© Vattenfall AB
1
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Mozambique Regional Transmission Backbone Project (“CESUL”):
Technical & Economic Feasibility Study
Presentation of Feasibility Study Report
CESUL Launch Workshop
Centro de Conferências Joaquim Chissano
Maputo, 24 November 2011
© Vattenfall AB
2
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Presentation outlinePresentation outline Feasibility study objective & goalsFeasibility study objective & goals Feasibility study highlightsFeasibility study highlights Power market assessmentPower market assessment Mozambique generation options consideredMozambique generation options considered CESUL technical feasibilityCESUL technical feasibility Economic & financial feasibilityEconomic & financial feasibility CESUL project timelinesCESUL project timelines Institutional and operational arrangementsInstitutional and operational arrangements Conclusions & RecommendationsConclusions & Recommendations
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
3
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Feasibility Study objective & goals
Objective:• Provide technical and economic determination of least
cost option for transfer of 3,100 MW north-south in Mozambique
CESUL Project Goals:
• Contribute to Mozambique’s economic and social development through facilitating improved access to electricity by:– Interconnecting the Mozambique power systems north-south,
i.e. creating a Backbone Transmission System
– Supply electricity at affordable prices to load centres and consumers along the transmission system corridor
• Facilitate realisation of Mozambique’s large power development potential, with particular focus on hydropower, for domestic and industrial use and bulk export of cost-competitive renewable energy to South Africa and Southern Africa
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
4
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Feasibility Study scope of work
Review and update all information in previous studies and undertake:
•Load forecasts (Mozambique / Southern Africa region)
•Regional generation expansion scenarios (for Mozambique candidate projects)
•Power system studies– Minimum one (1) AC link north-south as a premise for acceptability of any alternative
•Determination of substation locations
•Line routes – HVAC and HVDC (incl. electrode locations)
•Preliminary engineering designs (lines & substations) and costing
•Project packaging and implementation programme
•Operational and control centre requirements, including organisation & training
•Economic and financial feasibility analysis
•Liaise with CESUL ESIA/RPF Consultant (separately appointed)
The CESUL Feasibility Study builds on previous pre-feasibility study (2008) by Vattenfall Power Consultants and subsequent technical Optimisation Study (2009)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
5
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Feasibility Study deliverables
The Technical and Economic Feasibility Study report consists of the following documents:
•Volume I-A: Main Report
•Volume I-B: Appendices to Main Report
•Volume II: Economic Impact Study (still being completed)
•Volume III-A: Preliminary Design Report – HVAC and HVDC Transmission Lines
•Volume III-B: Preliminary Design Report – HVAC and HVDCSubstations
•Volume IV: Line Route Report – HVDC Line
•Volume V: Line Route Report – HVAC Line
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
6
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Key challenges encountered
• Challenges to successful realisation of CESUL and the associated large (hydropower) generation developments include:
– Project size and remoteness / distances involved
– Technical requirements (to ensure high availability & reliability)
– Cost competitiveness compared to alternative regional options
– Amount of financing and commercial frameworks required
– Integrated nature of generation and transmission developments, requiring alignment of stakeholder interests and high degree of coordination
• Other key considerations include:– Devising transmission solutions in support of initial generation developments
while facilitating long-term expansion to tap Mozambique’s energy potential
– Ensuring sustainability and tangible benefits to local (Mozambican) economy from recommended technical and economic solutions
– Minimising environmental & social impacts through line route selection
– Dynamic and iterative nature of planning, analysis, structuring and financing
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
7
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Findings and Conclusions
• Feasibility Study confirms technical viability of combined HVAC and HVDC transmission backbone solution for 3,100 MW (and more) power transfer capability
• CESUL Phase 1 investment costs (excl. financing costs and IDC) are estimated at US$ 2,119 million (of which US$ 1,800 million for Stage 1)
