001 Rapidan Spillway SDR 06.01.201601+-+SDR.pdf · Contains Critical Energy Infrastructure...
Transcript of 001 Rapidan Spillway SDR 06.01.201601+-+SDR.pdf · Contains Critical Energy Infrastructure...
Contains Critical Energy Infrastructure Information - Do Not Release -
SUPPORTING DESIGN REPORT
SPILLWAY MODIFICATIONS
RAPIDAN HYDROELECTRIC PROJECT (FERC NO. 3071-MN)
Prepared for:
Blue Earth County Licensee:
Eagle Creek Renewable Energy, LLC Neshkoro, Wisconsin
Prepared by:
Fitchburg, Wisconsin www.KleinschmidtGroup.com
June 2016
Contains Critical Energy Infrastructure Information - Do Not Release -
SUPPORTING DESIGN REPORT
SPILLWAY MODIFICATIONS
RAPIDAN HYDROELECTRIC PROJECT (FERC NO. 3071-MN)
Prepared for: Blue Earth County
Licensee:
Eagle Creek Renewable Energy, LLC Neshkoro, Wisconsin
Prepared by:
Fitchburg, Wisconsin www.KleinschmidtGroup.com
June 2016
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - i -
SUPPORTING DESIGN REPORT
SPILLWAY MODIFICATIONS RAPIDAN HYDROELECTRIC PROJECT
FERC NO. 3071-MN
TABLE OF CONTENTS
1.0 INTRODUCTION ...............................................................................................................1
2.0 DESCRIPTION OF PROJECT............................................................................................2 2.1 EXISTING PROJECT DESCRIPTION ..............................................................................2 2.2 MAIN DAM ................................................................................................................2 2.3 SPILLWAY .................................................................................................................2 2.4 POWERHOUSE ...........................................................................................................3 2.5 HISTORY OF DOWNSTREAM SCOUR ..........................................................................3 2.6 PROPOSED PROJECT MODIFICATIONS ........................................................................4
2.6.1 NEEDLE BAYS ...............................................................................................4 2.6.2 TAINTER GATES ............................................................................................4 2.6.3 LOWER APRON ..............................................................................................5
2.7 OPERATIONAL PROCEDURES .....................................................................................5
3.0 HYDROLOGY AND HYDRAULIC ANALYSIS .............................................................6 3.1 SPILLWAY CAPACITY ................................................................................................6 3.2 SPILLWAY TAINTER GATE OPENING .........................................................................8 3.3 ENERGY DISSIPATION - TAILWATER .......................................................................10
4.0 SPILLWAY MODIFICATIONS .......................................................................................11 4.1 NEEDLE BAY MODIFICATIONS ................................................................................11 4.2 TAINTER GATE HOIST SYSTEM DESIGN ..................................................................11
4.2.1 PROPOSED GATE OPERATION ......................................................................12 4.2.2 METHOD OF ANALYSIS ...............................................................................12
4.3 SPILLWAY NAPPE AERATION ..................................................................................13
5.0 LOWER APRON REPAIRS .............................................................................................15 5.1 APRON REPAIR ........................................................................................................15 5.2 RIGHT ABUTMENT REPAIR ......................................................................................15
6.0 REFERENCES ..................................................................................................................16
Contains Critical Energy Infrastructure Information - Do Not Release -
TABLE OF CONTENTS (CONT.)
JUNE 2016 - ii -
LIST OF FIGURES
FIGURE 1 USACE UPSTREAM NAPPE DIAGRAM ......................................................................9
FIGURE 2 APPROXIMATE NAPPE OVER SPILLWAY ..................................................................10
LIST OF APPENDICES
APPENDIX A PROPOSED MODIFICATION DRAWINGS APPENDIX B HOIST SYSTEM DESIGN TABLE AND DIAGRAM J:\1871\043\Docs\SDR\Spillway\001 Rapidan Spillway SDR_06.01.2016.docx
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 1 -
SUPPORTING DESIGN REPORT
SPILLWAY MODIFICATIONS RAPIDAN HYDROELECTRIC PROJECT
FERC NO. 3071-MN
1.0 INTRODUCTION
This Supporting Design Report (SDR) provides information on the design of the proposed
spillway modification to address spillway capacity and downstream apron scour repair at the
Rapidan Hydroelectric Project (FERC No. 3071-MN). The modifications were performed in
response to the Independent Consultant’s recommendation in the Part 12D Consultant’s Safety
Inspection Report, submitted on January 6, 2015, to FERC. Additionally, this SDR addresses
comments provided from FERC letter dated November 25, 2015, regarding the spillway
modification and apron repair.
All vertical elevations are in 1929 National Geodetic Vertical Datum (NGVD29, also known as
USGS datum), unless noted otherwise. To convert from NGVD29 to Plant Datum, subtract
713.1 feet from NGVD29. Directions along the river (left and right) reference a viewer looking
downstream. All units of measure are in English units. No horizontal datum is referenced in this
study.
