Planned Progress % Actual Progress % Variance % Ahead/Behind

Elevators 71.42% 8.41% -63.01% Behind

Residential Tower N4 76.11% 11% -65% Behind

Residential Tower N3 61.94% 11% -51% Behind

Residential Tower N2 58.33% 11% -47% Behind

Residential Tower N1 59.50% 11% -49% Behind

Residential Tower S3 80.00% 11% -69% Behind

Residential Tower S2 73.67% 11% -63% Behind

Residential Tower S1 88% 11% -77% Behind

Hotel Tower H1 74.86% 0% -75% Behind

Hotel Tower H2 71.53% 0% -72% Behind

Planned Progress % Actual Progress % Variance % Ahead/Behind

Elevators 71.42% 8.41% -63.01% Behind

Residentials 70.88% 11% -60% Behind

Hotel 73.19% 0% -73% Behind