Summary of Previous Lecture Understand why ranking project proposals on the basis of IRR, NPV, and...

Post on 18-Jan-2018

218 views 0 download

description

Learning Outcomes After studying Chapter 14 you should be able to: Define the "riskiness" of a capital investment project. Understand how cash-flow riskiness for a particular period is measured, including the concepts of expected value, standard deviation, and coefficient of variation. Describe methods for assessing total project risk, including a probability approach and a simulation approach. Judge projects with respect to their contribution to total firm risk (a firm-portfolio approach). Understand how the presence of managerial (real) options enhances the worth of an investment project. List, discuss, and value different types of managerial (real) options.

Transcript of Summary of Previous Lecture Understand why ranking project proposals on the basis of IRR, NPV, and...

Summary of Previous Lecture

• Understand why ranking project proposals on the basis of IRR, NPV, and PI methods “may” lead to conflicts in ranking.

• Describe the situations where ranking projects may be necessary and justify when to use either IRR, NPV, or PI rankings.

• Understand how “sensitivity analysis” allows us to challenge the single-point input estimates used in traditional capital budgeting analysis.

• Explain the role and process of project monitoring, including “progress reviews” and “post-completion audits.”

Chapter 14 (I)

Risk and Managerial (Real) Options in Capital

Budgeting

Learning OutcomesAfter studying Chapter 14 you should be able to:• Define the "riskiness" of a capital investment project. • Understand how cash-flow riskiness for a particular period is

measured, including the concepts of expected value, standard deviation, and coefficient of variation.

• Describe methods for assessing total project risk, including a probability approach and a simulation approach.

• Judge projects with respect to their contribution to total firm risk (a firm-portfolio approach).

• Understand how the presence of managerial (real) options enhances the worth of an investment project.

• List, discuss, and value different types of managerial (real) options.

Risk and Managerial (Real)Options in Capital Budgeting

• The Problem of Project Risk• Total Project Risk• Contribution to Total Firm Risk: Firm-

Portfolio Approach• Managerial (Real) Options

Expectation and Measurement of Dispersion

Probability distribution can be explained in two parameters of distribution; (1) The expected Value, (2) the standard deviation.Expected value is the weighted average of possible outcomes, with weights being probabilities of occurrence.Standard deviation is the statistical measurement of the variability of a distribution around its mean.

Coefficient of Variation (CV)

SD sometime can be misleading in comparing the risk or uncertainty. CV is the ratio of the SD of a distribution to the mean of that distribution. It is a measure of relative risk. Smaller the CV, the lesser the risk. A project with lower CV is better.

Discrete and Continuous DistributionIn the discrete case, one can easily assign a probability to each possible outcome: when throwing a die, each of the six values 1 to 6 has the probability 1/6. a continuous random variable is the one which can take a continuous range of values — as opposed to a discrete distribution, where the set of possible values for the random variable is at most countable. While for a discrete distribution an event with probability zero is impossible (e.g. rolling 3½ on a standard die is impossible, and has probability zero), this is not so in the case of a continuous random variable. For example, if one measures the width of an oak leaf, the result of 3½ cm is possible

http://en.wikipedia.org/wiki/Probability_distribution

An Illustration of Total Risk (Discrete Distribution)

ANNUAL CASH FLOWS: YEAR 1PROPOSAL A

State Probability Cash Flow

Deep Recession .10 $ 3,000Mild Recession .20 3,500Normal .40 4,000Minor Boom .20 4,500Major Boom .10 5,000

Probability Distribution of Year 1 Cash Flows

.1Prob

abili

ty

3,000 3,500 4,000 4,500 5,000

Cash Flow ($)

Proposal A

.2

.3

.4

Expected Value of Year 1 Cash Flows (Proposal A)

CF1 P1 (CF1)(P1)3000 0.1 3003500 0.2 7004000 0.4 16004500 0.2 9005000 0.1 500

Σ = 1 4000CF =

(CF1)(P1) (CF1 - CF1)2(P1)

$ 300 (3,000 - 4,000)2 (.01) 700 (3,500 - 4,000)2 (.20) 1,600 (4,000 - 4,000)2 (.40) 9,000 (4,500 - 4,000)2 (.20) 500 (5,000 - 4,000)2 (.01)

$4,000

Variance of Year 1 Cash Flows (Proposal A)

(CF1)(P1) (CF1 - CF1)2(P1)

$ 300 100000 700 50,000 1,600 0 9,000 50,000 500 100,000

$4,000 300,000

Variance of Year 1 Cash Flows (Proposal A)

Summary of Proposal A

The standard deviation = SQRT (300,000) = $548

The expected cash flow = $4,000

Coefficient of Variation (CV) = $548 / $4,000 = 0.14

CV is a measure of relative risk and is the ratio of standard deviation to the mean of the distribution.