– Phase 1 financing requirement of ~US$2,780 million incl. IDC & price contingency
• Economic viability of combined hydropower and transmission backbone is robust• Financial viability and competitiveness of delivering electricity at Mozambique / South Africa
border in southern Mozambique appears promising– Timely realisation of Mphanda Nkuwa project is key to commence CESUL development
– Realising Cahora Bassa North Bank will allow complete CESUL Phase 1 development
– Cost of debt financing to be tested with market participants
• HVAC solution will ensure interconnection of Mozambique’s national transmission grid, with increased access to electricity along line route
• HVDC portion of transmission backbone is scalable – for initial CESUL Phase 1 solution and beyond
• Due to magnitude of project costs, a staged Phase 1 realisation should be considered• CESUL development needs to continue without delay from early 2012 to align with planned
timeframe for commissioning of hydropower project(s)
•
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
8
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
• CESUL Phase 1 includes combined HVAC & HVDC solution
• HVAC solution includes:• 1,340 km 400 kV AC line for 900 MW continuous power
transfer at 400 kV, but with 550 kV design of equipment
• 50% series compensation of AC line
• HVDC solution (Phase 1) includes:• 1,275 km ±500 kV DC bipolar transmission line and converter
stations with 2,650 MW capacity
• 90 km transmission lines to Cataxa and Maputo electrodes
• Implementation of HVDC solution is proposed staged:• Stage 1: ±500 kV DC line with 1,325 MW converter capacity
• Stage 2: Additional 1,325 MW converter capacity
• Project is proposed packaged and tendered as a limited number of contracts (indicatively 7)
• Timeframe to implement Phase 1 / Stage 1 is 59 months:• Design, tendering and contracting period: 17 months
• Construction period: 42 months
Recommended CESUL Phase 1 solution
© Vattenfall AB
9
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Feasibility Study – CESUL Feasibility Study –
Power Market AssessmentPower Market Assessment
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
10
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Mozambique demand forecast - recent electricity demand growth trajectory (excluding Mozal)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
11
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Mozambique demand forecast (cont. I)
• Forecast period is 2010 – 2030:– Energy supplied (before losses) (in GWh) and Peak demand (MW)– Natural growth + Large consumer demand– Medium forecast = base case (+ high and low forecast)
• General electricity demand drivers:– Annual GDP growth:
• 2010 - 2015: 6.5% - 7.9% (IMF estimates)• 2016 - 2030: initially 7.0%, tapering off to 4.0%• GDP elasticity: 1.2, tapering off to 1.1 (except large loads)
– Electricity tariffs – current tariffs do not cover costs:• 7% real increase assumed over next 5 years• Assumptions applied will contribute to dampen future demand growth
• Large user loads:– Defined as > 5 MW initial loads, identified based on information from EdM,
Ministry, developers and consultant estimates– Cost-reflective tariffs assumed, with consequences for energy intensive projects
that rely on low tariffs (e.g. Mozal expansion)– Uncertainty with respect to loads and timing dealt with by estimating probability
and applying loads to medium forecast, high forecast and low forecast respectively
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
12
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Mozambique demand forecast (cont. II) –Base Case national demand forecast (GWh)
National Energy Demand (GWh): Medium Case Forecast
0
2000
4000
6000
8000
10000
12000
14000
2009 2014 2019 2024 2029
GWh
Northern
Central
Southern
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
13
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Mozambique demand forecast (cont. III)
Peak Demand – Base Case, High and Low forecasts (MW)
Base Case forecast – natural growth and large loads (MW)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
14
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Southern African power demandSAPP power demand and supply: Importance of South Africa’s IRP2010
• South Africa approved an IRP2010 in April 2011, being a 20-year indicative generation expansion plan
• Strong focus on clean, renewable energy
• Plan assumes 2,600 MW of hydropower import, mainly from Mozambique, to commence in 2022 (earlier if possible)
• Preference is for base load / mid-merit energy (not peaking)
• IRP2010 includes long-term indicative electricity price forecast
• Forecast average cost of new (base-load) generation is >10.0 USc/kWh
• Represents benchmark for Mozambique hydropower at South Africa border
• Actual price will however be subject to commercial negotiations
• Southern Africa needs additional generation capacity – quickly!
