Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Prabang, Lao PDR

Post on 29-Jan-2018

636 views 1 download

Transcript of Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Prabang, Lao PDR

Presentation Team:1.Abhushan Neupane/AG Power

2.Bharat Mani Pandey/ UT-3A(NEA)

3.Surendra Dev Bhattq/Pahadi Hydro

4.Umesh Pathak/ Sanjen HEP

COUNTRY PRESENTATIONSTATUS OF HYDROPOWER IN NEPAL

Glance of Hydropower in NepalFirst Hydropower in Nepal: 1911 AD (500 Kw Pharping HEP)

Theoretical Potential: 83,000 MW

Technically Feasible: 44,000 MW

Economically Feasible: 43,000 MW

Electricity Access percentage: ~60%

Current Generation: ~ 800 MW (Mostly RoR type)

Largest Operation Hydropower: 144 MW (Kaligandaki A)

Construction Ongoing: More than 2500 MW

Largest Construction Ongoing: 456 MW (Upper Tamakoshi)

Transmission Loss percentage: ~25%

2

UTK-456MW

Sanjen(Upper) -14.8 MW

Power Map of Nepal

3

ContentsActs/Policy/GuidelinesEnergy StatusOpportunities Challenges

4

Acts/Policy/Guidelines

5

Main Legislation Governing HydropowerWater Resources Act 1992 & Regulation 1993

• Use of water for hydropower shall have priority over the use of water for cottage industries, navigation and recreation but not over the use of water for drinking and domestic use, irrigation or agriculture

Electricity Act 1992 & Regulation 1993 • Deal with management of electricity in Nepal, including the survey, generation and distribution of

electricity• Regulates the electricity sector by a system of licensing

6

Main Legislation Governing Hydropower Contd..

Hydropower Development Policy 2001• Objectives of HP-2001

• Generate electricity at low cost;• Provide reliable and quality electricity at a reasonable price;• Combine electrification with the economic activities;• Extend rural electrification; and• Develop hydropower as an export commodity

• Key Policy Provisions (HP-2001)• BOOT model• In case of multipurpose projects, GoN may participate• Environment- 10% d/s release (min)• Facilitate property acquisition

7

Main Legislation Governing Hydropower Contd..

Hydropower Development Policy 2001• Terms of License

• Survey License for 5 years• Generation License

• Internal consumption 35 years• Export Oriented 30 years• In case of reservoir 5 years extension on the basis of construction period• Captive Plant as it remains in operation

Other Important aspects of policy• Transfer of Projects

• Every hydropower project has to be transferred to the government, free of costs, after the completion of license period

8

Authorities for Hydropower Development

Major Implementing Authorities:• Ministry Of Energy (MoE)• Department of Electricity Development (DOED)• Nepal Electricity Authority (NEA)

Other Regulating Authorities: Department of Environment (DoE) Ministry of Forest

9

Other Relevant Legislation

Environment Protection Act, 1996 (2053 B.S.)

Forest Act, 1993 (2049 B.S.)

National Parks and Wildlife Conservation Act, 1973 (2029 B.S.)

Foreign Investment and Technology Transfer Act, 1992 (2049 B.S.)

Local Self-Governance Act, 1999 (2055 B.S.)

Industrial Enterprises Act, 1992 (2049 B.S.)

Land Acquisition Act, 1977 (2034 B.S.)

10

Guideline and Action PlanAction plan and concept paper for Energy Emergency Eradication decade , 2016 has

paved the ways for FDI entrance in Nepal Government Guarantees for development Foreign Currency denominated PPAs (up to Loan Repayment or 10 years) PPAs based on Take or Pay basis (Dry Energy >>30% ) No Hydrology risk up to 10 MW Provision for Hedge funds

Government has recently launched program “Nepal ko pani: Janta ko Lagani”(Water of Nepal: Investment from People)

Planning for Institutional reform Unbundling of Nepal Electricity Authority (NEA) Separate Generation Company New Power Trade Company

11

Environmental Requirements for HPP development

National Requirements (Environment Protection Act/ Rules, 1997):

