00. Basic Structure Training for Non-structure Background Staffs
-
Upload
karthikv83 -
Category
Documents
-
view
218 -
download
0
Transcript of 00. Basic Structure Training for Non-structure Background Staffs
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
1/46
COPYRIGHT (C) KEPPEL FELSLTD
1
Basic structure training course fornon-structure background staffs
in Mumbai Engineering Office
Date: 21 Feb 2006.
By: Paul Liang
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
2/46
COPYRIGHT (C) KEPPEL FELSLTD
2
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
3/46
COPYRIGHT (C) KEPPEL FELSLTD
3
CONTENT
1. TYPES OF OFFSHORE STRUCTURE TYPES2. JACK UPS
3. SEMI- SUBMERSIBLES
4. BASIC SHIP STRUCTURE
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
4/46
COPYRIGHT (C) KEPPEL FELSLTD
4
Types of OffshoreInstallations
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
5/46
COPYRIGHT (C) KEPPEL FELSLTD
5
Submersibles
Semi submersibles
Drill ship Fixed Platforms
Jackups
FPSO, FSO, FPS
Others
Types of offshore installations
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
6/46
COPYRIGHT (C) KEPPEL FELSLTD
6
KFELS TRACK RECORDTo date KFELS has built a whole range of offshore drilling rigs and support
platforms which includes :
34 Jack-ups
12 Semi-submersibles
5 Submersible drill barges
5 Drillships
3 Drilling Tenders
2 Tension Leg Platforms
3 FPSOs
3 Cable-laying Ships
5 Topside Decks
3 Power Plants
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
7/46
COPYRIGHT (C) KEPPEL FELSLTD
7
Jack-ups
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
8/46
COPYRIGHT (C) KEPPEL FELSLTD
8
Terms Used On Jack-Ups
Spudcan
Legwell
Leg Structure
Jackcase
Preload Tank Drill Water Tank
Ballast Tank
Pipe Rack
Cantilever
P Tank (Bulk Storage)
Drag Way
V Door Ramp (Pipe Ramp)
Choke & Kill Manifold
Mud Return Through
Derrick
Rotary Table
Cellar Deck
Skidding Deck
Drillfloor
Mud Pits Driller Office
Mouse Hole
Rat Hole
Setback
Bop Stack
Mud Ditch
Trip Tank Hillman Rollers
Draw Works
Mud Standpipe Manifold
Inner Bottom
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
9/46
COPYRIGHT (C) KEPPEL FELSLTD
9
The main hull scantling drawings for a Jack-up
Bottom Shell Plan
Tank Top Plan
18-0 Level Plan Main Deck Plan
Transom Bulkhead Section
Transverse Frame Section
Transverse Bulkhead Section
Longitudinal Section
i) Side Shell Elevation
j) Leg Well Details
k) Leg Spud Can Structures
l) Leg Structures
m) Jack Case & Lower Guide
n) Jack Foundation Bracings
o) Location of Full Penetration
p) Deck House structures.
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
10/46
COPYRIGHT (C) KEPPEL FELSLTD
10
Steel Outfitting for a Jack-up
a) Bottom Plugs Location
b) Sea-Chest Details
c) Anchor Rack Detailsd) Main Generator Foundation
e) Emergency Generator
Foundation
f) Skeg Details
g) Pumps Foundation
h) Fwd/Aft Towing Pad Details
i) Structural Doors Schedule
j) Grating Platforms
k) Hatchesl) Booby Hatches
m) Manholes & Vertical Ladders
n) Inclined Ladders
o) Loose Tanks
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
11/46
COPYRIGHT (C) KEPPEL FELSLTD
11
Jack ups are used
for shallow water
drilling.
To withstandstrong wind and
wave pressure
Jack ups are
mostly in
triangular shape
There are 3 or
more vertical legs.
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
12/46
COPYRIGHT (C) KEPPEL FELSLTD
12
These legs have teeth
that can be raised or
lowered by a jacking
mechanism on the deck
When arrival to next
location, the legs are
jacked down till theytouch the sea bed.