• Current reserve margins are insufficient• South Africa is by far the dominant market
© Vattenfall AB
15
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Feasibility Study – CESUL Feasibility Study –
Mozambique Generation Options and Regional Generation Mozambique Generation Options and Regional Generation Expansion ScenariosExpansion Scenarios
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
16
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
• Potential generation projects were reviewed, focused on hydropower, coal, gas-fired projects
• Gas-fired plant with a total capacity of up to 600 MW are assumed built in Southern Mozambique, as well as 100 MW of local generation injected into Tete part of system
• Based on regional market assessment, hydropower projects are considered priority:
• Mphanda Nkuwa (“MPNK”)• 1,500 MW base-load / mid-merit plant
• 8,600 GWh of annual energy (850 MW firm power)
• Feasibility study complete / Concession Agreement exists
• Cahora Bassa North Bank (“CBNB”)• 1,245 MW estimated mid-merit/peaking capacity
• 2,983 GWh of gross annual energy (but only 854 GWh increase in overall Cahora Bassa annual energy)
• Studies ongoing / data & information to be firmed up
Generation Option Assessment –Mozambique candidate generation projects
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
17
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Generation Scenarios and associated Transmission Solutions
Candidate generation projects and associated transmission alternatives were studied through scenarios, with grid injection of 600 MW gas-fired generation in south and 100 MW
generation in Tete common to all scenarios
No. Scenario: CESUL capacity CESUL transmission alternative
0 Reference 0 MWNot applicable (new 400kV line Songo-Matambo-Inchope + reinforcement in south required)
1 CBNB 1,245 MWSingle circuit 400 kV line (4 x Tern) with 550 kV equipment rating, 70% series compensation
2 MPNK 1,500 MWDouble circuit 400 kV line (4 x Tern) with 550 kV equipment rating, 50% series compensation
3 MPNK + CBNB 2,745 MWSingle circuit 400 kV line (4 x Tern) with 550 kV equipment rating, 50% series compensation, plusBi-pole DC line (4 x Martin), 2,650 MW capacity
4 Add. Hydro Energy 3,536 MWSame as Scenario 3 (2nd bi-pole may be required if all generation projects implemented early)
5 Extended Hydro 4,486 MW Scenario 3 plus 2nd bi-pole (5,300 MW capacity)
6 Large Hydro & Coal 7,545 MWScenario 3 plus 2nd bi-pole to Maputo and 3rd bi-pole terminated in South Africa
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
18
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Regional generation expansion modelling
• Southern Africa needs ~1,500 MW of additional (base-load) capacity per annum
• Future generation and transmission developments in Mozambique will depend on competitiveness of Mozambique projects compared to alternative regional projects
• Cost characteristics for Mozambique and regional generation projects were developed and analysed
– January 2011 used as reference year for prices and cost estimates
– Investment, (fixed and variable) O&M costs, and fuel costs considered
– Analysis covered thermal (coal and gas-fired) and renewable generation projects (including hydropower, wind and solar)
– Cost data were sourced from EPRI, Nexant and Consultant’s own data bases
– Particular focus on generation expansion as envisaged by South Africa’s IRP2010
• Generation expansion simulations were undertaken to demonstrate economic viability of large-scale power export from Mozambique
– Total generation costs, including energy not served (“ENS”) and spinning reserve costs, as well as generation related transmission costs (including losses) considered
– Mozambique options substituted for ‘generic’ options in IRP2010
– Overall NVP of total generation costs in regional generation simulations was calculated, using feasibility study Generation Scenarios 1 to 6 as previously presented
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
19
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Generation expansion scenario results
Generation Expansion Simulations 2011 - 2030
(NPV in US$ billion)
Sc. 0 Refe-rence
Sc. 1 CBNB
Sc. 2 MPNK
Sc. 3 MPNK
& CBNB
Sc. 4 3,500 MW
Hydro
Sc. 5 4,600 MW
Hydro
Sc. 6 Large Hydro & Coal
Total Generation System Costs (capital, O&M, fuel, ENS)
132.481 131.357 130.635 129.903 129.616 129.751 129.252
Generation System Savings (relative to Reference Scenario)
- 1.124 1.846 2.579 2.866 2.731 3.230
Transmission System Costs (related to generation options)
0.233 0.685 0.983 1.384 1.422 1.748 2.368
Total Costs 132.714 132.042 131.618 131.287 131.038 131.499 131.620
Total Savings (relative to Reference Scenario)
- 0.672 1.096 1.427 1.676 1.215 1.094
Tentative value of reduced CO2 emissions (using US$20 per ton)
- 0.255 0.752 0.884 1.104 1.198 0.937
Savings incl. emission reduction (relative to Reference Scenario)
- 0.927 1.848 2.311 2.780 2.413 2.031
Some observations:•All generation scenarios with inclusion of Mozambique hydropower projects appear merited•Despite significant transmission costs, both MPNK and CBNB are economically viable projects•While Scenario 4 shows the highest potential saving, this scenario may trigger additional investments in transmission infrastructure at an early stage•On balance, therefore, Scenario 3 (MPNK and CBNB) appears to be most robust, with scope for future expansion by additional hydropower resource developments
© Vattenfall AB
20
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Feasibility Study – CESUL Feasibility Study –
Technical Feasibility AssessmentTechnical Feasibility Assessment
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
21
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Planning methodology & criteria
• Transmission– Planning assumptions document prepared and discussed with Eskom (ref.