This report was prepared under the direction of the undersigned, the Independent Consultant for
the Second Part 12D Consultant Safety Inspection of the Rapidan Hydroelectric Project.
Sincerely, KLEINSCHMIDT ASSOCIATES
Kim A. Hansen, P.E. Project Manager
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 2 -
2.0 DESCRIPTION OF PROJECT
The Rapidan Hydroelectric Project is located on the Blue Earth River south of Mankato,
Minnesota. The Rapidan Dam is classified as having a significant downstream hazard potential.
The hazard rating is based on the environmental damage that would be caused by an
uncontrolled release of the agriculturally impacted sediments that fill the reservoir. The
inundation areas downstream of the dam have no permanent inhabited structures, but there is a
park located downstream of the dam which attracts hikers and fishermen. The park has primitive
camp sites and a canoe launch.
2.1 EXISTING PROJECT DESCRIPTION
From left to right looking downstream, the project consists of a left abutment with a 115-foot-
long core wall, a 54-foot-long non-overflow section, a 92-foot-long integral intake and
powerhouse, a steel radial-gated 180-foot-long spillway section, a timber needle-gated 72-foot-
long spillway section, a 58-foot non-overflow section with an upstream wall extending about
18 feet into the right abutment. The dam is an Ambursen dam, designed and constructed by the
Ambursen Hydraulic Co., Boston, Massachusetts, in 1910 with an overall length of
approximately 475 feet (as measured from the ends of the upstream wall excluding the left
abutment cutoff wall). The spillway section has an upstream face slope of 1H:1V and a
downstream face slope of 7H:12V). There are four 5-foot-high by 7-foot-wide steel sluice-gates
at the toe of the upstream face of the dam in bays 9 through 12 of the Ambursen Dam. The low
level sluice gates have not been used during recent history. The dam and powerhouse are
founded on the Jordan sandstone, which has sub-units which are easily erodible.
2.2 MAIN DAM
There are no embankments at the Rapidan Dam. The dam is keyed into bedrock with concrete
abutments.
2.3 SPILLWAY
The spillway section of the dam is founded on the Jordan Sandstone formation. The spillway is a
buttress and slab Ambursen dam, consisting of 15 buttresses and 14 bays. The buttresses are
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 3 -
spaced 18 feet on center. Gate piers are located over every other buttress creating seven 33-foot-
wide gate bay openings. The dam is furnished with five 33-foot-wide by 10-foot-high Tainter
gates, and two 33-foot-wide by 7.5-foot-high needle gate sections.
There are four sluice tunnels under the spillway between buttresses 4 through 8 that were
intended to provide a low level outlet for the reservoir. The sluice tunnels have 5-foot-high by 7-
foot-wide cast iron slide gates on the sloping upstream side of the spillway section that were
originally operated with a mechanical hoist in the gallery of the dam. The low level sluice gates
were retired after gate operation problems, which led to the eventual silting of the reservoir.
There is one 36-inch-diameter low flow pipe located in the upper portion of the power house
adjacent to the spillway. The low flow pipe is controlled by a butterfly valve and is used to
discharge low flows that are less than the minimum allowable turbine capacity.
2.4 POWERHOUSE
The powerhouse is located at the left end of the dam. The powerhouse structure is founded on
Jordan Sandstone bedrock and consists of a reinforced concrete structure that is integral with the
spillway. The powerhouse contains two identical horizontal Kaplan generating units, which
together are capable of generating 5.0 megawatt (MW) while passing 1,200 cubic feet per second
(cfs). The powerhouse also has one unused turbine bay and a former exciter bay.
For more information on the project structures and configuration, see Section 2 of the STID
(North American Hydro Holdings, Updated 2014).
2.5 HISTORY OF DOWNSTREAM SCOUR
Blue Earth County, owner of the Rapidan project, notified the United States Army Corps of
Engineers (USACE) of potential failure condition due to large voids found at the spillway toe
below the missing downstream apron in April 2002. Further investigations by USACE
determined that undermining at the toe of the spillway had developed and an emergency repair
was necessary to provide remediation against further undermining and scour downstream of the
toe.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 4 -
The original spillway section included a reinforced concrete apron that extended downstream of
the spillway for scour protection. This concrete apron was damaged which allowed scour and
undermining to occur. Repairs were completed to remediate the missing downstream apron and
fill voids below and under the spillway toe including rock fill and grouting of scour areas.
Dumped rock was used to fill the downstream scour hole and extended upstream under some of
the spillway’s footprint. The remainder of undermining under to the spillway was filled with
grout. Scour areas downstream of the spillway were then capped with a reinforced concrete slab.