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
13/46
COPYRIGHT (C) KEPPEL FELSLTD
13
@ Port Side View
Cantilever @ 20ft CL. Of Well Off Transom
Cantilever
Port Aft
Crane
DerrickLegs
Jack Up
Motor
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
14/46
COPYRIGHT (C) KEPPEL FELSLTD
14
Life Boat
( 107Men )
Heli Deck
Quarters
Yard Temporary Access
@ Port Side View
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
15/46
COPYRIGHT (C) KEPPEL FELSLTD
15
@ Front View
( 225ft x 208ft x 25ft )
Quarters
Life Boat
(107Men)
HeliDeck
DerrickLegs
(517ft)
Yard Temporary Access
Jack Up
Motor
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
16/46
COPYRIGHT (C) KEPPEL FELSLTD
16
@ Top Of Cantilever, Elevation 44 - 9
1/2 ABL.
Crane
V-Door
Ramp
PipeRack
Deck
Dragway
Access To Pipe Rack Deck
Derrick
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
17/46
COPYRIGHT (C) KEPPEL FELSLTD
17
@ Port Leg View
Jack
Unit
LegCrane
Pipe
Rack
Deck
Access To Pipe Rack Deck
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
18/46
COPYRIGHT (C) KEPPEL FELSLTD
18
@ Port Leg View, Main Deck, Elevation 25 - 6
1/4 ABL..
Jack
Up
Leg
Jack
Up
Motors
Main
Deck
Crane
Access To Pipe Rack Deck Radiator Platform
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
19/46
COPYRIGHT (C) KEPPEL FELSLTD
19
@ Main Deck, Elevation 25 - 6 1/4 ABL.
Quarters
Cement
P-Tanks
Main
Deck
Crane
Jack
Up
Leg
Jack Up
Motors
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
20/46
COPYRIGHT (C) KEPPEL FELSLTD
20
Jack Up
Leg
Jack Up
Motor
Quarters
CementP-Tank
Main
Deck
Crane
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
21/46
COPYRIGHT (C) KEPPEL FELSLTD
21
@ Port Side - Aft View
Crane
Heli-Deck
Quarters
Access ToMain Deck
Jack Up
Motors
Jack Up
Legs
Derrick
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
22/46
COPYRIGHT (C) KEPPEL FELSLTD
22
@ Front View
( 225ft x 208ft x 25ft )
Jack
Up
Legs
Derrick
Life
Boat
Quarters
Heli-
Deck
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
23/46
COPYRIGHT (C) KEPPEL FELSLTD 23
@ Front View
( 225ft x 208ft x 25ft )
Jack
Up
Legs
Life Boats
( 107Men )
Heli-
Deck
Life
Boats
( 65Men )
Life Boat
Davit
Yard Temporary Access
Jack
Up
Motors
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
24/46
COPYRIGHT (C) KEPPEL FELSLTD 24
@ Port Side View
Cantilever @ 20ft CL. Of Well Off
Transom
Cantilever
Derrick
Legs
Crane
Heli
DeckCable
Festoon
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
25/46
COPYRIGHT (C) KEPPEL FELSLTD 25
@ Port Side ViewCantilever @ 20ft CL. Of Well Off Transom
Derrick
Cantilever
Cable
Festoon
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
26/46
COPYRIGHT (C) KEPPEL FELSLTD 26
Semi-submersible
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
27/46
COPYRIGHT (C) KEPPEL FELSLTD 27
Semi-Submersible
Most useful of all other drilling platforms.
Towed to the location and ballasted down so
that it sits on the bottom.