“Memorandum of Transmission Planning Assumptions”)• Complies in general with South Africa’s Grid Code
– Deterministic N-1 planning criteria, but with agreement that up to 2,000 MW of generation can be tripped in Tete area for an outage of a line on CESUL transmission backbone (effectively a “N-½ criteria”)
• Will normally not affect customers in South Africa due to size of South Africa system
– Series compensation facilities and Static VAr Compensators (SVC) along AC backbone planned with redundancy
– All transmission alternatives considered include at least one 400 kV AC line from Tete area to Maputo, to provide supply to areas in between
– Recognised that wheeling capacity through Zimbabwe may be limited
• Generation characteristics recognised– Production profiles– Forced and Scheduled outages– Minimum 15% reserve requirement for South Africa, with maximum 19% import
share (of peak load)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
22
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Transmission system studies undertaken
• Load flow, voltage stability and losses
• Simulation of normal ‘steady state’ operation
• Contingency analyses
• Transient and dynamic stability
• Fault levels
• Sub-synchronous resonance studies
• Switching studies
• Optimisation of conductor configuration
• Optimisation of reactive power compensation facilities:– Line and bus shunt reactors
– AC line series compensation
– Static VAr Compensation (SVC)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
23
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Transmission system studies (cont.)
• Key assumptions:– Generation at Benga and Moatize developed basically to
cover own demand, with 100 MW surplus generation sold to EdM
– HVDC Songo - Apollo transfer capacity of 1,920 MW
– SAPP grid support during contingencies
– Wheeling via Zimbabwe attempted kept at low level as full capacity of interconnection Songo - Bindura may not be available in future
• Under normal operations, wheeling may possibly be avoided once CESUL HVDC line is in service
– Comparison of alternatives based on unit cost estimates• Detailed cost estimates based on supplier quotations
developed for recommended CESUL scheme
– CESUL O&M costs estimated at 2.0% p.a.
– Marginal cost of losses priced at 6.0 USc/kWh (for equivalent capacity and energy cost)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
24
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
• HVDC• 500 kV and 600 kV bi-pole schemes - bi-pole
lines
• 800 kV mono-pole Phase 1
• 2nd 800 kV mono-pole in Phase 2, forming bi-pole with DC in Phase 1
• HVAC• 400 kV operation (but heavier equipment design)
• Quadruple line configuration to limit reactance
• Compact line / expanded bundle design considered for high transfer levels
• Series compensation up to 70% to achieve transient stability
• Line and bus shunts to handle energization / load rejection
• SVCs for voltage & stability control measures
• Intermediate substations required for voltage control combined with supply to local area
Both HVAC and HVDC technology solutions were examined in the
Feasibility Study, under a number of design considerations
Transmission solutions considered
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
25
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Transmission studies – considerations
• Characteristics of existing transmission system
• Defining a base case (without CESUL backbone)
• Specific technical challenges (line lengths, fault levels, compensation, energization)
• Substation locations (AC + DC)
• Interaction with HVDC system Songo – Apollo (RSA)
• Integration with neighbouring SAPP countries and wheeling over SAPP networks
• System expansion in Southern Mozambique
• Interfacing with Motraco system
• New Master Power Controller (MPC)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
26
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Key considerations:General
•Utilize existing and planned "energy" corridors (transmission lines, roads, railways)
•Minimise social and environmental impact
•Access and maintenance conditions
•Utilise reliable low cost design
•Least cost
HVAC Line Routing
•Support for development of Mozambique
•Interconnection of EDM grid
•Selection of substations considering reactive compensation requirements
HVDC Line Routing
•Bulk power transfer (aligned to generation scenarios)
•Minimise social and environmental impact
•Utilise reliable low cost design
Line routings (HVDC and HVAC)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
27
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Conclusions from transmission studies
For AC line(s), the following is noted:
•Distance from Tete to Maputo (~1,340 km along chosen route) presents technical challenges:
