SUM104-Topic6 - MS Project2013 - Murat Islam

Post on 08-Aug-2015

19 views 3 download

Transcript of SUM104-Topic6 - MS Project2013 - Murat Islam

Weekly Activity Submission Form

ABERDEEN BUSINESS SCHOOL

Master of Science in Project Management (Distance Learning)

Weekly Activity Submission Form

Name:

Murat Islam

Email:

1413749@rgu.ac.uk

Course: MSc Project Management (Distance Learning)

Module:

Project Commercial Integrity

(SUM104)

Assignment and

Title:

Activity No: 6

Activity Title: Introduction to Planning Software:

Microsoft Project

Date:

27 March 2015

For the attention

of the Module

Coordinator

(SUM104):

Toni Fisher

Number of pages

in submission:

Read nos: (a) &

(b) below

Agree to both (a) & (b): Insert your Signature/Confirm

by writing your full name here: Ivan Messaggi

Before submitting ensure:

(a) That the work undertaken for this assignment is entirely your own and

that you have not made use of any unauthorised assistance;

(b) That the sources of all references material have been properly

acknowledged.

BY SUBMITTING THIS DOCUMENT YOU ARE CONFIRMING STATEMENTS (a)

AND (b) ABOVE

Schedule 0

Baseline Constraints: Work between 8am-12pm and 1pm-5pm

Schedule 1

Additional Constraints to Previous Schedule: Work between 8am-12am and 1pm-5pm and Stop on Fridays at 4pm

Schedule 2

Additional Constraints to Previous Schedule: Christmas holidays: 25-26 Dec 14 and 1-2 Jan 15

Schedule 3

Additional Constraints to Previous Schedule: Trades holiday, 2nd week in August (11-15 Aug 14)

Schedule 4

Additional Constraints to Previous Schedule: Resource X cannot work in period 22-31 Dec 14 and 1-4 Jan 15

Resource Levelling 1

Levelling Approach for the above constrained Schedule: Float only & Fixed Units

Resource Levelling 2

Levelling Approach for the above constrained Schedule: Adjusted Task Assignments

Resource Levelling 3

Levelling Approach for the above constrained Schedule: Adjusted Task Assignments and Priorities

Selected Project Schedule based on the Levelled Resources

Resource Levelling 3 with further adjustments: Adjusted Task Assignments and Priorities

An additional for Resource X (100%) to be hired and working on weekends are allowed only for Resource X at a Rate

of 1.5 x Normal Rate (£22.5/hr) between 26/11/2014 – 22/01/2015. Task K and L are based on a Weekend Calendar.

RESULT: £11,100 cost and 1week lead time increase based on the over allocated resource case. 1st and 2nd levelling

options haven’t been selected due to excessive lead time or resource allocation requirements.

Updates to Above Levelled Baseline

A As schedule B Started 2days late

C As schedule D As schedule E Finished 1 wk late

F As schedule G Finished 1 day early

H As schedule I As schedule J Started 2 days early

K 75% complete L 25% complete

M As schedule N ----

O 75% complete