2.6 PROPOSED PROJECT MODIFICATIONS
The proposed modification of the spillway include the followings:
Permanently abandoning the needle bays (spillway bays nos. 6 & 7) to avoid discharge flows onto the right abutment;
Replacing the hydraulic capacity by lifting the five Tainter gates (spillway bays nos. 1 through 5) higher to avoid orifice flow;
Repair scour holes in the lower apron slab; and
Provide air supply ventilation hole through Buttress No. 1 for nappe aeration.
Proposed modifications to the Rapidan project is represented in the drawing in Error!
Reference source not found..
2.6.1 NEEDLE BAYS
The existing needle bays current consists of vertical wooden stoplogs supported by a horizontal
steel beam. The vertical needles can be removed during flood events to increase spillway
capacity but discharges onto weak sandstone that is susceptible to erosion. The wooden stoplogs
will be replaced with an additional support beam and reinforced concrete panels to permanently
close the needle bays.
2.6.2 TAINTER GATES
The gate operating system and Tainter gates will be modified to allow the gates to be raised
higher than the existing systems, and bent members repaired. These modifications will consist
of:
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 5 -
1. Relocating the existing lifting pulley;
2. Replacing the existing lifting cable with new longer cable;
3. Relocating the existing gate stop to allow gates to open higher;
4. Installing a new gate resetting rod and portable angle drill devise to reset the gate after full opening; and
5. Repair the bent lower left arm on gate nos. 2 and 5
2.6.3 LOWER APRON
The existing apron repair will consist of; reinforcing the lap joint with grouted dowels, filling the
existing scour with dumped rock, and capping the repair with structurally reinforced concrete
slab.
2.7 OPERATIONAL PROCEDURES
The proposed spillway modifications will change the Tainter gate operational procedures after an
extreme flood events. The proposed modifications will eliminate the need to remove wooden
needle gates from Bays 6 and 7 to safely pass the IDF and an additional step will be required to
close the Tainter gates after an IDF event.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 6 -
3.0 HYDROLOGY AND HYDRAULIC ANALYSIS
3.1 SPILLWAY CAPACITY
The flow capacity of the Rapidan spillway has been estimated and documented in numerous
studies and documents. The St. Paul District of the USACE performed a spillway capacity
analysis as part of the Blue Earth River Ecosystem Restoration Feasibility Study in February,
2009. The hydraulic capacity of the spillway with zero freeboard as presented in the Ecosystem
Restoration Feasibility Study was stated as 41,900 cfs assuming orifice flows or greater than
70,000 cfs assuming weir flow. The Federal Energy Regulatory Commission (FERC)
subsequently accepted 41,900 cfs as the basis for the Inflow Design Flood (IDF) with zero
freeboard (pool level of 881.6 feet, NGVD29).
The flow capacity and the nappe shape for the Rapidan spillway at IDF conditions (flow =
41,900 cfs, headwater at 881.6) were estimated by several methods. The capacity of the spillway
was computed as a free-flowing weir, and the nappe shape was evaluated to determine if free-
flow conditions would occur at the IDF flow.
The first calculation is the net head required to pass 8,400 cfs (total IDF x 0.2) through each
spillway bay. The weir flow was calculated as:
.
Where
C = 3.7
The net width was 33.0 feet minus end contraction loss of 1.35 feet, resulting in W = 31.65
Q = 8,400 cfs
Solving for the required net head is 17.3 feet to pass the target flow, resulting in an energy
gradeline of 881.4 at the crest (spillway sill elevation at 864.1). The upstream head includes the
depth of flow, estimated at 12.6 and a velocity head of 4.7 feet. The velocity head of the
approach flow was estimated on the basis of the effective flow area approaching the spillway.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 7 -
The effective flow width at a point 100 feet upstream of the spillway is assumed to be 377 feet.
This contracts at a 1:1 ratio, to 177 feet wide approaching the spillway piers. The net width at the
piers is 165 feet, with five bays at 33 feet wide.
The calculations indicate that the five Tainter bays can pass the IDF flow of 41,900 cfs with the
pond at zero freeboard level (elevation 881.6 feet NGVD29), with modifications to allow the
Tainter gate to be opened above the nappe. The current configuration allows a maximum gate
opening to elevation 871.6 feet. Modifications to the operator are needed to allow the Tainter
gate to be raised above elevation 874.8 feet, which would allow flows to pass under gate and
maintain weir flow conditions. The new raised elevation only reflects the lip of the skin plate, a
portion of the trunnion arms will remain within the flow path. However the bottom of the Tainter
gate and trunnion arms will be rotated at least eight feet downstream of the spillway crest where
the ogee sharply drops away. This geometry results in only localized increases in the nappe
profile near the trunnions and should not significantly affect spillway capacity. There are no
horizontal cross members between the trunnion arms that would be in the flow path. The
estimated flow nappe elevation under the raised gate location is estimated to be about 874 feet.