– Voltage control (for energisation and normal and contingency operation)
– Transient and dynamic stability
– (Note: 53 km of 400 kV line Songo – Cataxa will be required, not currently defined as part of CESUL Phase 1)
•Low reactance is required, implying:– Four bundle conductor configuration
– Compact line design with expanded bundle would be required for high transfers (>1,400 MW)
•Low reactance leads to high capacitance, causing:– Higher switching surges
– Increased insulation level
– Higher investment costs
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
28
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Conclusions from transmission studies (cont. I)
• AC line requires extensive reactive power control for energisation and voltage regulation during normal and contingency operation:
– Long line - must be split in sections
– Intermediate substations at Inchope, Vilanculos and Chibuto are required and will feed into local grids
– Line shunt reactors required at either end of each line section in combination with switched bus shunt reactors
– Large SVCs required at intermediate substations, with two units at each of Inchope and Vilanculos to maintain operability during outages of SVCs
• New substation proposed at Moamba to act as feeding point for Maputo area (and suitable connection point for gas-fired plant and potential future 3rd 400 kV line to South Africa)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
29
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Conclusions from transmission studies (cont. II)
For DC line(s) the following is noted:
•500 kV HVDC bi-pole solution with bi-pole DC line estimated to present least-cost solution for CESUL DC link
– 600 kV HVDC bi-pole and 800 kV mono-pole also evaluated, but considered to imply slightly higher overall costs
•Bi-pole solution will provide higher overall availability (than mono-pole), although loss of 500 kV bi-pole will require tripping of generation as for a 800 kV mono-pole solution
•500 kV bi-pole solution will also limit environmental impacts through reduced width of right-of-way, lower line towers (about 3.5 m lower) and less time of operation with electrodes
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
30
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
• HVAC operated at 400 kV (equipment designed for 550 kV) – 900 MW transfer capacity
• HVDC operated at ±500 kV – 2,650 MW transfer capacity, implemented in two stages , each with 1,325 MW converter capacity
CESUL Phase 1 – combined HVAC / HVDC solution
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
31
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Stage 1: 1,325 MW Stage 2: 1,325 MW
Staged implementation of HVDC for CESUL Phase 1
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
32
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL connections to Mozambique power system
Connection to load centres and consumers along CESUL HVAC transmission line route
Connection to ‘regional’ power systems
Voltage levelsTransmission
linesTransformer
capacity
Matambo 400/220 kV - 2 x 250 MVA
Inchope 400/220 kV 220 kV in-out 1 x 400 MVA
Vilanculos 400/110 kVExternal project
(not CESUL)1 x 125 MVA
Chibuto400/110 kV110/33 kV
External project (not CESUL)
1 x 125 MVA1 x 40 MVA
Moamba400/275 kV275/110 kV110/33 kV
External project (not CESUL)
1 x 500 MVA1 x 125 MVA1 x 63 MVA
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
33
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Project cost estimates
• General approach– Unit costs used for comparison, drawn from Consultant’s databases and
external cost statistics (e.g. CIGRE)– Supplier quotations used for actual Project costing and economic/financial
analysis, based on EPC delivery, "CIF to port“
• Project costing includes Engineering & Owner’s Costs and Contingencies (added to suppliers’ EPC cost quotations):
– Engineering & Owners Cost: 10% of EPC quotations• Considered conservative
– Physical Contingencies: 10% of EPC quotations– Price Contingencies: not included in Project cost estimates
• 10% price contingency on EPC quotations recommended included when finalising Project financing requirements
• Relocation / compensation payments:– Included in Project costs with value equal to 2% of estimated transmission
line cost (HVAC and HVDC)– CESUL RPF Report recommendations will be used in Final Report, with
latest indication is 3% of transmission line costs
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
34
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Phase 1 HVAC costing
HVAC - Cost Components400 kV
ForeignUSD (‘000)
LocalUSD (‘000)
Total USD (‘000)
HVAC Transmission Line 339 641 81% 79 672 19% 419 313
HVAC Substations 336 736 92% 29 281 8% 366 017
