SOUTHERN REGIONAL POWER COMMITTEE BANGALORE
Agenda for the 29th Meeting of Protection Coordination Sub-Committee
of SRPC to be held on 20.02.2014 (Thursday)
1. Confirmation of the Minutes of the 28th Protection Coordination Sub-Committee meeting held on 24th January , 2014
2. Details of Grid Disturbances & Major Grid Incidences
It is requested that the constituents may send the Report / Analysis of the Grid disturbance/ Major Incidence within 24 hours of the occurrence to SRLDC and SRPC Secretariat.
3. Grid Occurrences in the Southern Region
It is requested that the detailed Report of the Grid occurrence may please be Uploaded in the SRLDC website within the time schedule as stipulated in
IEGC.
4. CERC Order dated 19.12.13 in respect of Petition No.
263/MP/2012.
APTRANSCO,KPTCL, KSEB ,Puducherry and TANTRANSCO are requested
to send the status of implementation/ action taken for implementing the
Hon'ble CERC order dated 19.12.2013 in respect of Petition
No.263/MP/2012.
5. Status of Pending Protection issues
Status of the following pending protection issues may be informed to the PCSC forum latest by 14.02.2014.
a. Status of Recommendations of the 27th PCSC
With respect to Grid Disturbance that occurred at Kothagudam
TPS and Khammam S/S on 25.09.2013
Agenda for the 29th Protection Coordination Sub Committee Meeting to be held on 20.02.2014 Page 2
SN
Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 a. APGENCO to consider usage of relays of different make for Main –I and Main II distance protection for KPTS- Managuru line-2. Relevant APTRANSCO c.APTRANSCO to review distance protection settings of KPTS- Managuru line-2 as it tripped for fault in KPTS- Managuru line-1. d.APGENCO to review reverse distance protection settings of KPTS- Shapurnagar Line. e. APGENCO to enable DEF Back Up protection in all lines emanating from KTPS. f. APGENCO to enable IDMT characteristics for GTs and ICTs at KTPS which is to be coordinated with primary protection. g. APGENCO to review the Overload settings of Unit 4 h .DR at Khammam Substation to be time synchronized with GPS i. APGENCO to review bus bar protection settings.
27th PCSC
Yet To be reported
APTRANSCO/APGENCO
Pending
APTRANSCO / APGENCO to send the status of implementation
b. Recommendations to be complied by November 2013
SN
Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 DTOC settings for ICTs to be removed and IDMT settings to be adopted.
21st PCSC (25.06.2013)
Nov-13 SRTS I, PGCIL
- SRTS I, PGCIL yet to report to the PCSC forum.
2 Main2 distance protection for EMPC#1 feeder not available - Edamon
17th PCSC (26.02.2013 )
Nov-13 KSEB - KSEB to update the status
Agenda for the 29th Protection Coordination Sub Committee Meeting to be held on 20.02.2014 Page 3
3 LBB not in service for SBEM 2, 3 and EMPC #1- Edamon
17th PCSC (26.02.2013 )
Nov-13 KSEB - KSEB to update the status
c. Recommendation to be complied by December 2013
SN
Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 NPCIL,KPCL and KPTCL in coordination to review the protection settings at Kaiga Corridor
24th PCSC (26.09.2013 )
Dec-13 NPCIL, KPCL
NPCIL,KPCL Pending
Compliance of KPCL, Kaiga, and NPCIL is yet to be reported to the SRPC Secretariat.
d. Recommendations to be complied by January- 2014
SN
Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 BUSBAR PROTECTION AT KAYATAR 110KV SUBSTATION
21st PCSC held on 25.06.2013
Jan-14 TANTRANSCO
Pending
TANTRANSCO informed that the protection issue would be sorted within the agreed time.
2 PROVIDING DR AND EL-MAMIDAPALY
23rd PCSC held on 27.08.2013
Jan-14 APTRANSCO
Pending
-
e. Recommendations to be complied by March 2014
SN Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 DG set at Edamon 17th PCSC (26.02.2013 )
Mar-14 KSEB Pending
KSEB informed that the protection issue would be completed by Mar-2014.
2 Bus Bar protection Scheme at Ragalapadu Substation
26th PCSC (21.11.2013)
Mar-14 APTRANSCO
pending
-
Agenda for the 29th Protection Coordination Sub Committee Meeting to be held on 20.02.2014 Page 4
f. Recommendations to be complied by May - 2014
SN Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 48 V DC SUPPLY REDUNDANCY NOT AVAILABLE-EDAMON
17th PCSC (26.02.2013 )
May-14 KSEB Pending
KSEB informed that the protection issue would be sorted within the agreed time.
