SunCoke Energy, Inc.

1. Overall Project Summary 2. Safety Plan 3. SunCoke Energy - Contacts 4. Bowen Engineering – Contacts 5. IEA – Contacts 6. Schedules & Logs 7. Operation Plans 8. Quality Control Plan 9. Site Plan & FGD Layout Plan 10. Challenges / Opportunities 11. Team Goals

TABLE OF CONTENTS

Project Summary

• Installation of a new FGD & Components

• Project was awarded on 11/07/08

• Project Value: $ 12,805,000.00

• Estimated start date: Dec. 12, ‘08

• Completion date: Aug. 01, ‘09

• NMA (National Maintenance Agreement) (Tab C) Extension Accepted 11/07/08

• Advance Mobilization Invoiced on 11/07/08 in the Amount of $ 1,920,750.00

Safety

• Weekly jobsite Safety Schedule• Site Specific Safety Plan • Site Specific Safety Incentive Program• JSA’s (Bowen)• Weekly Management Safety Audit• OSHA 300A / Safety Bulletin

Safety Plan

Steve Morey smorey@sunocoinc.com VP - Construction

Chris Allen cpallen@sunocoinc.com Project Manager

Steve Van Nest svannest@sunocoinc.com Director – Contracts

Mohammed Noor namohammed@sunocoinc.com Project Controls

David Kramer djkramer@sunocoinc.com Project Superintendent

Robert Bennett rlbennett@sunocoinc.com Project Finance

SunCoke Key Contacts

CONTACT INFORMATION Contact Office # Cell # Email

Jeff Purdue – Southern District Manager 812-475-3880 812-305-3775 jeff@bowenengineering.com

Aaron Purdue - Operations Manager 812-475-3880 812-305-3769 apurdue@bowenengineering.com

Robert Redden – Site Manager 812-475-3880 317-502-8975 rredden@bowenengineering.com

Roger Havil – Project Superintendent 812-475-3880 812-305-6150 rhavil@bowenengineering.com

Marc Reynolds – Project Engineer 812-475-3880 812-483-8768 mreynolds@bowenengineering.com

Tami Silver – Project Coordinator 812-475-3880 812-306-5829 tsilver@bowenengineering.com

Org Chart

Contact Information:

Portland, Maine - IEA Headquarters27 Pearl Street, Suite 1Portland, ME 04101

207-541-5800207-775-0936 (Fax)

Louis Asali - lasali@ieaenergy.com – Program Manager

Martin Rilling - mrilling@ieaenergy.com – Project Manager - (207) 329-3705

Edwin Weddeke - eweddeke@pssanders.com – Project Coordinator - (407) 637-9954

OPERATION PLANS

Quality Control Plan

Elevation – All elevations will be double checked by both the Foremen and Engineer and verified against the existing drawings & control

points.

Materials – Confirm Owner Supplied Materials & Damage

Foundation & Slab Quality – • Check all anchor bolts prior to erecting any material.• Check concrete Slab/Foundation elevations.• Establish work area and lay-down areas.

Challenges / Opportunities

Challenges

• Zero Injuries & Accidents• Meet and or beat Schedule & Budget• Gain knowledge of local work force• Working in a confined area• Critical Lifts• Weather

Opportunities• Build stronger SunCoke Energy

relationship thru collaboration & creativity to reduce time & effort.

• Reuse gang panels & miscellaneous tools from completed projects to enhance our budget.

• Utilize learning curve from completed projects to make professional decisions affecting schedule & Budget.

• Obtain additional work from SunCoke.

Team Goals

• Complete this project with ZERO recordable incidents and or accidents

• Become the best contractor SunCoke has ever had on their sites

• Complete this project ahead of schedule and budget• Insure our integrity and core values are portrayed in

all aspects• Utilize our good relationships to gain future work