggers an inspection.
-
8/9/2019 01 57 19 - Environmental Controls
20/84
.
Section
01 5719
ENVIRONMENTAL CONTROLS
Page20
Toronto
Transit
Commission
CONTRACT A29-1
10.4
10.5
10.6
10.7
7
1
. 1
Provide five (5) copies of a final close-out report that coalesces individual Site reports to the
Commission's Representative summarizing the then current status of all
measures/indicators listed and used in paragraph 10.4 below and an electronic copy
of
all
records made during the construction period.
The Contractor shall design and establish a plan to address erosion and sediment control
and monitoring on Site and on adjacent streets, for each construction Site associated with
this Contract that reflects the Contractor's means and methods of construction. These shall
be
consistent with and based on the details shown on the on the following Drawings:
Contract A29-1: Drawing No. A29-1 C5102 and C5504 Erosion and Sediment Control plan
and details
Where changes in construction staging, methods and/or the arrangement
of
construction
Site(s) occur that change or modify the Contract details, a revised ESC Plan shall be
prepared and submitted by the Contractor to the Commission's Representative
for
review
prior to implementation.
The ESC Plan shall include an inspection schedule including times, areas and personnel
responsible. Reports on the inspections shall be included on the daily and weekly El l and
Summary forms and provided to the Commission's Representative for review. The ESC
Plan shall include from among the following ESC control measures and shall identify the
following monitoring trigger levels and alert levels which identify when corrective action
must be taken by the Contractor, as well as the corrective action to be taken under each
condition:
Measures/Indicators
Monitoring
fTrigger Level
Action Level
Heavv Dutv Silt Fence 30 full 50 full
Jersey Barrier with Sil t Fence 30 full 50 full
Staked Sediment Control Log 30
of
height
50
of
height
Truck Wash
As specified by Manufacturer's
As specified by Manufacturer's
0
Mmanual O Mmanual
Mud Mat 50 coverage 75 coverage
Concrete Wash-out Station
30 full
50 full
Inlet Sediment Control Device
15 full
30 full
Sediment Trap
15 full
30 full
Temporary Rock Check
Dam
15 full
30 full
Sediment Control Pond
15 full
30 full
Erosion Control Blanket 85 coverage
<
70 coverage
Mulch
85 o v e r ~ ~ e
< 70 coveraQe
Hydroseed 85 coverage
< 70 coverage
Sediment and erosion control measures shall be inspected and monitored
by
the
Contractor:
On a weekly basis .
.2 After large rainfall events (>20 mm in twenty-four (24) hours)
.3 After significant snowmelt events
.4 Daily during extended rain or snowmelt periods.
-
8/9/2019 01 57 19 - Environmental Controls
21/84
Toronto Transit Commission
CONTRACT A29-1
Section 1
57 1
ENVIRONMENTAL CONTROLS
Page21
5
6
10 8
10 9
10 10
11
11 1
11 2
1
2
3
During inactive construction periods, where the Site is left inactive for thirty {30 days o
longer, a monthly inspection shall be conducted and reported after to the Commission
Representative to ensure that these measures are maintained in proper working order unt
all areas are fully stabilized.
Provide daily reports once a week to the Commission s Representative on l l form
accompanied by required submittal documents.
All damaged erosion and sediment control measures shall be repaired or replaced within
forty-eight (48) hours of the inspection to the satisfaction of the Commission
Representative. Repair and replacement actions and materials will be reported on Ell
and Weekly Summary forms. Repair materials must be maintained on site
for
all installed
ESC measures.
The ESC plan shall also include provisions for monitoring and maintenance to ensure th
ESC measures at each Site are functioning within their established discharge quality and
quantity limits.
Erosion and sediment controls shall be removed or retained at the end of the Contract a
directed by the Commission s Representative. All remaining control materials shall be lef
in good working order and all elements that will be dismantled shall
be
removed from the
Site. Those ESC facilities/elements to be retained will be documented in the final closeou
report and submitted
to
the Commission s Representative.
SURFACE WATER MANAGEMENT PLAN
The Contractor shall design and implement a Surface Water Management
Plan
(SWMP) a
part of the CECMP for each Site and submit to the Commission s Representative fo
review.