The computed drawdown of the nappe profile as it approaches the crest also indicates that no
concrete removal is required from the overhead operating deck or support beams. The proposed
modification is shown in Appendix A along with approximate nappe profile across the spillway
gate.
Existing hoist drum location will remain the same, but the pulley will be repositioned to increase
lift height. The new pulley location will be able to lift the gate farther downstream to provide the
required gate opening. During IDF conditions, the gate will need to be lifted beyond its center of
gravity and the gate travel will pivot onto new gate stops. A supplemental system will be
required to pull the gate upstream and off the gate stop as IDF flood flows recede to reset the
gate. The supplemental system will consist of a hole in the operator’s concrete deck to allow for
an Acme rod to be inserted through the deck and hook onto the open/close gate. Pulling or
pushing on the Acme rod with portable hand drill or a hand wheel will reset the Tainter gate
back upstream and allow the wire rope operator to control lowering the gate.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 8 -
3.2 SPILLWAY TAINTER GATE OPENING
The nappe shape at Rapidan is a function of the ogee shape, at points downstream of the crest.
The estimated upstream nappe has a typical drawdown curve, with additional influence from the
flow contraction at the interface with the piers.
The downstream nappe was estimated by two methods. A supercritical HEC-RAS model was
developed, using the measured ogee geometry. The tabulated values are based on the (0,0)
coordinate at the crest of the ogee, which is approximately the same as the gate lip strike plate
location. Due to the steepness of the ogee spillway, the nappe was also estimated using jet
trajectory computations as described by a USBR/ASCE reference (ASCE, 2008). The equation is
as follows:
2
Where g = 32.2 ft/sec2 and v0 is the horizontal velocity at the spillway crest.
The upstream nappe was derived from guidance from USACE Hydraulic Design Chart 111-23/1.
The definition sketch is shown in Figure 1. Due to the shape of the spillway, this method is not
appropriate for the downstream nappe evaluation. The normalized nappe shape in the HDC is
based on a typical Type 3 pier (rounded) with a standardized horizontal distance from the nose of
the pier to the ogee crest. The standardized coordinate system was adjusted for the Rapidan
spillway configuration by shifting the horizontal coordinates to match the horizontal distance
from the nose of the pier to the spillway crest.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 9 -
FIGURE 1 USACE UPSTREAM NAPPE DIAGRAM
Figure 2 shows the estimated nappe shape for the upstream (dark blue/red) and the downstream
(yellow, purple and light blue) quadrants. As previously stated, due to the non-standard shape of
the ogee, the quadrants were estimated separately. The downstream nappe has been observed to
follow the “free jet” shape as shown by the yellow line, and the computed nappe bottom (light
blue) indicates that there is some degree of nappe separation as the flow progresses over the
ogee.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 10 -
FIGURE 2 APPROXIMATE NAPPE OVER SPILLWAY
3.3 ENERGY DISSIPATION - TAILWATER
Past apron repairs have been successful with the exception of a couple10-foot scour holes
approximately 70 feet downstream of the spillway at sluiceway section. The 50 foot-long upper
apron was constructed in 2003 and has not been modified since installation. Annual bathometric
surveys of the apron have been completed as part of the DSSMP and no damage has occurred to
the upper apron. The lap joint of the two aprons may have accelerated this scour damage and this
joint may need improvement to reduce the possibility of future problems. The scour hole will be
repaired and possibly capped with concrete and drains to relieve potential under seepage flows.
More detailed discussion of apron strengthening and right abutment repair is presented in
subsequent Section 5.
‐30
‐25
‐20
‐15
‐10
‐5
0
5
10
15
20
‐20 ‐10 0 10 20 30
Spillway
Center Nappe
Edge Nappe
CWSEL HEC‐RAS model
Control Points
Upper
Lower
Edge nappe expected to extend slightly below center nappe
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 11 -
4.0 SPILLWAY MODIFICATIONS
4.1 NEEDLE BAY MODIFICATIONS
The needle bays (spillway bays 6 and 7) will be permanently closed by replacing the wooden
needles with concrete panels. Appendix A shows the proposed modification required to support
the concrete panels against IDF loads. The proposed modification will use the existing support
beam and require one additional support beam at lower level to support the concrete panels
during IDF loading conditions. The new support beam will have similar end connections into the
concrete piers using simple double angle shear connections. The concrete panels will be cast in-
place against the upstream face of the bridge deck with overlap to enclose the headpond at flood
levels.
4.2 TAINTER GATE HOIST SYSTEM DESIGN
The Tainter gate hoist systems will be modified to open the gates higher than the existing
systems. This higher lift will allow for greater flow to pass under the gates. The existing hoist
system has two cables, two pulleys, and one drum. Each hoist cable attaches near the bottom at
each side of the Tainter gate. Each cable wraps about its own stationary pulley located above the
Tainter gate on both sides, and anchored to the overlaying concrete deck. The existing lifting
cable pulley will be relocated to allow for higher lift, and a new longer stainless steel cable will
be installed. The existing motors, gearboxes, and drums will be reused. Refer to Appendix A for
hoist system design drawings.
