PENNDOT PROJECT INFORMATION
West Carson Street
BettermentSR 0837, Section A48
City of Pittsburgh, Allegheny County
PROJECT TEAM
Design Division
Direct questions to:
Anthony C. Annett, P.E. - Project Manager at 412.429.5030 or anannett@pa.gov.
Mark J. Young - District Environmental Manager
Todd C. Crouch - Assistant District Environmental Manager
Press Office
Steve Cowan - District Press Officer
Please complete survey at end of presentation
PURPOSE OF PRESENTATION & PROJECT INTRODUCTION
SR 0837, Section A48 (West Carson Street) Project
The purpose of this presentation is to introduce the project to the public, gather feedback, and present the construction staging
The purpose of the project is to rehabilitate the existing deteriorated roadway surface and extend the usable life of the pavement
PROJECT LOCATION
Start Work
Stop Work
PROPOSED PROJECT IMPROVEMENTS
Roadway Rehabilitation from Smithfield Street to the West End Bridge
Concrete Reconstruction from Smithfield Street to Station Square Drive
Milling and Resurfacing from Station Square Drive to the West End Bridge
Curb repairs, drainage improvements, updates to Department signs and pavement markings, Traffic Signals, ADA Curb Ramps and ITS equipment.
Work will occur during both daylight and nighttime hours
All work will be done within existing Legal Right-of-Way.
Construction anticipated to begin 2019
PROPOSED TRAFFIC CONTROL
Long-term Lane Restrictions
SR 837 West Carson Street Concrete Reconstruction through Station Square
Short-term Lane Restrictions
SR 837 West Carson Street Milling and Resurfacing
Traffic Signals, Curb repairs, Drainage Improvements, ADA Curb Ramps.
Overnight detours
SR 8039 (Ft. Pitt Bridge Ramps to/from SR 837 West Carson Street)
SR 3106 (Ramps to/from SR 51 West Carson Street)
Example short-term restriction
SR 3106 SB (Ramp from SR 51)DETOUR PLAN
SR 3106 Eastbound Workzone
SR 3106 Eastbound Detour RouteDetour Length – 0.3 miles
SR 3106 SB
Traffic Flow
SR 3106 NB (Ramp to SR 51)DETOUR PLAN
SR 3106 Westbound Workzone
SR 3106 Westbound Detour RouteDetour Length – 0.3 miles
SR 3106 NB
Traffic Flow
SR 8039 (Ramp from SR 376 WB Ft Pitt Bridge to SR 837 NB) DETOUR PLAN
SR 8039 Workzone
SR 8039 to SR 837 NB Detour RouteDetour Length – 3.3 miles
SR 8039
Traffic Flow
SR 8039 (Ramp to SR 376 EB Ft Pitt Bridge from SR 837 SB) DETOUR PLAN
SR 8039 Workzone
SR 8039 to Ft. Pitt Bridge Detour RouteDetour Length – 3.2 miles
SR 8039
Traffic Flow
NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)
Public outreach begins with PennDOT Connects and extends into the NEPA (National Environmental Policy Act) process:
NEPA requires agencies to integrate environmental values into their decision-making processes by considering the environmental impacts of their proposed actions and reasonable alternatives to those actions
NEPA also includes public involvement activities and gathering feedback from the public
Image courtesy of MDOT
PROJECT SURVEY
https://www.surveymonkey.com/r/XVDYHZF