The Contractor shall define in the SWMP procedures, monitoring and reporting to
implement mitigation measures that ensure following surface water managemen
objectives:
Protection of local vegetation and surrounding properties from flooding and/or so
saturation (the frequent or prolonged inundation of soil).
Maintained proper Site drainage
Protection of excavations and trenches against flooding and damage
-
8/9/2019 01 57 19 - Environmental Controls
22/84
Section 1 57 19
ENVIRONMENTAL CONTROLS
Page
Toronto Transit Commission
CONTRACT A29 1
11.3 Table 1 reflects the general elements of the SWMP.
Table 1
Monitoring
of
MonitorinQ Frequeno
Parameter
Method
Baseline 1 During Contract
Element
locations
Construction Completion
Surface Water
Total At sources
Grab samples none In accordance none
Quality
suspended across the
with analytic with the
solids TSS)
construction testing results discharge
site s).
permit and
after every
20 mm rain
event or major
snowfall.
Dissolved
At sources Field analysed
none
In accordance none
Oxygen DO),
across the
with portable
with the
pH, construction
meter
discharge
conductivity site s).
permit and
after every
20 mm rain
event or major
snowfall.
Surface Water
Temperature
At
sources
Continuous none Continuous none
Temperature
across the
logger, field downloaded
construction analyzed with bi-weekly.
site s)
if
portable meter
discharge is
to the storm
sewers.
Water Quantity
Calculated At each
Continuous flow none Continuous, none
Sewer input for discharge
metre downloaded
storm or
location of bi-weekly,
sanitary construction
reported
site s).
monthly.
11.4 The SWMP shall:
1 Address the means and methods to control Site flooding and soil saturation at all
construction Sites
.2 Shall be executed on a Site by Site basis by the Contractor and reported
in
the daily EIL s),
the Weekly Summary form and on the incident follow-up form for each Site
.3 Shall describe and implement a program that establishes ongoing monitoring,
implementation
of
control methods, establishes discharge trigger and alarm levels and lists
pro-active mitigation to
be
implemented on site
in
accordance with Table 2 below
.4 The Surface Water Management Plan shall include monitoring, control methods, trigger and
alarm levels and pro-active mitigation
in
accordance with Table 2 and as appropriate to
each construction Site and the activities therein, as well as appropriate to the potential for
flooding
at
each construction Site. These methods may include:
1 Frequent on-Site daily visual and odour observations
of
areas
of
collected surface
water for spills and high turbidity levels.
-
8/9/2019 01 57 19 - Environmental Controls
23/84
Toronto Transit
Commission
CONTRACT A29-1
Section 01
57
1
ENVIRONMENTAL
CONTROLS
Page
23
Table 2
-
1
Baseline:
No
on
site
flooding
SurfaceWater Ri.moft'
Management
(
Monitor:
surf
ace
water runoff
for
spills
and
turbidity,.met
eo ro logical co nd
it ons, o n site
flooding
and
the surf
ace
water runoff collection system(s)
I
1 1 1 1 1
Trigger:
Trigger: Observed
Alarm:
2dmrnl24 hr rain
Baseline:
Alarm: Spill
or
areas
of pooled
On-site
fall event (pre ,
No
evidence
deleterious substance
surface water or
flooding
during
and
post
of spill
is
presentwithin
aturated soils
event) , thav.
surface w ~ e r runoff
I
event
1 l
Action: Employ
r
Action: Inspect
'
Action: Employ Spill
Contingency .Plan for
surface drainage
Canting encyPian
Severe
Weather
and
collection system(s)
measures
inspect surface water
prior to, during and
drainage system(s),
postrain event
to
increase
monitoring
ensure
proper
frequencl
function,
ensure
filter
/settling components
'
are
in good function to
Action:
I+
reduce
turbidity levels
Implement
Action:
Inspect surface '
prior
to
entry into
the
proactive
Action:Take
all
storm sewer, ensure
mitigative
'
water
drainage
system(s), take all
necessary actions to
sediment and erosion
measures for
ensure surf
ace
water
controls
are in
good
spills
necessary
steps to
drainage
system(s)
is
'
function
1
nsure·
the surface water
runoff
drainage
system s
functioning properly
functioning property,
I
ncrease
monitoring
frequency
.2
Frequent daily visual observations for flooding
or
areas of surface
water
run-o
collection on Site .