Compensation (2% of line) 0 0% 8 386 100% 8 386
Engineering & Owner's Cost (10%) 47 120 60% 31 413 40% 78 533
Physical Contingencies (10%) 62 826 80% 15 707 20% 78 533
Total HVAC Phase 1 786 323 83% 164 459 17% 950 782
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
35
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Phase 1 HVDC costing
HVDC - Cost ComponentsStage 1, ± 500 kV 1325 MW
ForeignUSD (‘000)
LocalUSD(‘000)
TotalUSD (‘000)
HVDC Transmission Line 308 258 81% 72 308 19% 380 566
HVDC Stations 294 685 92% 25 625 8% 320 310
Compensation (2% of line) 0 0% 7 611 100% 7 611
Engineering & Owner's Cost (10%) 42 053 60% 28 035 40% 70 088
Physical Contingencies (10%) 56 070 80% 14 018 20% 70 088
Total HVDC: Stage 1 of Phase 1 701 066 83% 147 597 17% 848 663
HVDC - Cost ComponentsStage 2, Additional 1325 MW
ForeignUSD (‘000)
LocalUSD (‘000)
Total USD (‘000)
HVDC Stations 244 720 92% 21 280 8% 266 000
Engineering & Owner's Cost (10%) 15 960 60% 10 640 40% 26 600
Physical Contingencies (10%) 23 940 90% 2 660 10% 26 600
Total HVDC: Stage 2 of Phase 1 284 620 89% 34 580 11% 319 200
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
36
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Phase 1 – total investment costs
Summary CESUL Phase 1:400 kV 900 MW HVAC Transmission and± 500 kV 2,650 MW HVDC Transmission USD (’000)
Total HVAC Phase 1 950 782
Total HVDC Stage 1 of Phase 1 848 663
Total HVAC + HVDC Stage 1 of Phase 1 1 799 445
Total HVDC Stage 2 of Phase 1 319 200
Total CESUL Phase 1(excl. IDC, Financing costs/fees and Price Contingencies)
2 118 645
Interest During Construction (IDC) & Financing Costs / Fees (est.) 450 000
Price Contingency (10% of Project Costs excl. IDC & fees) 211 865
Total Phase 1 Funding Requirement 2 780 510
© Vattenfall AB
37
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Feasibility Study – CESUL Feasibility Study –
Economic & Financial FeasibilityEconomic & Financial Feasibility
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
38
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Economic feasibility – objective & approach
• Objective of economic analysis:– Establish least-cost Project option (for each generation scenario)– Ensure that benefits of least-cost Project option exceeds Project costs– Demonstrate that Project represents efficient use of scarce economic resources
• Approach:– Project benefits and costs are compared to a situation without the Project– Analysis is based on discounted cash flow (“DCF”) modelling– Required Internal Rate of Return (“IRR”) of 10% in real terms (equal to assumed
economic opportunity cost of capital)– Calculation of Economic IRR (“EIRR”), Net Present Value (“NPV)” and Economic
Unit Energy Cost (“EUEC”) of electricity generated and transported – Analysis focused primarily on assessment of Generation Scenarios 1, 2 and 3:
• Scenario 1: CBNB only (1,245 MW)
• Scenario 2: MPNK only (1,500 MW)
• Scenario 3: MPNK + CBNB (1,500 MW + 1,245 MW), with CBNB implemented 2 years after MPNK
• Scenario 3: MPNK only + Stage 1 of CESUL Phase 1 only
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
39
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Economic feasibility – assumptions
• Main assumptions:– 45 years Project life
– All power from MPNK and CBNB assumed contractually transmitted over CESUL infrastructure
– Transmission losses assumed as 4.5% in recommended alternative
– Electricity valued at 10.5 USc/kWh at SA border
• Equal to estimated alternative cost of base-load supply (assuming Combined Cycle Gas-Fired plant using imported LNG)
– Operating costs of CESUL infrastructure: 2.0% p.a. of investment
– Energy transmitted from:
• MPNK: 8,548 GWh/year
• CBNB: 2,983 GWh/year– Total net increase of production at Cahora Bassa complex is 854 GWh/year,
including a decrease at CBSB of 2,129 GWh/year
– Loss of generation at CBSB takes place at night, and such lost generation is priced at 2.6 USc/kWh (assumed as variable cost of coal-fired plant)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
40
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Economic feasibility - results
CESUL Project Economic Feasibility Results
Scenario 1 Scenario 2Scenario 3
Phase 1
Scenario 3Phase 1
Stage 1 only
Project IRR 12.5 % 12.5 % 12.7 % 12.6 %
NPV (USD mill) @ 10% 184 268 402 332
Break even tariff (USc/kWh)
4.60 2.35 2.56 2.89
Total Economic Value (Generation + CESUL) - in USD million
Scenario 1 Scenario 2Scenario 3
Phase 1
Scenario 3Phase 1
Stage 1 only
Total Economic NPV (at 10% economic discount rate)
132 1 565 1 962 1 416
Note: IRR and NPV calculations are based on financial transmission tariff
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
41
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Economic feasibility – results (cont.)
