u NORTH & EAST POST CONFLICT RESETTLEMENTS PILOT WASH PROJECT IN TRINCOMALEE DISTRICT PROGRESS OF PROJECT ACTIVITIES Exposure and Experience sharing visit Holiday Inn, Polonnaruwa 20 th & 21 st of July 2012

Transcript of Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified...

Page 1: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

u

NORTH & EAST POST CONFLICT RESETTLEMENTS PILOT WASH PROJECT IN

TRINCOMALEE DISTRICT

PROGRESS OF PROJECT ACTIVITIES

Exposure and Experience sharing visit Holiday Inn, Polonnaruwa

20th & 21st of July 2012

Page 2: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

Hygiene Programme School level – Hygiene awareness

programmes Sub Project

Area

School Identified Programmes

Progress

Killiveddy T/M/U/ Killiveddy Maha Vidyalayam

Awareness Programme

Art/ Essay Competition

Neelapola T/ Neelapola Vidyalayam

Awareness Programme

Art/ Essay Competition

Kumburupity East

T/Kumburupity East Junior School

Awareness Programme

Street Drama

Namalwatte T/ Namalwatte Vidyalayam

Awareness Programme

Art/ Essay Competition

Mahadiwulwewa Stage I

T/ Mahadiwulwewa Maha Vidyalayam

Awareness Programme

Street Drama

Backmeegama

T/ Medawatchiya Vidyalayam

Awareness Programme

Art/ Essay Competition

Page 3: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

Village level - Hygiene Awareness Programme

NO Sub Projects Planned Dates

1 Mahadiwulwewa 02.08.2012

2 Navatchcholai 06.08.2012

3 Killiveddy 08.08.2012

4 Backmeegama  

10.08.2012

5 Neelapola 09.08.2012

6 Namalwatte 13.08.2012

Page 4: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

Sanitation

No

Name of Sub Project

Phase I

Phase II

Progress

1 Killiveddy 40 22 40 pits have been dug & 1 pit has been constructed

2 Neelapola 25 46 25 pits have been dug & 1 pit has been constructed

3 Kumburupity East

40 19 40 pits have been dug

4 Namalwatte 21 38 18 pits have been dug

5 Mahadiwulwewa Stage I

43 30 40 pits have been dug

6 Backmeegama 36 29 33 pits have been dugNote : Fund will be released to WUA on 24/07/2012

Page 5: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

School Sanitation ProgrammeSub Project

AreaSchool

Submission of

Proposals

Acceptance from ZED

Killiveddy T/M/U/ Killiveddy Maha Vidyalayam

√ √

Neelapola T/ Neelapola Vidyalayam

√ √

Kumburupity East

T/Kumburupity East Junior School

√ √

Namalwatte T/ Namalwatte Vidyalayam

√ √

Mahadiwulwewa Stage I

T/ Mahadiwulwewa Maha Vidyalayam

√ √

Backmeegama T/ Medawatchiya Vidyalayam

√ √

Note : Preparation of detailed estimate in progress

Page 6: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

Training and Documentation

Submitted of Resource profiles of six sub project areas to PMU

Submitted reports of hygiene awareness programmes which were conducted in six schools

Conducted financial Management training for members of WUA

Page 7: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

Water Supply

NO Sub ProjectsIdentification of sub project boundaries

Water supply Beneficiaries

1 Mahadiwulwewa Completed 260

2Navatchcholai Completed 269

3 Killiveddy Completed 195

4 Backmeegama  

Completed 222

5 Neelapola Completed 202

6 Namalwatte Completed 199

  Total 1347

Page 8: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

No

Activity Progress

Killiveddy Navatsolai

Mahadiwulwewa

Backmeegama

Neelapola

Namalwatte

1 Identification of Water Sources

√ √ √ x x √

2 Pumping test √ √ √ x x √

3 Clearance for land for intake well and the source

In progress

4 Environmental Protection

In progress

5 Availability of electricity for the intake (Distance )

400 m 200m 150 m

150m

Page 9: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

DesignSub Project area

Preparation of technical Drawings

Preparation of BOQ

Tender Documents

Killiveddy In Progress Completed Completed

Navatchcholai Completed Completed Completed

Mahadiwulwewa

In Progress In Progress In Progress

Backmeegama

Neelapola

Namalwatte In Progress In Progress In Progress

Page 10: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.

Status of maintenance of documents at sub Project level

TaskKilliveddy

Navatsolai

Mahadiwulwewa

Neelapola

Namalwatte

Log Book √ √ √ √ √

Cash Register

√ √ √ √ √

Receipt book

√ √ √ √ √

Name board

√ √ √ √ √

Distribution of resource profile

x x x x x

Page 11: Hygiene Programme School level – Hygiene awareness programmes Sub Project Area SchoolIdentified Programmes Progress Killiveddy T/M/U/ Killiveddy Maha.