.3 Frequent daily inspection of the surface water drainage collection system(s) to ensur
proper maintenance and function as provided in the design specifications .
4
Daily monitoring
of
Environment Canada weather forecast to anticipate
and
plan
fo
rain and thaw events
.5 Identify personnel by name, responsible for ensuring that the work Site (s) shall b
maintained at all times, such that materials are contained during regularly foreseeabl
weather conditions. Additional protocols must be identified for implementation if greate
than a one-in ten (1 in 10)
or
one-in-one hundred years storm is forecasted .
.6 Shall cause to be prepared and filed copies
of
all records which will be maintained
at
eac
Site's construction office for inspection by regulators and the Commission's Representative
including the daily Ells, the Weekly Summary Forms and records
of
each incident or even
that triggers
an
inspection.
-
8/9/2019 01 57 19 - Environmental Controls
24/84
Section 1
57 9
ENVIRONMENTAL CONTROLS
Page24
Toronto Transit Commission
CONTRACT A29 1
.7 Shall cause to report any exceedance of MOE water quality standards/City of Toronto
discharge standards to the Commission s Representative and when required to the MOE.
.8 Describe and cause to be implemented a program whereby site surface water wil l be
sampled, tested
and
monitored for water quality including total oil and grease, Total
Suspended Solids (TSS), general chemistry and total metals (e.g. copper, iron, zinc, and
boron). Samples will be taken consistently from established post treatment discharge
locations as approved in the Contractor obtained City o f Toronto s discharge permit (either
storm or sanitary sewer). monitoring Sites at the same time in-situ (field) water quality
measurements are taken. TSS may not exceed 5 ppm .
.9 All measurements, as well as the date and time of sample collection are to be recorded and
submitted by the Contractor to the Commission s Representative with corresponding
analytical laboratory reports including original signed test results, four additional copies and
an electronic version .
.10 Specify that the Contractor must submit all laboratory results to the Commission s
Representative within twenty-four (24) hours of receipt. An original signed laboratory result
shall be provided. Laboratory results may be appended to the Ells and Weekly Summary
Reports
. Shall include a severe weather element that identifies all appropriate precautions to be
taken by the Contractor to ensure that, in the event
of
severe weather, the integrity
of
each
Site(s) and the safety of the workers will be maintained .
.12 The SWMP shall identify procedures to
be
followed to implement the following surface
water run-off action plan including the listed trigger and alarm levels shown in Table 2
above.
11.5 Baseline stormwater discharge monitoring results shall
be
compiled into a report and five
(5) paper copies and a PDF electronic copy shall be provided to the Commission s
Representative for review within thirty (30) days of Notice to Proceed. The Contractor
is
provided the monitoring reports from design phase work (Refer to Attachment 6).
Contractor shall provide monthly reports throughout the duration of the Contract.
11.6 Final stormwater discharge monitoring results shall be compiled into a report and five (5)
paper copies and a .pdf format electronic copy shall be provided to the Commission s
Representative. The report shall summarize the results throughout construction and a final
set
of
results for the Site shall be submitted prior to final payment.
11.7 The Surface Water Management Plan shall implement and be consistent and compatible
with the surface water handling requirements specified in Drainage of Excavated Areas of
Section
3
23 19.
11.8 The Contractor shall maintain all components of the surface water management system in
good condition and ensure that all sediment and erosion control measures are functioning
as designed. Replacement and repair of all facilities must
be
made no longer than 4 hours
after identification of failure or shortfall.
-
8/9/2019 01 57 19 - Environmental Controls
25/84
Toronto Transit Commission
CONTRACT A29-1
Section 01 57 19
ENVIRONMENTAL CONTROLS
Page 25
11.9 The SWMP shall identify those responsible for ensuring that Work Sites shall be maintained
at all times, such that materials are contained during regularly foreseeable weather
conditions. Additional protocols must be identified for implementation i f greater than one-in
ten
1
in 10) or one-in-one-hundred 1 in 100) years storms are forecast.
