FILL MATERIAL AND COMPACTION

PROPOSED KIOSK SUBSTATION PRECAST PADSCHNEIDER ELECTRIC 415kVA TRANSFORMER

Mobile: 0427 411 633 Email: ntce@westnet.com.au

Engineers

Consulting

Northern Territory, Australia

P.O. Box 900

COOLALINGA 0839

ABN 73 102 631 186

N.T. Consulting Engineers

TOP VIEW

SL92 MESH 50 mm

BTM COVER

2600

KIO

SK

S

UB

ST

AT

IO

N 4

45

0

46

50

300

1940

360

37

25

50

25

74

69

04

64

SCHNEIDER

A

173

1820607

DEFENCE KIOSK

SECTIONSCALE: 1:50

TYPICAL

A

_

CONCRETE

CURE CONCRETE AT AMBIENT ENVIRONMENT FOR A

PERIOD OF 21 DAYS OR UNTIL CONCRETE PEACHES 70%

OF STRENGTH SPECIFIED. SOME CRACKING OF

CONCRETE SLABS IS ANTICIPATED. THIS CRACKING WILL

BE NON STRUCTURAL & ASTHETIC IN NATURE.

372 550 2574 690 464

16

5

90

0 m

in

PRECAST PAD

APRON SLAB

100 thk: 25 MPa

GAL SL72 MESH:

40 TOP COVER.

GENERAL NOTES

PLAN, SECTION & NOTES

NORTHERN TERRITORY OF AUSTRALIA BUILDING ACT

SECTION 40 – CERTIFICATE OF COMPLIANCE STRUCTURAL CONSTRUCTION

Revised 31/7/2014 No changes to the declaration are permitted Page 1 of 2

All sections must be completed – mark N/A to any question that does not apply

PROPERTY / PROJECT DETAILS

Owner (if known): Lot/Portion Number:

n/a

Address:

RAAF Location:

Tindall

Town / Hundred :

Katherine Description of works :

Proposed Substation PAD Building Permit Number (if known)

DOCUMENTS ATTACHED (as built drawings or latest amendments)

Drawing Nos:

NTCE Dwg No.’s U822688-S1 Inspection Records :

VARIANCES FROM DESIGN CERTIFICATE CRITERIA

COMMENTS / EXCLUSIONS (Exclusions to this Certificate must be clearly identified).

CERTIFICATION BY STRUCTURAL ENGINEER

Company Name if certification is on behalf of a company

Company NT Registration Number

I certify that reasonable care has been taken to ensure that structural engineering aspects of the works described above have been constructed in accordance with the approved plans and permit.

*Name (print clearly)

Michael Cooper

* Nominee/Individual NT Registration Number

21133ES

Signature Date

30 April 2017

Page 2 of 2

SCHEDULE OF STRUCTURAL INSPECTIONS COMPLETED

[ X ] 1. Completion of site preparation/site filling/excavations for footings prior to placement of any reinforcement

or concrete.

[ ] 2. Completion of preparations for placing of concrete strip footings including placement of reinforcement.

[ X ] 3. Completion of preparations for placing concrete slabs including compaction of fill and sand blinding,

placement of formwork, reinforcement, starter bars and cast in items.

[ ] 4. Completion of preparations for placing of concrete pier footings including reinforcement (if any).

[ ] 5. Starter bars and cast in items after placing of concrete and prior to any covering up work.

[ ] 6 Reinforcement to walls completed prior to core filling (inspection holes and cleanout cores to be completed).

[ ] 7. Structural steelwork and cold formed steelwork completed and prior to any covering up work. Floor framing

system completed before floors are laid or underside is lined.

[ X ] 8. Suspended concrete floor slabs with formwork, reinforcement and cast in items completed, prior to placing

of concrete.

[ ] 9. Wall framing or blockwork wall core filling completed (with windows fixed in place) and roof framing with

connections completed and prior to sheeting or lining.

Note: [ ] Prior lodgement of truss manufacturer’s drawings, details and certification required.

[ ] Prior lodgement of windows manufacturer’s drawings including fixings and certification required.

[ ] 10. Structural wall linings completed and prior to any covering up work.

[ ] 11. Final inspection upon completion of all structural work including fixings of external roof and wall claddings,

flashings, barges & vents.

[ X ] 12. Other Inspections