Additionally, a gate resetting rod will be used to rotate the gate in the upstream direction when
the gate’s center of gravity is further downstream than the trunnion pin. The resetting rod will
operate via a ball screw system on top of the deck along with a portable support bracket. When
the gate needs to be flipped back to upstream position, a 3/4" dia. Acme rod (5 ton capacity) will
be inserted through a 5 inch diameter hole from the spillway deck to a new push point on a skin
plate. The rod will be attached with a ball screw and portable drill will be used to push the rod
down, moving the gate upstream. until it can close by gravity, as it does in the current mode of
gate-closing operation.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 12 -
4.2.1 PROPOSED GATE OPERATION
When the inflow is expected to be near IDF, or headwater elevation EL. 881.6, the existing gate
hoist system will lift the center of gravity of the Tainter gate beyond the trunnion pin and flip the
gate in downstream direction, disengaging from existing hoist system. After the headwater
subsides to normal operational level, operator will be equipped with portable resetting Acme rod
that can be placed on to a proposed support system at each spillway bays and reposition the
Tainter gate back in upstream direction to reengage with the existing hoist. Gate operating
sequence is as follows:
To Open
1. Lift gate with hoist to tipping point,
2. Gate tips downstream side to limit of hoist cable travel,
3. Lower gate onto gate stops with hoist.
To Close
1. Lift gate upstream with hoist to limit of slack,
2. Push resetting rod to gate tipping point,
3. Gate tips upstream side to limit of slack,
4. Lower gate onto spillway crest with hoist.
Proposed gate operating position and limit of hoist cable is shown in Appendix B.
4.2.2 METHOD OF ANALYSIS
Analyses was completed to compare the lifting load of the current pulley location to the new
pulley location and then determine the force required to reset the gate after full opening. The
proposed gate operating sequence of operation should not exceed the rated lifting capacity of the
existing motor/gearbox system. The existing motor/geartbox is rated at 22,194 ft-lbs of torque. In
comparison to maximum required load of 7,900 ft-lbs. These analyses are included in Appendix
B.
The initial lifting tension needed from each hoist cable to initiate opening of the gate from its
fully closed position was calculated. It was determined that the increased hoist load from
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 13 -
relocated pulley is negligible. As the orientation of hoist cable remains tangential to the skin
plate. Since the lifting force with the new pulley position is the same as the original load, the
currently operated lifting system can be reused with the addition of a new stainless steel cable
and a new pulley. Forces due to hydrostatic loadings, hydrodynamic loadings, trunnion friction,
sealing friction, ice and weather related loadings, and gravitational effects were all considered in
this analysis for the design gate positions. The rated capacity for each new stainless steel cable
should be rated at 8 tons. The length of each hoist cable required is 26 foot 3/4 inches, and the
diameter of the cable is 3/4 inches. Each relocated pulley was assumed for a 0.5 to 1.0 ft/min line
speed of operation. The new pulley locations will be mounted to the upstream vertical surface of
the concrete support beam using epoxy anchors.
When the gate is at its fully open position, its center of mass will be to the downstream of its
vertical axis and will require a resetting force to reengage the hoist pulley and drum to initiate
closing. The new gate resetting rod will need to have a rated capacity of 1 tons, or less, to reset
the gate. An Acme rod will be used to push the gate for resetting operation. The rod will be
supported by bracket at the deck with pin to allow the rod to rotate as gate moves upstream.
Hydrodynamic forces acting on the gate arms from flowing water were addressed but considered
negligible since the water elevation during operation never rises above the gate’s trunnion.
Additional gate positions were considered for determining the amount of resetting force needed
to reengage the pulley-hoist system and complete gate closing operation. When the gate’s center
of gravity rotates ±1.8 degree from vertical, where the gate is at tipping point, less than 1,000 lbs
of force is required to move the gate.
4.3 SPILLWAY NAPPE AERATION
The quantity of air required for nappe aeration is difficult to quantify. However, there are (4) 3 inch-
diameter nappe aeration holes along the downstream face of each spillway gate that have performed
historically without any signs of distress. The five spillway gates sums up to a total of 2 square-ft of
opening for nappe aeration. The access doorway from the powerhouse into the spillway is
approximately 3.5 ft by 6.5 ft for a total of about 22 square-ft. However, the doorway is equipped with
solid door and lower access portals through powerhouse is at top elevation of 822.2ft which is about
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 14 -
4.8 feet below the estimated IDF tailwater. All other buttresses have additional portals near the top of
the spillway.