An Illustration of Total Risk (Discrete Distribution)

ANNUAL CASH FLOWS: YEAR 1PROPOSAL B

State Probability Cash Flow

Deep Recession .01 $ 2,000Mild Recession .20 3,000Normal .40 4,000Minor Boom .20 5,000Major Boom .01 6,000

Probability Distribution of Year 1 Cash Flows

.1Prob

abili

ty

2,000 3,000 4,000 5,000 6,000

Cash Flow ($)

Proposal B

.2

.3

.4

Expected Value of Year 1 Cash Flows (Proposal B)

CF1 P1 (CF1)(P1)2000 0.1 2003000 0.2 6004000 0.4 16005000 0.2 10006000 0.1 600

Σ = 1 4000CF1 =

(CF1)(P1) (CF1 - CF1)2(P1)

$ 200 (2,000 - 4,000)2 (.10)

600 (3,000 - 4,000)2 (.20) 1,600 (4,000 - 4,000)2 (.40) 1,000 (5,000 - 4,000)2 (.20) 600 (6,000 - 4,000)2 (.10)

$4,000

Variance of Year 1 Cash Flows (Proposal B)

(CF1)(P1) (CF1 - CF1)2(P1)

$ 200 400,000

600 200,000 1,600 0 1,000 200,000 600 400,000

$4,000 1,200,000

Variance of Year 1 Cash Flows (Proposal B)

Summary of Proposal B

The standard deviation of A < B ($548< $1,095), so “A” is less risky than “B”.The coefficient of variation of A < B (0.14<0.27), so “A” has less relative risk than “B”.

The standard deviation = SQRT (1,200,000)= $1,095

The expected cash flow = $4,000Coefficient of Variation (CV) = $1,095 / $4,000

= 0.27

Total Project Risk

Projects have risk that may change from period to period.

Projects are more likely to have continuous, rather than discrete distributions.

Cash

Flo

w ($

)

1 2 3 Year

Probability Tree Approach

A graphic or tabular approach for organizing the possible cash-flow streams generated by an investment. The presentation resembles the branches of a tree. Each complete branch represents one possible cash-flow sequence.

Probability Tree ApproachA project that has an initial cost today of $240. Uncertainty surrounding the first year cash flows creates three possible cash-flow scenarios in Year 1.

Probability Tree Approach

Node 1: 25% chance of a $500 cash-flow.

Node 2: 50% chance of a $200 cash-flow.

Node 3: 25% chance of a -$100 cash-flow.

-$240

(.25) $500

(.25) -$100

(.50) $200

Year 1

1

2

3

Probability Tree Approach

Each node in Year 2 represents a branch of our probability tree.

The probabilities are said to be conditional probabilities.

-$240

(.25) $500

(.25) -$100

(.50) $200

Year 1

1

2

3

(.40) $500

(.20) $200

(.40) $800

(.20) $500

(.60) $200

(.20) -$100

(.20) $200

(.40) -$100

(.40) -$400

Year 2

Joint Probabilities [P(1,2)]

.01 Branch 1

.01 Branch 2

.05 Branch 3

.10 Branch 4

.30 Branch 5

.10 Branch 6

.05 Branch 7

.10 Branch 8

.10 Branch 9

-$240

(.25) $500

(.25) -$100

(.50) $200

Year 1

1

2

3

(.40) $500

(.20) $200

(.40) $800

(.20) $500

(.60) $200

(.20) -$100

(.20) $200

(.40) -$100

(.40) -$400

Year 2

Project NPV Based on Probability Tree Usage

The probability tree accounts for the distribution of cash flows. Therefore, discount all cash flows at only the risk-free rate of return.

The NPV for branch i of the probability tree for two years of cash flows is

NPV = S (NPVi)(Pi)

NPVi = CF1

(1 + Rf )1 (1 + Rf )2

CF2 - ICO+

i = 1

z

NPV for Each Cash-Flow Stream at 8% Risk-Free Rate

$ 909 $ 652 $ 394

$ 374 $ 117-$ 141

-$ 161-$ 418-$ 676

-$240

(.25) $500

(.25) -$100

(.50) $200

Year 1

1

2

3

(.40) $500

(.20) $200

(.40) $800

(.20) $500

(.60) $200

(.20) -$100

(.20) $200

(.40) -$100

(.40) -$400

Year 2

Calculating the Expected Net Present Value (NPV)

Branch NPVi

Branch 1 $ 909Branch 2 $ 652Branch 3 $ 394Branch 4 $ 374Branch 5 $ 117Branch 6 -$ 141Branch 7 -$ 161Branch 8 -$ 418Branch 9 -$ 676

P(1,2) NPVi x P(1,2) .10 $ 91 .10 $ 65 .05 $ 20 .10 $ 37 .30 $ 35 .10 -$ 14 .05 -$ 08 .10 -$ 42 .10 -$ 68

Weighted Average = $ 116=NPV

Calculating the Variance of the Net Present Value

P(1,2) (NPVi - NPV )2[P(1,2)] .10 $ 62,885 .10 $ 28,730 .05 $ 3,864 .10 $ 6,656 .30 $ 0.30 .10 $ 6,605 .05 $ 3,836 .10 $ 28,516 .10 $ 62,726

Variance = $203,819

NPVi $ 909 $ 652 $ 394 $ 374 $ 117 -$ 141 -$ 161 -$ 418 -$ 676

Summary of the Decision Tree Analysis

The standard deviation = SQRT($20,3819) = $451

The expected NPV = $ 116

Summary

We covered following topics in today’s lecture;

• Define the "riskiness" of a capital investment project.

• Understand how cash-flow riskiness for a particular period is measured, including the concepts of expected value, standard deviation, and coefficient of variation.

• Describe methods for assessing total project risk, including a probability approach.