US-CMS User Facilities
Vivian O’Dell
US CMS Physics Meeting May 18, 2001
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 2
User Facility HardwareUser Facility HardwareTier 1:
CMSUN1 (User Federation Host) 8 400 MHz processors with ~ 1 TB RAID
Wonder (User machine) 4 500 MHz CPU linux machine with ¼ TB RAID
Production farm Gallo, Velveeta: 4 500 MHz CPU linux servers with ¼ TB
RAID each 40 dual CPU 750 MHz linux farm nodes
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 3
Popcrn01 - popcrn40
GALLO,WONDER,VELVEETA, CMSUN1
WORKERS: SERVERS:
CMS ClusterCMS Cluster
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 4
Prototype Tier 2 StatusPrototype Tier 2 Status
1. Caltech/UCSD Hardware at Each Site
20 dual 800MHz PIII’s, 0.5 GB RAM Dual 1GHz CPU Data Server, 2 GB RAM 2 X 0.5 TB fast (Winchester) RAID (70 MB/s sequential) CMS Software installed, ooHit and ooDigi tested.
• Plans to buy another 20 duals this year at each site.See http://pcbunn.cacr.caltech.edu/Tier2/Tier2_Overall_JJB.htm
2. University of Florida 72 computational nodes
Dual 1GHz PIII 512MB PC133 MHz SDRAM 76GB IBM IDE Disks
Sun Dual Fiber Channel RAID Array 660GB (raw) Connected to Sun Data Server Not yet delivered. Performance numbers to follow.
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 5
Tier 2 Hardware Status (CalTech)Tier 2 Hardware Status (CalTech)
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 6
UF Current (“Physics”) TasksUF Current (“Physics”) Tasks
Full digitization of JPG Fall Monte Carlo Sample..Fermilab, CalTech & UCSD are working on thisFermilab is hosting the User Federation (currently 1.7 TB)Full sample should be processed (pileup/nopileup in ~1-2
weeks(?)) Of course things are not optimally smooth
For up to date information see:http://computing.fnal.gov/cms/Monitor/cms_production.html
Full JPG sample will be hosted at FermilabUser Federation Support
Contents of the federation and how to access it is at the above url. We keep this up to date with production.
JPG NTUPLE Production at FermilabYujun Wu and Pal Hidas are generating the JPG NTUPLE
from the FNAL user federation. They are updating information linked to the JPG web page.
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 7
Near Term PlansNear Term PlansContinue User Support
Hosting User Federations. Currently hosting JPG federation with combination of disk/tape (AMS server <-> Enstore connection working). Would like feedback.
Host MPG group User Federation at FNAL? Continue JPG ntuple production, hosting and archiving
Would welcome better technology here. Café starting to address this problem.
Code distribution support
Start Spring Production using more “grid aware” tools More efficient use of CPU at prototype T2’s
Continue commissioning 2nd prototype T2 centerStrategy for dealing with new Fermilab Computer Security
Means “kerberizing” all CMS computing Impact on users!
Organize another CMS software tutorial this summer(?) coinciding with kerberizing CMS machines Need to come up with a good time. Latter ½ of August before CHEP01?
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 8
T1 Hardware StrategyT1 Hardware StrategyWhat we are doing
Digitization of JPG fall production with Tier 2 sitesNew MC (spring) production with Tier 2 sitesHosting JPG User Federation at FNAL
For fall production, this implies ~4 TB storage (e.g. ~1 TB on disk, 3 TB on tape).
Hosting MPG User Federation at FNAL? For fall production, this implies ~4 TB storage (~ 1 TB disk, 3 TB tape)
Also hosting User Federation from spring production, AOD or even NTUPLE for users
Objectivity testing/R&D in data hostingWhat we need
Efficient use of CPU at Tier 2 sites – so we don’t need additional CPU for production
Fast, efficient, transparent storage for hosting user federation Mixture of disk/tape
R&D for RAID/disk/OBJY efficient matching This will also serve as input to RC simulation
Build & operate R&D systems for analysis clusters
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 9
Hardware Plans FY01Hardware Plans FY01
We have defined hardware strategy for T1 for FY2001.
~ Consistent with project plan and concurrence from ASCB.Start User Analysis Cluster at Tier 1. This will also be an
R&D cluster for “data intensive” computing.Upgrade networking for CMS clusterProduction User Federation Hosting for physics groups
(more disk/tape storage)Test and R&D systems to continue path towards full
prototype T1 center. We are focusing this year on data server R&D systems.
Have started writing requisitions. Plans to acquire most hardware over the next 2-3 months.
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 10
FY01 Hardware Acquisition OverviewFY01 Hardware Acquisition Overview
Item Cost
Networking: 52,000GE for all data servers, FE for worker nodes,
Switch Chasis with 256 Gbps backplane
Test systems: 101,500Sun dataserver + RAID test system 48,500
Production test system (8 worker nodes cluster) 53,000
Analysis cluster (8 dual nodes + disk/data server) 53,000
Data Access and Distribution Servers 135,0002 linux data servers 32,000
4 TB RAID (various technologies) 103,000
Add'l Disk Data Storage for User Federation 45,000
Support (video/computing) 10,000
Total 396,500
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 11
Funding Proposal for 2001Funding Proposal for 2001
WBS Item 2001
1.5.1 Onsite Networking 52,000
1.6.1 Distributed Data & Computing testbeds 48,500
1.6.2.2.1 Data Intensive Computing 53,000
1.6.2.2.3 Data Access and Distribution Servers (6 TB) 188,000
1.7.2 Data Storage 45,000
1.7.4 Data Import/Export 0
1.8.1 Desktop Support 10,000
Total 396,500
Some costs may be overestimated – (but) also we may need to augment our farm CPU
May 18, 2001 Vivian O’Dell, US CMS User Facilities Status 12
SummarySummary
User facility has a dual missionSupporting Users
Mostly successful (I think) Open to comments/critiques and requests!
Hardware/Software R&D We will be concentrating on this more over the next year This will be done in tandem with T2 centers and international
CMS
We have developed a hardware strategy taking these two missions into account
We now have 2 prototype Tier 2 centers.CalTech/UCSD have come onlineUniversity of Florida is in the process of
installing/commissioning hardware