The proposed ventilation into the Ambursen spillway through the powerhouse right abutment should
be at least 4 square-ft (twice the area supplied near the crest for nappe aeration) to avoid inducing a
significant pressure reduction within the spillway. There are multiple louvers and dampers to provide
adequate powerhouse ventilation. Proposed location of the vent hole is presented in Appendix A.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 15 -
5.0 LOWER APRON REPAIRS
5.1 APRON REPAIR
The flow characteristics of the downstream tailrace area is characterized by low Froude number
that dissipates over a long distance and traditional stilling basin is not required. The existing
downstream apron has been repaired previously and the latest Underwater Inspection by Ayres
(2015) indicates that the repaired downstream apron is performing adequately, exception of few
sours at the apron lap joint.
The downstream apron was repaired on two separate occasions after the initial April 2002 repair
as funds became available to the Blue Earth County. First apron repair extended approximately
50 feet downstream from the toe of the spillway and second apron repair was placed downstream
of the first apron, extending approximately 115 feet. A lap joint was constructed to connect the
two aprons, and according to the underwater inspection, is where scour was found to be located.
The proposed apron repair will reinforce the lap joint with grouted dowels, filling the existing
scour with dumped rock and capping the repair with structurally reinforced concrete slab. The
repaired condition will provide flush apron surface to mitigate adverse flow characteristics
within the downstream apron. Detailed plan and drawing is presented in Appendix A.
5.2 RIGHT ABUTMENT REPAIR
With no proposed traditional stilling basin in the tailrace, the existing grouted riprap protect at
the right abutment and the right shoreline is considered adequate. Additionally, the needle bays
(spillway bays 6 and 7) directly upstream of the right abutment will be permanently abandoned
and prevent spillway flow from causing erosion to right abutment. Therefore, construction of
additional remediation to the right abutment is not required.
Contains Critical Energy Infrastructure Information - Do Not Release -
JUNE 2016 - 16 -
6.0 REFERENCES
American Concrete Institute (ACI). 2011. Building Code Requirements for Structural Concrete (ACI 318-11).
American Society of Civil Engineers. 2010. Minimum Design Loads for Building and Other Structures (ASCE7-10).
Ayres Associates. 2015. Underwater Inspection Rapidan Hydroelectric Project. September.
Blue Earth County, MN. Apron Repair Project After Action Report, 2003.
Department of Defense (DoD), 2014, Unified Facilities Criteria Program, Unified Facilities Guide Specifications (UGFS). Updated May 9, Uploaded May 20. <http://www.wbdg.org/ccb/browse_cat.php?c=3>
Federal Energy Regulatory Commission (FERC). 2010. Engineering Guidelines for the Evaluation of Hydropower Projects, Chapter 3: Gravity Dams and Chapter 10: Other Dams. 1997.
Kleinschmidt Associates. 2014. Second Safety Inspection Report Rapidan Hydroelectric Project. December.
Naval Facilities Engineering Command (NAVFAC). 1986. Design Manual 7.02. September.
North American Hydro Holdings. 2010. Supporting Technical Information Document (STID) Rapidan Hydroelectric Project. Revised April, 2014.
U.S. Army Corps of Engineers (USACE). Emergency Repairs, 2002.
U.S. Army Corps of Engineers (USACE). Rapidan Dam Investigations, September 2009.
Contains Critical Energy Infrastructure Information - Do Not Release -
APPENDIX A
PROPOSED MODIFICATION DRAWINGS
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871-043_C
-C
over S
heet.dw
gM
ay. 1
9, 2
01
6 - 1
0:2
7 A
M
100% REVIEW
NOT FOR
CONSTRUCTION
06-01-16
EAGLE CREEK RENEWABLE ENERGY, LLC
NESHKORO, WISCONSIN
FERC NO. 3071-MN
RAPIDAN HYDROELECTRIC PROJECT
SPILLWAY IMPROVEMENTS
DRAWING LIST
LOCATION MAP
VICINITY MAP
SITE PLAN
1:250
(SEE NO. 2 IN TABLE)
(SEE NO. 1 IN TABLE)
SCOPE OF WORK:
STRUCTURAL NOTES
GENERAL NOTES
1871-043
EAGLE CREEK RENEWABLE ENERGY, LLC
NESHKORO, WI
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871-043_S
P-1 T
HR
U S
P-3.dw
g
Drawing
No.
Ma
y. 2
7, 2
01
6 - 2
:3
1 P
M
22x34 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
JDS JHL-
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
GENERAL NOTES
AND SITE PLAN
SP-3
A
2
4
4
4
2
2
4
05-27-16
06-01-16100% REVIEW
NOT FOR CONSTRUCTION
100% REVIEW
STAGING PLAN
1"= 50'-0"
HAY BALE EMBEDDING DETAIL
TYPICAL STRAW OR HAY BALE DIKE
SILT FENCE DETAIL
N.T.S.
N.T.S.