Sensitivities – Economic Unit costs (USc/kWh) – MPNK
Scenario 2Scenario 3
Phase 1
Scenario 3Phase 1
Stage 1 only
Construction cost + 20% 7.30 7.41 7.73
Construction cost + 10% 6.94 7.06 7.38
Base case (unit cost at SA border)
6.58 6.71 7.03
Construction cost - 10% 6.22 6.35 6.68
Construction cost - 20% 5.86 6.00 6.33
Sensitivities – Economic Unit costs (USc/kWh) – CBNB
Scenario 1Scenario 3
Phase 1
Construction cost + 40% 10.37 8.01
Construction cost + 30% 10.13 7.78
Construction cost + 20% 9.89 7.54
Construction cost + 10% 9.65 7.31 Base case (unit cost at SA border)
9.41 7.07
Construction cost - 10% 9.17 6.84
Construction cost - 20% 8.93 6.60
• MPNK + CESUL are economic viable and robust solution
• With MPNK only, cost ‘penalty’ of developing CESUL with combined HVAC and HVDC has marginal impact only
• Staged CESUL Phase 1 development is viable solution
• CBNB + CESUL represent an economic viable solution based on HVAC transmission solution
• CBNB economics improve substantially when developed with MPNK and ‘complete’ CESUL solution (HVAC + HVDC)
• CBNB economics appear robust in combination with MPNK, based on recommended CESUL Phase 1
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
42
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Financial viability – objective & approach
• Objective of financial analysis:– Takes the view of prospective investors in CESUL
– Establishes whether investors can be expected to achieve a satisfactory equity return
• Approach:– Project financial income and costs are compared to situation without
the Project
– Analysis is based on discounted cash flow (“DCF”) modelling
– Required USD based equity IRR of 16% after tax in nominal terms for CESUL, 17% for generation investments
– Calculation of Project and Equity IRR, NPV and Financial Unit Energy Cost (“FUEC”) of electricity generated and transported
– Same Generation scenarios as in Economic Analysis, i.e. Scenarios 1 to 3, including alternative with Scenario 3 Stage 1 only
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
43
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Financial viability – assumptions
• Main assumptions:– 30 years concession period
– Electricity selling price set at 10.5 USc/kWh at SA border• Based on estimated alternative cost of base-load supply (assuming
Combined Cycle Gas-Fired plant using imported LNG)
• 10% of MPNK (and CBNB) energy sold with 40% discount to EdM (as per term of Concession for MPNK)
– 70/30% debt/equity ratio assumed
– 8.0% - 8.5% interest rate on USD loans (including margin)• Debt financing assumptions to be tested and confirmed by CESUL Financial
Adviser
– VAT and excise duty exemptions assumed for Generation and CESUL
– No income tax incentives assumed for CESUL
– Tax regime for Generation projects assumed as per MPNK Concession
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
44
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Financial viability - results
MUSD NPV Scenario 1 Scenario 2Scenario 3
Phase 1
Scenario 3Phase 1
Stage 1 only
Total Financial NPV -39 293 389 200
Total Government take 216 793 897 826
CESUL Project Financial Results
Scenario 1 Scenario 2Scenario 3
Phase 1
Scenario 3Phase 1
Stage 1 only
Project IRR 13.0% 13.0% 13.1% 13.0%
Equity IRR 16.0% 16.0% 16.0% 16.0%
Break-even transmission tariff (USc/kWh)
5.78 2.95 3.26 3.64
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
45
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Financial viability – results (cont.)
Sensitivities Financial Unit costs (USc/kWh) – MPNK
Scenario 2Scenario 3
Phase 1
Scenario 3Phase 1
Stage 1 only Construction cost + 20% 9.74 9.94 10.31 Construction cost + 10% 9.25 9.45 9.82 Base case (Unit cost at SA border)
8.75 8.96 9.33
Construction cost - 10% 8.25 8.47 8.85 Construction cost - 20% 7.75 7.98 8.36
Sensitivities Financial Unit costs (USc/kWh) – CBNB
Scenario 1 Scenario 3
Construction cost + 40% 12.34 9.46
Construction cost + 30% 12.05 9.17
Construction cost + 20% 11.76 8.89
Construction cost + 10% 11.47 8.60 Base case (Unit cost at SA border)
11.18 8.32
Construction cost - 10% 10.89 8.03
Construction cost - 20% 10.60 7.75
• MPNK + CESUL is a financially viable and robust solution
• Cost ‘penalty’ of CESUL with combined HVAC and HVDC solution has marginal impact only
• Staged CESUL Phase 1 development is viable
• CBNB financial viability uncertain based on CESUL HVAC solution
• CBNB viability improves when developed with MPNK and ‘complete’ CESUL solution with HVAC + HVDC
• CBNB financial viability appears robust in combination with MPNK, based on recommended CESUL Phase 1 solution
© Vattenfall AB
46
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Feasibility Study – CESUL Feasibility Study –
Project TimelinesProject Timelines
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
47
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Implementing CESUL – key steps
• Key Project development activities– Appoint Consultant for Design, Specifications & Tender documents - Feb 2012
– Commencement of Procurement process - Mar 2012
– Approved tender evaluation - Mid Apr 2013
– Approved contracts - Jun 2013
– Financial Close of Project – Jul 2013
• Construction of Project Facilities– Commencement of OHTL Construction Contracts – Mid Jul 2013
– Commencement of Converter Stations Construction Contract – Mid Jul 2013
– Commencement of Substation Construction Contracts – Nov 2013
– Taking-Over of Project Facilities – Jan 2017
• Assumed timeline for associated IPP projects– Financial close MPNK – Mid-2013
– Commissioning of MPNK – 2nd half of 2017
– Commissioning CBNB ~ earliest mid-2017 (but could be later)
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
48
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Phase 1 – Indicative Project Programme
© Vattenfall AB
49
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Feasibility Study – CESUL Feasibility Study –
