Sydenham School Residents Meeting 11-02-14. Caretakers House Demolition. Decking to STEM and ARTS. Decking to STEM and ARTS. Concrete Frame. First Floor Slab. Rebar – Second Floor. Arts First Floor - Rebar. External MUGA and Lighting Layout. Car Park - Denver Pole Luminaire 5m columns. - PowerPoint PPT Presentation

Transcript of Sydenham School Residents Meeting 11-02-14

Sydenham School

Residents Meeting11-02-14

Caretakers House Demolition

Decking to STEM and ARTS

Decking to STEM and ARTS

Concrete Frame

Arts First Floor - Rebar

Rebar – Second Floor

First Floor Slab

External MUGA and Lighting Layout

Car Park - Denver Pole Luminaire 5m

columns

MUGA - Scorpius Luminaire 8m

columns

Upcoming Works

• Brickwork/Blockwork • Continue installing pre cast walls and columns along with In-

Situ elements• Scaffolding continuing • Decking continuing along lower ARTS – F/F and upwards• Concrete Pour to upper ARTS

Thank You.Follow us