JOINING FENCE SECTION
TURBIDITY CURTAIN DETAIL
N.T.S.
1871-043 05-13-16
EAGLE CREEK RENEWABLE ENERGY, LLC
NESHKORO, WI
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871-043_S
P-1 T
HR
U S
P-3.dw
g
Drawing
No.
Ma
y. 1
9, 2
01
6 - 2
:2
7 P
M
22x34 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
-
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
EROSION CONTROL
AND STAGING PLAN
SOIL & EROSION CONTROL NOTES:
JDS JHL06-01-16100% REVIEW
NOT FOR CONSTRUCTION
100% REVIEW
A
3/32"= 1'-0"
TYP. SLUICEWAY SECTION (SPILLWAY NO. 3 & 4)
SP-1
3/16"= 1'-0"
APRON LAP JOINT REPAIR DETAIL
1
1/2"= 1'-0"
SCOUR REPAIR DETAIL
2
1871-043 05-13-16
EAGLE CREEK RENEWABLE ENERGY, LLC
NESHKORO, WI
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871-043_S
P-1 T
HR
U S
P-3.dw
g
Drawing
No.
Ma
y. 1
9, 2
01
6 - 2
:2
7 P
M
22x34 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
-
NOT FOR CONSTRUCTION
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
SPILLWAY SECTION AND DETAIL
JDS JHL06-01-16100% REVIEW
100% REVIEW
BUTTRESS 1 SECTION
1/8"= 1'-0"
POWERHOUSE PLAN
1/8"= 1'-0"
1871-043
EAGLE CREEK RENEWABLE ENERGY, LLC
NESHKORO, WI
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871-043_S
P-4.dw
g
Drawing
No.
Ma
y. 1
9, 2
01
6 - 2
:3
0 P
M
22x34 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
-
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
PROPOSED NAPPE VENTILATION
ON BUTTRESS 1
JDS JHL
05-13-16
06-01-16100% REVIEW
NOT FOR CONSTRUCTION
100% REVIEW
B
3
3"= 1'-0"
BASE PLATE ANCHOR DETAIL
C
1 1/2"= 1'-0"
BASE PLATE CONNECTION DETAIL
C
DOUBLE ANGLE CONNECTION SECTION
3"= 1'-0"
D
PROPOSED NEEDLE BAY PLAN VIEW (SPILLWAY NO. 6 & 7)
1/2"= 1'-0"
3
1871-043 05-13-16
EAGLE CREEK RENEWABLE ENERGY, LLC
NESHKORO, WI
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871-043_S
-1.dw
g
Drawing
No.
Ma
y. 1
9, 2
01
6 - 2
:2
4 P
M
22x34 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
06-01-16 JDS JHL- 100% REVIEW
NOT FOR CONSTRUCTION
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
PROPOSED NEEDLE BAY
MODIFICATIONS
NEEDLE BAY ELEVATION
1/8"= 1'-0"
PROPOSED NEEDLE BAY SECTION ( SPILLWAY NO. 6 & 7)
1/4"= 1'-0"
EXISTING NEEDLE BAY SECTION (SPILLWAY NO. 6 & 7)
1/4"= 1'-0"
B B
100% REVIEW
3/8"= 1'-0"
RELOCATED PULLEY AND HOIST LIMIT OF LIFT
3/8"= 1'-0"
RELOCATED LIFTING PULLEY
3/8"= 1'-0"
NEW GATE RESETTING CABLE AT GATE CENTER
A
SK-2
B
SK-2
C
SK-2
D-D
1 1/2"= 1'-0"
VIEW
1-1/2"= 1'-0"
STRIP PLATE DETAIL
1-1/2"= 1'-0"
PULLEY DETAIL
D-D
1871043
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871043 sht S
K-1.dw
g
Drawing
No.
Ma
y. 2
7, 2
01
6 - 2
:2
9 P
M
22x34 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
-
PROPOSED
GATE LIFTING AND RESETTING SYSTEM
EAGLE CREEK RENEWABLE ENERGY, LLC.
NESHKORO, WI
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
JDS JHL
05-27-16
NOT FOR CONSTRUCTION
06-01-16100% REVIEW
100% REVIEW
PLAN AT EL. 881.0'±
3/16"= 1'-0"
A CB
SK-1 SK-1 SK-1
1-1/2"= 1'-0"
STEEL CABLE RUB GUARD DETAIL
3"= 1'-0"
GATE STOPPER DETAIL
3"= 1'-0"
GATE STOPPER PROFILE
SUPPORT BRACKET PLAN VIEW
3"= 1'-0"
D
RESETTING POCKET DETAIL
3"= 1'-0"
E
D
SECTION
3"= 1'-0"
E
SECTION
3"= 1'-0"
-
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871043 sht S
K-2.dw
g
Drawing
No.