2 EARTH PITS at EDAMON
17th PCSC (26.02.2013 )
May-14 KSEB Pending
KSEB informed that the protection issue would be sorted within the agreed time.
g. Recommendation to be complied by June - 2014
SN
Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 The Main I and Main II Protection of Different make-Sharavathy
21st PCSC held on 25.06.2013
June-14 KPCL Pending
Relays for M1 & M2 protection to be of different make: NIT has been issued and would be processed.
h. Recommendations to be complied by Aug 2014
SN Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 Synchronizing Facility at Hubli.
17th PCSC (26.02.2013 )
Aug-14 KPTCL Pending
KPTCL informed that the protection issue would be sorted within the agreed time.
i. Recommendations to be complied by Sep - 2014
SN Recommendation The
meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 Replacement of OLD CBs at Sharavathy
21st PCSC held on 25.06.2013
Sep-14 KPCL Pending
NIT has been issued and would be processed.
Agenda for the 29th Protection Coordination Sub Committee Meeting to be held on 20.02.2014 Page 5
2 COMPLIANACE OF 3RD PARTY AUDIT REPORT-Sharavathy
17th PCSC -25th PCSC (26.02.2013 to 22.10.2013)
Sep-14 KPCL Pending
NIT has been issued and it would be processed
j. Recommendations to be complied by Nov 2014
SN
Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 •As the Plant was more than 25 years old, all yard equipment need to be replaced. •Modification of Bus Scheme to be carried out. •The PCSC forum recommended for the modification of Bus Bar protection scheme at Idukki Substation. In the event of bus fault the entire substation should not be affected. This would improve the reliability and security of the Idukki Hydro Generating station.
26th
PCSC
Nov-14 KSEB Pending
KSEB informed that the protection issues
would be addressed by Nov 2014.
k. Recommendation to be complied by Dec 2014
SN
Recommendation The meeting in which the issue was Discussed
Anticipated date of completion
Agency Status Remarks
1 ONLY ONE BUS IS AVAILABLE, TRANSFER BUS SHALL BE PROVIDED -EDAMON
17th PCSC (26.02.2013 )
Dec-14 KSEB Pending
KSEB informed that the protection issue would be sorted within the agreed time.
Agenda for the 29th Protection Coordination Sub Committee Meeting to be held on 20.02.2014 Page 6
5. Remedial measures taken for critical tripping events
The respective constituents are requested to send the remedial measures
taken by them for the tripping events enclosed in the Annexure – I through
email latest by 07.02.2014.
6. SPS for Kudankulam Nuclear Power Station SRLDC brought to the notice of the PCSC forum that there had been re-orientation recently in respect of 400 KV lines emanating from Kudankulam. Three 400kV lines were now from Kudankulam to Thirunelveli while remaining one line is from Kudankulam to Madurai. Hence the following logic was proposed for SPS at Kudankulam on account of the change in the configuration:
Contingency Action
Tripping of all three lines from Kudankulam to Thirunelveli and two units in running condition at Kudankulam.
One unit at Kudankulam to go on house load and the second unit generation would be evacuated through 400kV Kudankulam-Madurai line.
28th PCSC Deliberations
Ø SRLDC informed the forum that PGCIL had furnished its response to the issues raised by NPCIL. It had asked KKNPP to restrict the generation to House Load on a Generator and 700 MW on other Generator.
Ø KKNPP, NPCIL informed that they would revert back within three week's time.
NPCIL to inform the status.
7. Phasing of Implementation of Protection Audit Recommendations
• In the 23rd SRPC meeting held on 26th October 2013m, it was agreed that the utilities to carry out implementation of the recommendations relating to third party protection audit as per prioritization in a phased manner.
• The schedule of activities would be furnished with in one month and would be discussed in the Protection sub committee meeting.
• The utilities would commence works identified in the above schedule
Agenda for the 29th Protection Coordination Sub Committee Meeting to be held on 20.02.2014 Page 7
without waiting for funding.
• SRLDC had also submitted its recommendations regarding phasing of works to Hon’ble CERC. Action by: TANTRANSCO, KPTCL, and Puducherry
8. Tripping Incidents in the Southern Region The tripping details that had occurred in the Southern Region during the month of January , 2014 is enclosed as Annexure - II .The Constituents were requested to update the details in the SRLDC Website at the earliest to analyze the incidents and suggest remedial measures if any.
