Tonight’s Agenda
•Discuss Rt. 28 Corridor & I-66 Interchange•What has been done•Projects currently underway•Preliminary Study•Next Steps•Questions/Answers/Comments
3
Rt. 28 Corridor & I-66 Interchange
Rt. 28 Corridor & I-66 Interchange
4
Efforts Currently Underway
Efforts Currently Underway
• WB 66 to NB 28 Ramp Extension
• Extend dual left turn SB 28 to EB 66
• Preliminary Interchange Study
Preliminary Study
5
Process:
• Identify interchange alternatives
• Concept level operational analysis
• Develop cost estimate
• Identify key implementation constraints
6
Preliminary StudyPreliminary Study
Considerations:
• Traffic Volumes (2040)• FCPA Property Right-of-Way Impacts• FCPA Property Access• Braddock & Walney Roads• Community Concerns• Existing Facility in SW quadrant of interchange• Possible phasing opportunities
Next Steps
• Work through the Preliminary Study
• Share study with the community and stakeholders
• Identify funding
8
Questions/Answers and Comments
Please send email to:Meeting_Comments@VDOT.Virginia.gov
• Be sure to include “Route 28/I-66” in the subject line.
• Comments due within 30 days (by June 29, 2012)
We look forward to hearing from you!