Week 11 Review
![Page 2: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/2.jpg)
Mechanical Components have been ordered and should arrive by Week 1 of winter quarter
Outstanding electrical components dependent on varying mechanical parts
Working on methods to attach and store electrical components (due Week 1 winter)
Test plans have been created for each component, will be ready to complete upon arrival
Current State
![Page 3: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/3.jpg)
Updated Specifications*Minimum Life Until Failure: As part of the design and testing process teams
should consider ways to prove an expected life as listed. Previous tests on
the device or tests conducted on components in a similar application will be acceptable. Methods of superposition
or extrapolation of high wear components may also be considered.
![Page 4: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/4.jpg)
Project Plan: Week 3
![Page 5: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/5.jpg)
Project Plan: Current
![Page 6: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/6.jpg)
Project Plan: Current
![Page 7: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/7.jpg)
Project Plan: Current
![Page 8: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/8.jpg)
Electrical component selection will be finalized when verify mechanical component testing
Outstanding purchased parts◦ electrical components for PCB and battery◦ Steel for attachment◦ Need to verify electronic attachment
Testing plan- need to verify power terrain, how to determine speed, full system testing
Project Plan: Unfinished Tasks
![Page 9: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/9.jpg)
Project Plan: MSD II
![Page 10: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/10.jpg)
Risk Assessment: Week 3
![Page 11: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/11.jpg)
https://edge.rit.edu/edge/P13002/public/Project%20Review
Risk Assessment: Current
![Page 12: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/12.jpg)
Added individual owners to all risk items Risk items more specialized, before was a
generalization Added specific tasks once finalized the
system architecture with the locking mechanism
Customer needs have been identified, should be met based on current design
Risk Assessment: Improvements
![Page 13: Mechanical Components have been ordered and should arrive by Week 1 of winter quarter Outstanding…](https://reader036.fdocuments.in/reader036/viewer/2022070616/5a4d1c127f8b9ab0599f7712/html5/thumbnails/13.jpg)
Notes from Meetings◦ General Meetings https://
edge.rit.edu/edge/P13002/public/Meetings%20by%20Date
◦ Feedback from Reviewshttps://
edge.rit.edu/edge/P13002/public/Meeting%20Notes/2012-10-05%20Systems%20Design%20Review.pdf
https://edge.rit.edu/edge/P13002/public/Meeting%20Notes/2012-11-01%20Detailed%20Design%20Review.pdf
Edge Documentation