12 TERRESTRIAL HABITAT MONITORING PROGRAM
12.1 The Contractor shall define a Terrestrial Habitat monitoring program as
part
of the
Comprehensive Controls and Methods Plan. The Terrestrial Habitat Monitoring Program
(THMP) shall include:
.1 Tree protection and monitoring in accordance with the local by-laws
.2 Vegetation protection in accordance with Ontario Ministry
of
Natural Resource s (MNR
provisions for the Species at Risk Act (SARA) listed species as applicable
.3 Wildlife protection
in
accordance with MBCA (Migratory Bird Convention Act)
.4 Reporting by the Environmental Manager in accordance with the reporting format as
specified herein .
.5 The Terrestrial Habitat Monitoring plan shall include the following baseline, threshold and
remediation levels:
Parameter Baseline
Threshold
Remediation
Terrestrial Health
Precondition Survey
Deficiencies
in tree
Repair or replace
protection materials
immediately
Preconstruction Nests (tree or ground)
Bird Nests
Survey
located within Immediate Repair
construction site
Tree Protection
Preconstruction Damage to or Failure
Immediate Repair
Survey
of protection
12.2 Establish tree protection plan(s) to implement City By-laws at all construction
Sites
. 1 The Contractor shall establish a tree protection plan in accordance with Section 3 01
91
.
.2 Provide monitoring by a certified arborist twice (2) annually during the growing seasons and
periodically year-round for the duration of dewatering and recovery to ensure that they are
functioning as designed .
.3 Address methods to correct deficiencies
.4 Report and repair deficiencies within twenty-four (24) hours of identification.
-
8/9/2019 01 57 19 - Environmental Controls
26/84
Section
01
57 19
ENVIRONMENTAL CONTROLS
Page 6
Toronto
Transit Commission
CONTRACT
A29 1
5
Specifically prohibit the following activities within Tree Protection Zones (TPZ)
.1 Construction activities .
.2 Altering of grade by adding fill, excavating, trenching, scraping, dumping, or
disturbances of any kind .
.3 Storage
of
construction materials, equipment, soil, construction waste,
or
debris
.4 Disposal of any liquids (e.g. concrete wash-out, gas, oil, etc.)
.5 Movement of vehicles and machinery.
12.3 If temporary stock piling of materials is to be located near a TPZ, appropriate measures, as
determined by a certified arborist, shall be installed to ensure no material enters the TPZ.
12.4 Establish a Wildlife Protection Monitoring plan to implement the Migratory Bird protections.
12.5 The Contractor
shall establish a mitigation and monitoring plan to implement construction
timing restrictions to avoid nesting/breeding periods for wildlife, including migratory birds.
As a result, wildlife habitat shall not be removed, from April1 to July
31
annually, where
possible.
12.6 If construction occurs at any Site between March 15 and July 31, the Contractor shall use a
qualified avian biologist to conduct a survey for migratory bird nesting sites.
12.7 Inspection results shall be recorded and shall include photos
of
any nests identified during
the inspection with locations of nests shown on a Project Site plan.
12.8 If an active nest is found during the breeding season, the Contractor shall immediately
notify the Commission s Representative and shall not disturb
nor
conduct Work that may
adversely impact the active nests.
12.9 If an active nest is found, the Contractor shall do the following:
1
The Contractor s avian biologist shall prepare a Site-specific mitigation plan in consultation
with the Commission s Representative. The Commission s Representative will contact the
Canadian Wildlife Service (CWS) to review and approve the Site-specific mitigation plan .
.2 Prior to vegetation clearing, wildlife capture/relocation and dispersal techniques shall be
used to protect wildlife from physical harm
in
accordance with the CWS approved
Site-specific mitigation plan .
.3 Establish procedures to ensure that vegetation with active nests and areas adjacent to the
nest cannot be disturbed until the young have fledged.