9. Status of implementation: SPS in Southern Region
SN
Name of the Scheme Details of the scheme
Implementing Agency
Status Remarks
1 Additional Logic for 765 KV Sholapur Raichur Line
Operation of Over current
protection (800 A or 1000
MW for 10 sec) in 765kV
Sholapur-Raichur line (Import
by SR) and
frequency <50.1 Hz
SRTS I,PGCIL
SRTS I to update the status.
The PCSC forum recommended for implementation of additional Logic for the SPS for 765 KV Sholapur Raichur Line w.e.f 27.01.2014.
2 Modification in NTPC Talcher SPS
NLDC has proposed for modification in the SPS for secure operation of Grid after synchronization of SR with NEW Grid.
NTPC/CTU in consultation with NLDC and SRLDC
- -
10. Status of implementation: SPS in Karnataka
SN
Name of the Scheme
Details of the scheme Implementing Agency
Status Remarks
1 Somanahally& Bangalore water supply
a) To trip all 220kV lines & 220 / 66kV trfs except 220 kV Harohalli & Tataguni lines at Somanahally and to trip Vrishabhavathi line at Tataguni when ICTs at Somanahally trip. b) To trip 220 kV Vajamangala and Madhuvanahally-1 & 2 lines at TK Hally when ICTs at Mysore trip.
KPTCL
KPTCL informed that the SPS is delayed due to ongoing R&M works at 220 KV Somanahalli SS.
KPTCL to submit the SPS Logic to the SRPC Secretariat.
2 (i) SPS for Tripping of one of 400 KV
In SR signal will be sent from Hiriyur to trigger 765 KV Raichur Sholapur SPS.500
KPTCL/ PGCIL
(i) KPTCL informed that action would
-
Agenda for the 29th Protection Coordination Sub Committee Meeting to be held on 20.02.2014 Page 8
Hiriyur Nelamangala D/C Line and flow on other line >850 MW (ii) SPS for tripping one of 400 KV Gooty Nelamangala S/C Line or 400 KV Gooty Somanahalli S/C Line and flow on the other line > 850 MW.
MW of additional loads in Southern Region to be identified which is separate from the loads identified for HVDC Kolar SPS and Kudankulam SPS.
be taken for identification of separate loads for the proposed SPS based on the recommendations of PCSC forum.
11. Implementation of Islanding schemes in SR
Mock testing of Islanding scheme – constituents may discuss.
12. Mapping of AUFR, df/dt, SPS in the SCADA of SLDC/SRLDC. The issue may be discussed
13. Protection Logic checking of Critical Substations Logic checking of following Critical Substations in the Southern Region had been approved in the SRPC meeting held on 18.05.2013 at Bangalore.
(i) 400 kV Guttur (vi) 400 kV Kurnool
(ii) 400 kV Ramagundam (vii) 400 kV Almatti
(iii) 400 kV Kalpaka (viii) 220 kV Edamon
(iv) 400 kV Nelamangala (ix) 400 kV VTS
(v) 400 kV Hoody (x) 400 kV Vemagiri
14. Implementation of recommendations of Enquiry Committee (NEW grid disturbance on 30th & 31st July, 2012)
(a) Healthiness of Batteries
Healthiness of Batteries Installed at 220 KV and above voltage level Substations (to provide Backup supply to the Relays, RTUs and Communication Equipments) may be updated on monthly basis since the same has to be communicated to CEA/MOP.
• The constituents were requested to submit the healthiness of batteries on monthly basis (i.e. on 7th day of the month).
Agenda for the 29th Protection Coordination Sub Committee Meeting to be held on 20.02.2014 Page 9
• The following constituents are requested to send the report regularly
APGENCO,KPCL,KPTCL,SRTSI (PGCIL) , NPCIL, Puducherry, JSWEL, UPCL
• The status of submission by the constituents is enclosed herewith as Annexure – III.
• The following constituents are requested to send the consolidated list of Batteries installed in the system (Substation wise) as a onetime report.
APGENCO,APTRANSCO,KPCL,KPTCL,SRTS I (PGCIL),
NPCIL, Puducherry, JSWEL, UPCL
15. Submission of completed dynamic study data All SLDCs were requested to direct the embedded IPPs connected at 220 kV and above voltage level to submit completed dynamic study format to SRPC, Secretariat.
16. Informing configuration changes to PCSC forum It was agreed in the PCSC forum that if any change in the system configuration ( i.e. addition of Generating Units, Capacitors, Reactors, LILO etc) are to be highlighted and brought to attention of PCSC forum during the PCSC Meetings . This would enable utilities to review their protection settings if any change in the adjoining utilities to have better protection coordination in the Southern Region. All the constituents are requested to send the change in the configuration in their system if any to the PCSC forum on monthly basis.
