Stream Restoration Projects Update - AlexandriaVA.Gov...Update September 2019. City Team 2...

Post on 29-Jul-2020

0 views 0 download

Transcript of Stream Restoration Projects Update - AlexandriaVA.Gov...Update September 2019. City Team 2...

Stream Restoration Projects Update

September 2019

City Team

2

Transportation and Environmental

Services (T&ES)

Recreation, Parks and Cultural

Activities (RPCA)

Department of Project

Implementation (DPI)

Joni CalmbacherCivil Engineer IIIStormwater Management 703.746.4174Joni.Calmbacher@alexandriava.gov

Demond FrazierCivil Engineer IV703.746.4632Demond.Frazier@alexandriava.gov

Murphy NgCivil Engineer III703.746.4699Murphy.Ng@alexandriava.gov

Syed ImranCivil Engineer III703.746.4659Syed.Imran@alexandriava.gov

Bob WilliamsDivision ChiefNatural Resources703.746.4174Bob.Williams@alexandriava.gov

Stream Restoration Program

3

1. Protect, stabilize, and improve the City’s waterways

2. Address Chesapeake Bay clean up mandates (Action Plan strategy)

3. Consistent with the City’s Environmental Sustainability Strategic Goal

Physical Chemical Biological

Benefits

Habitat

Aesthetics Bank and Channel Stability

Water Quality

Native Vegetation

Natural Characteristics

4

Typical In-Stream Structures

5

Stream Restoration Projects

• Lucky Run: ~900 LF• Strawberry Run: ~900 LF• Taylor Run: ~1900 LF

Three Current Projects

• 50/50 Stormwater Local Assistance Fund (SLAF) Grants• Lucky $668,720; Strawberry $800,000; Taylor $2.255M

Funding

• Parks and Recreation Commission• Civic Association and HOA Meetings• Public Meetings• Website• Social Media

Outreach

6

Lucky Run

7

Lucky Run

8

Lucky Run Status

100% Design Complete

Temporary Construction Easements by end of October

Invitation to bid estimated winter 2019

Construction estimated to begin spring/summer 2020

9

Archaeology and Survey Complete

Strawberry Run near Taft Avenue

10

Strawberry Run

11

Strawberry Run Status

12

60% Initial draft design is complete

Survey is complete

Phase I Archaeology complete

Phase II Archaeology to begin next month

Construction estimated to begin fall/winter 2020

Taylor Run near Chinquapin Park

13

14

Taylor Run

TaylorRun Status

15

Survey is in progress

Phase I Archaeology in progress

40% design anticipated Dec. 2019

Construction estimated to begin early 2021

Strawberry Run – Downstream Project

16

Before After