12.10 Where there are no active nests, vegetation clearing can occur within three (3) calendar
days of the survey, between March 15th and July 31st breeding period. For clearing activity
to occur outside of the three {3) calendar day window, the survey must be repeated.
12 11
The Contractor shall be responsible for the implementation of any Site-specific mitigation
plan approved by the CWS for the identified nesting site.
-
8/9/2019 01 57 19 - Environmental Controls
27/84
Toronto Transit Commission
CONTRACT A29-1
12.12 Reporting and Records:
Section 01 57 9
ENVIRONMENTAL
CONTROLS
Page27
.1
The Contractor shall provide a monthly report during nesting season of all
surveys
and
findings of nesting birds and wildlife recorded at the Site
.2 The Contractor shall maintain a copy of the Terrestrial Habitat Monitoring Plan,
l l
reports
any mitigation plans prepared and all monitoring reports and records on Site for review b
Federal and/or Provincial regulatory enforcement personnel .
.3 The Contractor shall maintain a copy
of
any CWS mitigation plans on Site
and make
them
available to the public upon request.
12.13 Vegetation Protection
and
Predator Protection Plans:
12.14 Landscape Contract Drawings identify additional plant materials to be protected
Contractor shall install protections prior to on-Site activities, in accordance with the Contrac
Documents,
and
shall inspect and maintain such protections as shown on the Contrac
Drawings. ·
12.15 Tree replacements and re-vegetation must be
in
accordance with requirements specified in
the Contract Documents.
12.16 The construction Site is located within the regulation area for both the Emerald Ash Bore
and the Asian long-Horned Beetle. Vegetation Removal shall be
in
accordance with
Canadian Food Inspection Agency (CFIA) requirements which include:
12.17 All trees being monitored have a numbered metal tag affixed to the tree with a staple. An
of these tagged trees that require removal must have CFIA inspect them prior to removal.
.1
All removed federal tags from removed trees must be returned to CFIA.
13 DISCOVERY OF UNEXPECTED CONTAMINATION
13.1 If unexpected contaminated materials are encountered, the Contractor shall immediatel
stop work in the affected area, inform the Commission s Representative
and
proceed in
accordance with the Commission Representative s direction.
14 SOILS MANAGEMENT PLAN
14.1
Soils management at each construction Site shall be conducted in accordance with the
relevant Sections of this Specification, including Sections 02 61 00 and 31 23 15, as
applicable.
14.2 The Contractor shall prepare a Soils Management Plan which implements the
recommendations of the applicable Soil and Ground Water Management Strategy. The
Contractor shall set out sampling and testing procedures for management
of
excavated soi
according to all applicable regulatory requirements.
-
8/9/2019 01 57 19 - Environmental Controls
28/84
Section 01 57 19
ENVIRONMENTAL CONTROLS
Page28
Toronto Transit Commission
CONTRACT
A29 1
14.3 The Contractor shall submit a proposed protocol to the Commission s Representative
where soils confirmed to be contaminated are to be segregated on Site to allow for further
testing by the Contractor. Contractor shall follow protocols for collection
of
samples, their
testing and methods of handling in accordance with those set forth in Section 02 61 00 of
this Contract, as applicable.
14.4 For soils, which do not meet all of the MOE standards, handling and disposal requirements
shall be determined based on thorough soil sample extraction and chemical analysis
by
the
Contractor. Analytical results shall
be
evaluated and compared with the applicable generic
standards, as provided in
Soil, Groundwater and Sediment Standards for Use under Part
XV.1 of the Environmental Protection Act (EPA) (dated March
9
2004). The standards are
referenced in Ontario Regulation 153/04 (the Record
of
Site Condition Regulation),
0.
Reg. 153/04 as amended by
0.
Reg. 266/08) under the EPA.
14.5 Prior to construction, the Commission will require the Contractor to submit the names,
locations and types of licences, as issued by the MOE, of the designated soil disposal sites.
15 DESIGNATED SUBSTANCES
15.1 The Occupational Health and Safety Act (OHSA) imposes a duty on the Owner
(Commission) to inform the Contractor
of
any designated substances present
at
the Work
Site, where it is reasonable for the Commission to have known about the substance.
