Post on 16-Jan-2016
Stakeholder Group Meeting
26. May 2010
Action Plan of the Region 2010Finn Dehlbæk
Main Action Points 2010 - 2011
• Well functioning Market Coupling North – CWE and preparation for enduring price coupling solution
• Transparency• Intra Day
Action #1: Market Coupling
20112010
Monitor commitments and ensure
launch of EMCC– CWE tight volume
coupling
Prepare necessary harmonisation of regulatory
framework for enduring price coupling solution in
North - CWE
Monitor progress in preparation of launch of
enduring price coupling solution in North - CWE
Action #2: Transparency
20112010
Monitoring report
Transparency in
production
Implementation of
Lacking points
Wholesale data
Monitoring report
Action #3: Intraday
20112010
Assessment of
AHAG target
model
Monitor implementation
of target model
Questions/comments