Institutional & Operational AspectsInstitutional & Operational Aspects
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
50
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Envisaged organisation of CESUL
• CESUL Project size, technical nature and complexity, as well as the very large financing requirements, are all factors indicating that CESUL should be established as a Special Purpose Vehicle (“SPV”)
– SPV model and recommended structure will be developed by CESUL Financial & Legal Advisors
– EDM is expected to be lead Sponsor
– Additional equity participation may be sought from credible international investors with relevant skills, experience and financial strength
• Organisation structure, staffing and training programme for CESUL SPV should be clarified early to mitigate against operational risks
• CESUL SPV will be granted long-term Concession under Mozambique law– Terms and conditions of the Concession need to be confirmed, including a
Transmission / Wheeling charge methodology supportive of limited recourse project financing structures (part of mandate of Financial & Legal Adviser)
– Relationships to EDM (as National Power Transmission Grid Manager), HCB, Motraco and other stakeholders must be clarified and formalised to ensure timely implementation of CESUL
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
51
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Skills and training requirements
Management of CESUL Transmission Company • Maintenance Management System Training
Staff of new Dispatch Centres • Operator training• Maintenance engineers and technicians: hardware, software and communication
equipment training
HVDC and SVC Staff• Project engineers, operation managers, control and protection specialists• Engineers responsible for HVDC and SVC control and protection• Technicians maintaining HVDC and SVC equipment• Operators for HVDC link, remote and local control
Maintenance staff of CESUL Transmission Company • Maintenance engineers and technicians: fault tracing and preventive maintenance
of HVAC substations, as well as live-line maintenance
Key staff should be in place and be trained during Project construction phaseComplementary external maintenance support by suppliers is recommended
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
52
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Control centre requirements
New Control Centres• Generation and load growth in North/Central area• System expansion, load growth and interface with
SAPP in South area
• Hence, two (2) new National Control Centres are proposed
Location• New NCC in (or near) Maputo SS• New SNCC in (or near) Matambo SS
• Each CC equally equipped to be able to act as full back-up for the other
• Existing Maputo RCC gradually transformed to Distribution CC for Maputo area
Manning• Operation, each centre continuously manned with:
− One chief operator and two assistant operators
• Maintenance, each centre manned with:− One chief and two assistant SCADA maintenance
engineers (in SNCC two assistant only) plus two telecom technicians
© Vattenfall AB
53
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Feasibility Study – CESUL Feasibility Study –
Conclusions & RecommendationsConclusions & Recommendations
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
54
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL Feasibility Study – Conclusions1. CESUL is found to be technically and economically viable
2. Recommended Phase 1 design is a combined HVAC (400 kV) and HVDC (500 kV bi-pole) solution with high reliability, at a total cost of US$2,119m (funding requirement of ~US$2,780m), providing a transmission capacity >3,000 MW
3. HVAC solution will ensure interconnection of central and southern parts of national grid, allowing for economic & social development along line route
4. Phase 1 solution is considered economically and financially robust, based on large-scale export of hydropower to South Africa, with significant revenue to GoM
5. Phase 1 facilitates implementation of MPNK and CBNB, with both projects found to be economically and financially viable in combination with CESUL solution
6. HVDC portion of CESUL Phase 1 can be implemented in two stages, allowing for staggered realisation of MPNK and CBNB if required (with MPNK assumed to be the first major hydropower development)
7. Phase 1 implementation is expected to take 59 months (of which 42 months construction time)
8. Financing requirements for CESUL Phase 1 are significant, with need for close coordination of generation and transmission developments to manage commercial and timing risks
9. CESUL can be expanded by adding 2nd bi-pole with capacity of 2,650 MW
© Vattenfall AB
Klicka här för att ändra format på underrubrik i bakgrunden
55
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
CESUL – Recommendations and Next Steps
i. Based on a targeted commercial operations date for MPNK by 2017, CESUL project preparation work has to commence early 2012 by progressing design, procurement and contracting arrangements
ii. In parallel, recommended legal, financial and commercial structures and arrangements need to be finalised
iii. Financial close of CESUL should be targeted for mid-2013 (to align with generation project timeframes)
iv. Early confirmation of CESUL equity sponsors (in addition to EDM) will be key to successful development
v. Timely and coordinated engagement with South Africa (Government and Eskom) will also be essential
vi. Consideration may be given to creation of a Mozambique Joint Coordination Committee for CESUL and associated hydropower projects
© Vattenfall AB
56
Technical & Economic Feasibility Study for Mozambique Regional Transmission Backbone Project (“CESUL”)
Obrigado / ThankObrigado / Thank you for your attention!you for your attention!
com energia construimos futuro………com energia construimos futuro………