15.2 There are currently eleven (11) substances designated. They are subject to special
regulations under OHSA:
.1
Asbestos
.2 Lead .
.3 Ethylene oxide
.4 Mercury
.5 Silica (free crystalline silica)
.6 Vinyl chloride monomer (not PVC)
.7 Benzene
.8 Arsenic
.9
Coke oven emissions
. 10 Acrylonitrile .
.
11
lsocyanates.
-
8/9/2019 01 57 19 - Environmental Controls
29/84
Toronto Transit Commission
CONTRACT A29-1
15.3 Asbestos:
Section 01 57
19
ENVIRONMENTAL CONTROLS
Page 9
.1
Notify the Commission's Representative immediately if any material suspected
to
be
asbestos-containing material is discovered during demolition/construction
.2 Cease work in the area
and
barricade the area to prevent entry until such time as th
Commission's Representative confirms the presence or non-presence of asbestos
.3 Comply with all provisions of the Occupational Health and Safety Act and the Regulations
Respecting Asbestos on Construction Projects and in Buildings and Repair
Operations .
15.4 Man-Made Mineral Fibre:
.1 Comply with Synthetic Vitreous Fibres Guidelines for Construction , Construction Safet
Association of Ontario Document DS036.
15.5 Designated substances, other hazardous materials and PCBs survey report.
15.6 In accordance with the requirements
of
the Ontario Occupational Health and Safety Act, no
reports of Designated Substances for Contract A37
1
have been prepared.
16 POLYCHLORINATED BIPHENYLS (PCBS)
16.1 Conform to the EPA and Regulations made thereunder, Ontario Regulation as amended.
16.2 In the event of unexpected discovery of PCBs immediately notify Commission'
Representative orally and in writing and do not handle, disturb nor remove items containing
PCBs. Commission's Representative will authorize remedial work, if any, in writing.
17 ENVIRONMENTAL CONTROLS AND CONTINGENCY PLAN FOR
CLEAN UP
OF
SPILLS
17.1 A spill is defined in the Ontario Environmental Protection Act as a discharge into the
natural environment, from or out
of
a structure, vehicle or other container, that
is
abnorma
in quality or quantity in light of all the circumstances of the discharge .
17.2 The Contractor is solely responsible and liable for, without being limited to, all testing
documentation, clean up reporting, repairs, removal, damages and associated costs an
any other actions arising from a spill.
.1 Provide, at each Site, a Spill Response Kit for use by any Site personnel including, but no
limited to, Subcontractors and Commission's Representative(s). The Spill Response Kit
shall contain materials and equipment capable of containing and disposing
any
spill tha
may occur during the course of this Contract.
.2
Provide all equipment specific for controlling spills directly into Black Creek Creek and
tributaries at thel construction Site(s}, or into stormwater management facilities that drain
into these creeks.
-
8/9/2019 01 57 19 - Environmental Controls
30/84
Section 1 57 19
ENVIRONMENTAL CONTROLS
Page3
Toronto Transit Commission
CONTRACT A29 1
.3 Contingency plans shall include, but not
be
limited to, provisions for spills of hazardous and
unknown materials (i.e. puncturing an unmarked drain during excavation)
4 o prevent spills during construction re-fuelling the Contractor shall:
.1 Not permit refuelling within 30 m of a watercourse or catchbasin .
.2 Have Emergency Response Plan in place before construction commences.
17.3
In
event of a spill, the Contractor shall at its own expense:
.1 Immediately report the spill to the MOE Spills Action Centre
.2 Immediately report the spill to the municipality within boundaries ofwhich the spill occurred
.3 Immediately communicate the details to the Commission s Representative. Report on the
type
of
spill, the quantity
of
the material spilled, the exact location of the spill and whether or
not the contaminant has entered any drain, or water course,
or
if the spill has occurred on
unpaved ground. Advise if any contaminant has entered a sewer line, floor drain, or has
affected any unpaved ground .
4
Contain the spill in a safe manner
.5 Proceed to clean up the spill
in
accordance with the applicable regulations.