IEE for Generation (1-50 MW, <5 Ha forest area) EIA for Generation (more than 50 MW, > 5 Ha forest area) IEE for Transmission line >=132 KV Outdoor substations tapping from 220Kv Substations and Transmission line >>EIA Construction of HPP displacing >100 persons need EIA Protected areas, Inter basin transfer etc need EIA Construction of Multipurpose Reservoirs need EIA

Donors requirements (FDIs and Development Loans/ Grants):

IFC performance Standards ADB safeguards Other donors/lender E&S requirements

12

Energy Status

13

StatusPower Situation (Daily Load Variation During Winter Season)

• Daily Peak demand: 1385 MW• Supply at the time of peak demand: 750 MW

14

Storage

Source: NEA,2016

Status Contd…

15

Total Annual Energy Available & Peak Demand in the System

Source: NEA,2016

Pattern of Seasonal Variation in Demand (Load) and Generation

STATUS CONTD….

Source: NEA,2015

Status Contd…

17

NEA Load Forecast

Source: NEA,2015

18

Hydropower Projects with FDIKhimti 60 MW (Operation)

• Owner: Butwal Power Company Limited, Norwegian companies - Statkraft SF, Kværner Energy a.s. (now G.E. Hydro Norway) and ABB Energi a.s. (now ABB ALSTOM a.s.)

• Construction period 1996-2000• License for generation for 50 years (Electricity Act 1992)

Upper Bhote Koshi Hydroelectric Project (45MW) (operation)• Owners: Originally majority share of Panda Energy• Construction period: 1997-2001• 40-year license to build, own, operate and transfer

Upper Trishuli I (216 MW) ( Planned)

Kabeli A (37 MW) (Under Construction)19

Status Contd…

Major Hydropower Under Operation

• Other Small Hydro 14,24420

Other sources of Electricity under NEA*

*NEA: Nepal Electricity Authority**Data based on Fiscal year 2014/15

Status Contd… Major Planned and Under Construction Hydropower Own By NEA

21

Opportunities

22

Opportunity

Snow capped Himalayas are Water Towers for Asia6,000 rivers including rivulets and tributaries totaling about 45,000 km in length The potential is estimated at 83,000 MW, of which half i.e. 43,000 MW is considered to be technically and economically viable.Export possibility of Energy to India & Bangladesh Lots of projects under FDI in Project Finance Modality are coming to Nepal

Challenges

24

ChallengesDuring Planning & Design

Posted rates (Feed in tariff) are unreasonable for developmentForeign currency fluctuationsLack of Technical manpower & resourcesLack of One Window policyNumbers of Protection Areas

During ConstructionTransmission LinesLand Compensation issueSocial and political instability

• During OperationSediment Related ProblemsGLOF/Climate change/LDLOFHanding over after 35 yrs is unclear 25

Case ProjectSanjen HEP-42.5MWSanjen(Upper) HEP-14.8 MW

26

27

Sanjen (Upper) HEP Sanjen HEP

Capacity 14.8 MW 42.5 MW

Project Type Peaking ROR Peaking ROR

PPA October 10, 2011 December 5, 2011

Transmission Line 5 km, 132kV 2 km, 132 kV

Design Discharge 11.07 m3/s 11.57 m3/s

Gross Head 161.3m 442 m

Contract Energy

Dry Season 10.583 GWh 34.278 GWh

Wet Season 71.856 GWh 207.587 GWh

Annual Energy 82.439 GWh 241.865 GWh

Total Energy from Both Projects: 324.30 GWh per Annum

Sanjen (Upper) HEP Sanjen HEP

Diversion Weir Length-14 m Chupchung Khola feeder

Desander 60m x 8m x9m

HRT 1376m x3.5m x3.75m 3630m x 3.5m x 3.75 m

Surge Shaft Dia 6m, H 40m Dia 6m, H 40 m

Penstock Pipe 478 m (l), 1.1~2.5 m dia. 1020 m (l), 1.06 ~ 2.5 m (dia)

Powerhouse Surface PH, 45 m x 14m x 20m Surface PH, 58 m x 15m x 25m

Tailrace Canal 28m x3m x7.5 m 27m x3m x7.5 m

Turbine 3 units Francis 3 units Pelton

31

Construction Progress: >50%Expected Completion Target: 2018

32

33