Westbury UFSDCapital Improvements Program

Construction Update

July 10, 2019

• High School Program– Review of Project Scope– Renderings of Facility– Construction Update– Minority / Women / Local Business Involvement

• Middle School Program– Review of Project Scope– Renderings of Facility– Construction Update (Roofing Project / Additions & Alterations)

Presentation Overview

• 14 classroom addition• Cafeteria addition with warming kitchen and connecting

link to existing building • Science Lab Alterations • Boilers, pumps and controls• Floors and ceilings• Site Work – parking lot modifications• Masonry Restoration – areas of work impact • Upgrade Electrical Service

Project Scope for HS

EVT-1 EVT-2

T-1 T2

TERRAZZO BASIS OF DESIGN

T4

EVT-2EVT-3

T3

EVT-3

Terrazzo Basis of Design1 3884 FROST -FORBO MARMOLEUM FRESCO

2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE

33736 GREEN SHIMMER -FORBO MARMOLEUM

CONCRETE T-4 3711

CLOUDY SAND -FORBO MARMOLEUM CONCRETE

Enhance Vinyl TileEVT-1 AD521 LIMO -ALTRO DOLCE TILE

EVT-2 AD512 LECHE -ALTRO DOLCE TILE

EVT-3 AD605 CILANTRO -ALTRO DOLCE TILE

LS-3LS-2

T-1 T2

TERRAZZO BASIS OF DESIGN

T4

LS-1

T3

Terrazzo Basis of Design1 3884 FROST -FORBO MARMOLEUM FRESCO

2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE

33736 GREEN SHIMMER -FORBO MARMOLEUM

CONCRETE T-4 3711 CLOUDY SAND -FORBO

MARMOLEUM CONCRETE

Sheet LinoleumLS-1 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE

LS-2 3240 WILLOW -FORBO MARMOLEUM CONCRETE

LS-3 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE

Cladding Panel SystemPRODEX CREAM -PRODEMA PANELS

Brick Veneer / Thin BrickPENNSYLVANIA MOLDED -BERKS WATSONTOWN BRICK COMPANY

Thin Cast LimestoneSMOOTH OAK RIDGE RENAISSANCE MASONRY UNITSARRISCRAFT INTERNATIONAL BUILDING STONE

• Poured concrete for footings and foundation walls for Classroom Addition

• Installed in-ground sanitary plumbing piping and electrical conduits in preparation of concrete slab at Classroom Addition

• Placed and compacted soil and stone bed in preparation for concrete slab pour

• Installed vapor barrier and slab reinforcement• Poured concrete slab for Classroom Addition• Received delivery for cold metal framing and commenced work

on perimeter walls

Construction Update

• Performed abatement and demolition of boilers: 66%• Formed and poured concrete pads for new boilers: 66%• Received boiler sections and relocated material to boiler room

for assembly• Existing sanitary system at Cafeteria Addition remediation: 100%• Installation of new sanitary structures and interconnecting

piping at Cafeteria Addition: 95%• Commenced excavation for foundation walls at Cafeteria

Addition

Construction Update

• Termination of feeders at new transformer in driveway: 60%• PSEG installed pole for new electrical service to transformer• Delivered new panelboards to electric room in basement• Commenced asbestos abatement operations at 2nd floor

classrooms• New Storm Drainage Installation: 60%• Working on drainage system for new courtyard by locker room• Completed foundations and concrete slab for East Connecting

Corridor

Construction Update

Classroom Addition – Prep for Pour

Classroom Addition – Slab Pour

Cafeteria Addition – Sanitary System

Boiler Room Operations – Demo & Assembly

Classroom Addition – Interior and Exterior Wall Framing

Electrical Service – Installation of New Transformer Vault

Electrical Service – Switchgear and Conduit Runs

Minority / Women / Local Business Involvement

Elite Construction has been actively meeting with each contractor on a weekly basis to examine their contract and workforce program. The contractors and consultants affiliated with the project are making a “Good Faith Effort” to achieve the District’s goals. • As the project continues, different skills will be required and

personnel currently assigned to the project will be modified accordingly.

• Individuals are required to obtain their OSHA 10 hour certification and provide to our office.

• Individuals are also required to be part of the Local Unions that will man this project: (Carpenters, Brick Masons, Laborers, Abatement, Plumbing, Mechanical, Electrical )

Minority / Women / Local Business Involvement

• VRD Contracting, Inc. – General Construction (WBE)– A&S Rebar, Inc. – Rebar Supplier (WBE)– Baybrent Construction – Ceramic Tiling (MBE)– Linda Lee Construction - Taping (WBE)– Park Ave Building Materials – Bldg Materials (MBE)– Island Nursery – Landscaping (WBE)

Minority / Women / Local Business Involvement

•Thermo Tech Combustion – Mechanical (HVAC)– DemoTec Mechanical – Boiler Demolition (WBE)

• WHM Plumbing & Heating, Inc.– Plumbing– AMG Demolition – Hot Water Tank Removal (WBE)

• Roland’s Electric, Inc. – Electrical & Fire Alarm– Advance Sound Co – PA/ Clocks / Smartboards (WBE)– CMT Lighting Co. – Lighting Supplies (WBE)

Minority / Women / Local Business Involvement

• 12 classroom addition with connection to existing building• Café addition-standard construction• Alterations to existing kitchen/cafeteria• Roof replacement and masonry• Mechanical system: replacement and abatement• Plumbing with abatement• Alterations-Increase corridor width, handicapped toilets

and handicapped access throughout building

Project Scope for MS

• P/A intercom, clocks, security, F/A• Ceilings, floors, and casework in all spaces• Site Work to include parking lot reconstruction• Upgrade Electrical Service• Abatement in Crawl Space, Floors & Ceilings

Project Scope for MS

Wiedersum

Associates

Architects

PERSPECTIVE VIEW 1

Wiedersum

Associates

Architects

PERSPECTIVE VIEW 2

Wiedersum

Associates

Architects

PERSPECTIVE VIEW 3

• Middle School Existing Roof Replacement Project– Contract was awarded to Niko K Construction– Work is scheduled to commence on July 15, 2019– Contract is scheduled for Summers of 2019 and 2020– Contract requires abatement, masonry reconstruction and roof

replacement of all existing surfaces– Requires coordination with prime contractors on Middle School

Additions and Alterations Project• Middle School Additions and Alterations Project

– Project is currently out of bidding– Bids due date to be established; Anticipate bid opening prior to

August 31, 2019

Construction Update

Westbury UFSDCapital Improvements Program

Construction Update

Question and Answer