17.4 The Contractor shall prepare and submit in accordance with Article 3 Site specific Spill
Prevention and Contingency Plan( s) for the avoidance, control and clean-up of spills in
accordance with 0 Reg. 224/07 and to meet the requirements of O.Reg 675/98 and other
applicable regulations. The Contractor shall
be
responsible for preparing, implementing,
directing and supervising the contingency plan(s). Submit for the Commission s
Representative s review five (5) copies of the Spills Prevention and Contingency Cleanup
Plan and make appropriate changes as requested. The plan shall include as a minimum:
.1 Names and telephone numbers of persons
in
local municipalities and MOE to be notified
immediately of a reportable spill
.2 Names and telephone numbers
of
representatives
of
fire, police and health departments
of
local municipalities who are responsible to respond to emergency situations
.3 Names and telephone numbers
of
companies experienced in control and clean-up
of
hazardous materials that will
be
called
in
an emergency involving a spill.
.4 A Site plan for each construction Site that identifies: Pre-designated safe and secure
Product storage areas at the materials staging areas; set-backs from any nearby
watercourses, drainage ditches and catchbasins and the creek that each drains into;
refuelling and equipment maintenance areas; diesel fuels and above ground storage tanks;
and compressed gas cylinder storage.
-
8/9/2019 01 57 19 - Environmental Controls
31/84
Toronto Transit Commission
CONTRACT A29-1
Section
01 57
ENVIRONMENTAL CONTROLS
Page 31
5 Shall require daily and weekly inspection of active and inactive storage areas
and
report th
results in the
Ell
and Weekly Summary Log .
.6 Procedures for monitoring and inspection to limit or reduce the potential for spills.
17.5 Contingency plans shall include, but not be limited to, provisions for spills of hazardous an
unknown materials (i.e. puncturing an unmarked drain during excavation). The contingenc
plan shall include:
1
Proposal for immediate containment and control of spill, clean up procedures to be initiate
immediately and any other action to be taken to mitigate potential environmental damag
while awaiting additional assistance
.2 Be responsible for preparing, implementing, directing and supervising the contingency plan
17.6 Spill prevention training for each Site shall be documented and included in the ETAP. A
personnel, including Contractor, Subcontractors and Commission s Representat ives sha
be trained in the procedures for all construction Sites which each may access during th
construction.
END OF SECTION
-
8/9/2019 01 57 19 - Environmental Controls
32/84
-
8/9/2019 01 57 19 - Environmental Controls
33/84
Toronto Transit
Commission
CONTRACT A29-1
Section 1
5719
ENVIRONMENTAL CONTROLS
ATTACHMENT 1: ENVIRONMENTAL INSPECTION LOG
Environmental Inspection Log - Contract A29-1
Site Location:
Date D/MIY):
Time 24hrs
:
Weather Conditions:
Construction Status:
Inspection Log Completed by printed name and signature):
CHECKLIST ITEM: ACCEPTABLE
1
NOT ACCEPTABLE
1
* NOT APPLICABLE
1.
Sediment Control Structures
Heavy Duty Sil t Fences IJ
c
c
Jersey Barriers with Silt Fence IJ
c c
Staked Sediment Control Logs IJ
IJ
c
Truck Wash IJ
c c
Mud Mat
c IJ c
Concrete Wash-Out Station
c
c c
Storm Drain Inlet Protection
IJ c c
Sediment Traps
c c c
Temporary Rock Flow Check Dams
IJ c c
Other
c
c c
2.
Stabilization Areas
Erosion Control Blankets
c
IJ c
Mulch
c c c
Hydroseed IJ c c
3.
General Noise Control Measures IJ c c
4.
General Air Quality Control Measures IJ
c c
8
Dewatering
Discharge Quality
c c c
Discharge Filters/Treatment System IJ
c c
Groundwater Level excavations)
c
c
c
Groundwater Level ecological) IJ c
c
9. Environmental Monitoring Activities
Soil Quality
IJ c c
Dryness Level of Spoils
IJ
c c
Surface Water IJ
c c
Aquatic Environment
c c
c
-
8/9/2019 01 57 19 - Environmental Controls