Ma
y. 2
7, 2
01
6 - 2
:2
6 P
M
22x34 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
NOT FOR CONSTRUCTION
1871043 05-27-16
PROPOSED GATE RESETTING SYSTEM
EAGLE CREEK RENEWABLE ENERGY, LLC.
NESHKORO, WI
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
06-01-16 JDS JHL100% REVIEW
COVER PLATE DETAIL
1"= 1'-0"
RESETTING ROD DETAIL
1"= 1'-0"
100% REVIEW
TAINTER GATE PLAN VIEW
1/4"= 1'-0"
F
F
SECTION
1/2"= 1'-0"
1871043
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871043 sht S
K-3.dw
g
Drawing
No.
Ma
y. 1
9, 2
01
6 - 2
:2
3 P
M
22x34 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
-
TAINTER GATE #2 AND #5
LOWER ARM MEMBERS REPAIR
EAGLE CREEK RENEWABLE ENERGY, LLC.
NESHKORO, WI
2014 FIELD PHOTO BY KLEINSCHMIDT
NTS
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
JDS JHL
05-13-16
NOT FOR CONSTRUCTION
06-01-16100% DRAFT PLANS
100% REVIEW
Contains Critical Energy Infrastructure Information - Do Not Release -
APPENDIX B
HOIST SYSTEM DESIGN TABLE AND DIAGRAM
3/8"= 1'-0"
POSITION 1: GATE CLOSED
3/8"= 1'-0"
POSITION 2: GATE AT TIPPING POINT
1871043 12-18-15
- - -
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871043 sht gate closures.dw
g
Drawing
No.
Ja
n. 6
, 2
01
6 - 1
1:0
9 A
M
22
x3
4 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
Dwg No. Reference Drawing Title
Date
- - -- -
PRELIMINARY
NOT FOR
CONSTRUCTION
PROPOSED
GATE LIFTING AND RESETTING SYSTEM
EAGLE CREEK RENEWABLE ENERGY, LLC.
NESHKORO, WI
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
3/8"= 1'-0"
POSITION 3: GATE OPENED
1871043 12-18-15
- - -
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871043 sht gate closures.dw
g
Drawing
No.
Ja
n. 6
, 2
01
6 - 1
1:1
1 A
M
22
x3
4 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
Dwg No. Reference Drawing Title
Date
- - -- -
PRELIMINARY
NOT FOR
CONSTRUCTION
PROPOSED
GATE LIFTING AND RESETTING SYSTEM
EAGLE CREEK RENEWABLE ENERGY, LLC.
NESHKORO, WI
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
3/8"= 1'-0"
POSITION 2: GATE AT VERTICAL
3/8"= 1'-0"
POSITION 1: GATE FULLY CLOSED
3/8"= 1'-0"
POSITION 5: GATE TO FULLY OPENED POSITION
3/8"= 1'-0"
CONTINUE OPERATING AFTER TIPPING
3/8"= 1'-0"
POSITION 3: GATE HOIST RELEASED AT TIPPING POINT
POSITION 4: GATE HOIST ENGAGED TO
GATE OPENING SEQUENCE
1871043 12-18-15
- - -
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871043 sht gate closures.dw
g
Drawing
No.
Ja
n. 6
, 2
01
6 - 1
1:1
2 A
M
22
x3
4 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
Dwg No. Reference Drawing Title
Date
- - -- -
PRELIMINARY
NOT FOR
CONSTRUCTION
PROPOSED
GATE LIFTING AND RESETTING SYSTEM
EAGLE CREEK RENEWABLE ENERGY, LLC.
NESHKORO, WI
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN
3/8"= 1'-0"
TO CONTINUE CLOSING AFTER TIPPING
3/8"= 1'-0"
POSITION 5: GATE FULLY CLOSED
3/8"= 1'-0"
POSITION 1: GATE FULLY OPENED POSITION
3/8"= 1'-0" 3/8"= 1'-0"
POSITION 3: GATE AT TIPPING POINT
POSITION 2: HOIST CABLE AT VERTICAL
GATE CLOSING SEQUENCE
POSITION 4: GATE HOIST ENGAGED
1871043 01-14-16
- - -
Project No. Date Revised
J:\1871\043\D
raw
ings\W
orking D
raw
ings\1871043 sht gate closures.dw
g
Drawing
No.
Ja
n. 1
5, 2
01
6 - 1
:3
6 P
M
22
x3
4 =
F
UL
L S
CA
LE
Date Drawn Checked
CheckedDrawnDesigned
RevisionNo.
01"
2"
3"
Dwg No. Reference Drawing Title
Date
- - -- -
PRELIMINARY
NOT FOR
CONSTRUCTION
PROPOSED
GATE LIFTING AND RESETTING SYSTEM
EAGLE CREEK RENEWABLE ENERGY, LLC.
NESHKORO, WI
RAPIDAN HYDROELECTRIC PROJECT
FERC No. 3071-MN