Post on 28-Jan-2018
Sunset Cove Restoration Update and Stakeholder Advocacy
Sunset Cove
12 acre site
Spectacular views of Jamaica Bay and NYC
Located at extreme south end of Broad Channel
NYC Parks land adjacent to NPS wetlands
Wetland cove and upland area
Unique Opportunity to restore Degraded shoreline area
NEXT MAJOR RESTORATION PROJECT TO BEGIN IN JAMAICA BAY
History
Small Marina since the 40’s
Marina greatly expanded thru illegal fill in 1970’s and 80’s.
Court action at both state and Federal level
Resulted in 1998 decision to reduce size
2008 decision for additional violations led to state acquisition
2008 Land put under jurisdiction of NYC DCAS
History
Broad Channel Civic Association led effort to have area deeded to NYC Parks.
Worked thru Councilman Ulrich’s office to have transferred to NYC Parks in 2009
BCCA passed unanimous resolution in February of 2010 endorsing wetlands restoration, upland forest, walking trails, boardwalk plan.
BCCA plan submitted to NYC PARKS RFEI—only plan submitted
Sunset Cove 2006
Sunset Cove 2013
DOI grant effort Post Sandy
Effort led by Broad Channel Civic Association
Letters of support obtained from
Senator Schumer ***
Congressman Meeks
Congressman Jeffries
State Senator Addabbo
Assemblyman Goldfeder
Councilman Ulrich
Federal lobbying coordinated with Harbor Coalition
Dept of Interior Grant awarded for 4.8 Million
Partners
NYC Parks
NYC DEP
NYS DEC
National Parks Service
Jamaica Bay Ecowatchers
American Littoral Society
Features of Project:
• Restoration of approximately 4 acres of low marsh.
• Restoration of approximately 0.5 acres of high marsh.
• Restoration of approximately 4 acres of scrubland.
• Restoration of approximately 3.5 acres of coastal forest.
• Restoration of approximately 1,000 linear feet of upland perimeter.
• Construction of boardwalk, outdoor classroom and perimeter walking trail/Berm and Eco-dock for student use .
Phase 1 funding
NEWIPCC EPA Grant - $60,000 State EPF Grant - $50,000 DOI NFWF Grant - $4,850,000 DEC Mitigation Payments Transco Williams - $500,000 Dept of Sanitation - $750,000 NYCDOT - $990,000 DPR - $70,000 (Beach 108 Bulkhead Project) DEP Design Contribution - $50,000
Total original Funding expectation- $7,320,000
Phase 2 Funding--
Total final cost estimate $ 1.8 Million
Funding Sources--
◦ Broad Channel CRZ NY Rising- -----$500,000◦ Queens Borough President Melinda Katz--$1,000,000◦ Assemblywoman Amato - $125,000◦ State Senator Addabbo--$ 175,000◦ Broad Channel Civic thru Participatory Budget-$200,00
* all design costs for Louis Berger firm from NY Rising
Funding shortfall
Project out for bid in May 2017
Minimum bid received 7 million short
Project in Jeopardy and DOI Funding
Ecowatchers and BCCA lobby Mayors office
Elected officials lend full support
Worked with Offic of Resiliency
October 6th Funding received from Mayors Office
Press Conference- October 6th
Sunset Cove Revised Time Frame
Phase 1—Funded/Design Completed Contractor identified /Construction to start Spring 2018
Total---$16,320,000
Phase 2- funding in Place/Design underway by Louis Berger/ Construction Spring 2019
Total funds---$1,800,000
Site plan
North site Plan with eco dock
Boardwalk and Entrance to Park –Phase 2
u
Boardwalk design using restored lumber from Rockaway Boardwalk
Shade features
SUNSET COVE
Wetlands Experience
Learning/Research
Solstice Markers
Sunset at the Cove