Larger type of drilling platformHouse of vessel were ballasted and allowed
to submerged and rest on the water
Drilling and accommodation deck remainsclear of water on tall pillars
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
28/46
COPYRIGHT (C) KEPPEL FELSLTD 28
Terms Used On Semi-Submersibles
Pontoons (lower Hull)
Columns
Bracings
Fenders
Blisters
Mooring Padeyes Upper Hull
Moonpool
K-Bracing
Ram Rig Substructure
Riser Pipe Stack
Forward Pipe Stack
Crane Boom Rest
Sand Trap
Degasser tank
Desilter Tank Clean Tank
Hazardous Drain Tank
Gumbo Box
Catwalk
Drain Gutter
Laydown Area Helideck
Fingerboard
Mud Logging Unit
Shale Shaker House
Ram Hoisting SWBD Room
HPU House
Navigating Mast Wind Sock
Surge Tank
Remote Operator Vehicle
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
29/46
COPYRIGHT (C) KEPPEL FELSLTD 29
Main Hull scantlings for a Semi-Submersibles
Pontoon Bottom Shell Plan
Pontoon Side Shell Plan
Pontoon Deck Plan
Pontoon Centerline Section
Column Shell Elevation
Column Centerline Section
Column TransverseSection
Longitudinal Section
Transverse Bracings
j) Diagonal Bracings
k) Fenders Structures
l) Blister Structures
m) Upper Hull Lower DeckPlan
n) Upper Hull Main Deck Plan
o) Upper Hull LongitudinalPlan
p) Upper Hull Transverse Plan
q) Deckhouse Structures
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
30/46
COPYRIGHT (C) KEPPEL FELSLTD 30
Steel Outfitting for a Semi-Submersibles
a) Pontoon Bottom Plugs
b) Pontoon Sea-Chest Details
c) Pontoon Anchor RackDetails
d) Pontoon ThrusterFoundation
e) Pontoon Motor Foundation
f) Pontoon Pumps Foundation
g) Pontoon Towing Pads / Chks
h) Pontoon Hand RailingDetails
i) Watertight Doors Schedule
j) Grating Platforms
k) Hatches
l) Booby Hatchesm) Manholes & Vertical
Ladders
n) Inclined Ladders
o) Loose Tanks
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
31/46
COPYRIGHT (C) KEPPEL FELSLTD 31
Can operate in
deep or slightly
shallow water.
Working deck with
vertical columns
fitted beneath the
deck.
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
32/46
COPYRIGHT (C) KEPPEL FELSLTD 32
Some of the tanks
ballasted to submerge
the vessel to maximise
stability and minimise
movement.
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
33/46
COPYRIGHT (C) KEPPEL FELSLTD 33
Basic Ship Structure
Bulkhead-Transverse
-Longitudinal
Corrugated Bulkhead
Transverse FloorLongitudinal Floor
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
34/46
COPYRIGHT (C) KEPPEL FELSLTD 34
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
35/46
COPYRIGHT (C) KEPPEL FELSLTD 35
Longitudinal Bulkhead
Transverse Bulkhead
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
36/46
COPYRIGHT (C) KEPPEL FELSLTD 36
Transverse floor
Longitudinalfloor
Tank Top
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
37/46
COPYRIGHT (C) KEPPEL FELSLTD 37
Main Functions Divide the main hull into different
compartments
In the event of a damage to the shell platingbulkheads limit the extend of flooding andhence of loss of buoyancy.
Transverse bulkhead prevents racking andtorsional distortion.
Longitudinal bulkheads contribute to thelongitudinal strength.
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
38/46
COPYRIGHT (C) KEPPEL FELSLTD 38
Corrugated Bulkhead Corrugations are formed on a corrugated bulkhead to
eliminate the need to fit the vertical stiffeners
It is stronger than a flat plate
Elimination of vertical stiffeners results in saving in steel
weight and cost of stiffeners.
Steel plates are arranged in a vertical direction increasingslight increase in plate steel weight
The angle of corrugation is normally about 45 degrees
Diaphragm plates or horizontal stringers are fitted on thebulkhead to keep the corrugation in place.
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
39/46
COPYRIGHT (C) KEPPEL FELSLTD 39
Corrugated bulkheadsunder construction
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
40/46
COPYRIGHT (C) KEPPEL FELSLTD 40
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
41/46
COPYRIGHT (C) KEPPEL FELSLTD 41
New plates in storage
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
42/46
COPYRIGHT (C) KEPPEL FELS
LTD
42
How are plates cut?
Plates are cut by cutting torch, whichproduces a flame with a stream of oxygento burn off steel material at the line of cut.
Hand or machine cutting can beperformed.
Other methods are plasma cutting,waterjet cutting, etc.
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
43/46
COPYRIGHT (C) KEPPEL FELS
LTD
43
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
44/46
COPYRIGHT (C) KEPPEL FELS
LTD
44
Double
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
45/46
COPYRIGHT (C) KEPPEL FELS
LTD
45
Double
Bottom
Blocksunder
construction
Typical Panel Marking
-
8/22/2019 00. Basic Structure Training for Non-structure Background Staffs
46/46
COPYRIGHT (C) KEPPEL FELS 46
Typical Panel Marking
Project Number Panel Number
Blk No.
MSS Number
Plate Number