17. Sending Agenda items for the PCSC meetings
As per the Guidelines of CEA/MOP it had been decided to conduct the PCSC meetings on a monthly basis .It is requested that Agenda Items for the PCSC meetings, if any, may please be sent latest by 5th working day of the month to SRPC Secretariat to compile and circulate the same so as to have fruitful discussions in the PCSC meetings.
18. Date & Venue of the next Meeting The 30th PCSC meeting would be conducted on 19.03.2014 (Wednesday) at SRPC Bangalore.
*******
ANNEXURE I
1
SRPC, Bangalore
Status of Remedial Measures for the Pending Critical Trippings Reports as on 04.02.2014 (Excluding O/V trips)
Status of Earlier Trips SN Element Name Outage
date/time Revival date/time
Reason for Outage Remedial Measure
1 HVDC BHADRAVATHI POLE 1 09-11-2013/ 14:50:00
09-11-2013/ 15:00:00
AUX. POWER SUPPLY FAILURE To-be-discussed
2 HVDC BHADRAVATHI POLE 2 22-11-2013/ 15:26:00
22-11-2013/ 15:39:00
DUE TO PROBLEM IN THE SOFTWARE OF POLE CONTROL SYSTEM
To-be-discussed
3 HVDC BHADRAVATHI POLE 2 07-01-2014/ 22:20:00
07-01-2014/ 22:32:00
DUE TO FILTERS TRIPPING ON SOUTH SIDE
To-be-discussed
4 HVDC BHADRAVATHI POLE 1 07-01-2014/ 22:20:00
07-01-2014/ 22:32:00
DUE TO FILTERS TRIPPING ON SOUTH SIDE
To-be-discussed
5 400 kV VIJAYAWADA - VTPS IV 2 15-01-2014/ 02:09:00
15-01-2014/ 03:36:00
REASON AWAITED To-be-discussed
6 400 Kv GOOTY - NPS 1 15-01-2014/ 12:29:00
15-01-2014/ 17:40:00
R - N FAULT To-be-discussed
7 400 kV VIJAYAWADA - VTPS IV 2 15-01-2014/ 18:42:00
15-01-2014/ 19:01:00
PLCC MAL OPERATION To-be-discussed
8 220 kV SABARIGIRI - THENI 20-01-2014/ 12:39:00
20-01-2014/ 13:01:00
DISTANCE PROTECTION OPERATED To-be-discussed
9 400 kV NELLORE - ALAMATHI 20-01-2014/ 18:03:00
20-01-2014/ 22:32:00
Y-PH LA FAILURE AT NLR END To-be-discussed
ANNEXURE I
2
10 400/220 kV ICT-2 AT CHITTOOR 24-01-2014/ 12:40:00
24-01-2014/ 13:10:00
FOREIGN MATERIAL FALLEN ON ICT To-be-discussed
11 400 kV MAHABOOB NAGAR - RAICHUR 24-01-2014/ 18:06:00
24-01-2014/ 18:31:00
PLCC MALOPERATION To-be-discussed
12 400 kV NELLORE - ALAMATHI 25-01-2014/ 18:27:00
25-01-2014/ 22:55:00
B PHASE LA FAILED AT NELLORE To-be-discussed
13 220 kV KAIGA - KODASALLY 25-01-2014/ 23:55:00
26-01-2014/ 01:06:00
TRIPPED ON EARTH FAULT To-be-discussed
14 220 kV KAIGA - KADRA 1 26-01-2014/ 00:44:00
26-01-2014/ 01:03:00
TRIPPED ON BACKUP OVER CURRENT PROTECTION
To-be-discussed
15 400 Kv TRICHUR - PALLAKAD 2 29-01-2014/ 14:29:00
29-01-2014/ 15:32:00
TRIPPED ON R-B FAULT To-be-discussed
16 400 Kv RTPS - BTPS 29-01-2014/ 18:12:00
29-01-2014/ 19:28:00
DISTANCE PROTECTION OPERATED To-be-discussed
ANNEXURE III
1
As on 04.02.2014 the status of Healthiness of Batteries as submitted by the constituents.
S.No Constituent
Healthiness of Batteries Consolidated List of Batteries Installed in
the System
Remarks
Oct- 2013 Nov-2013
Dec-2013
1 APTRANSCO Reported Healthy
Reported Healthy
Yet to report Yet to report APTRANSCO Is requested to send the consolidated List of Batteries installed in their system (Substation wise) –one time report.
2 APGENCO Yet to Report Yet to Report Partly Submitted
Yet to report APGENCO is requested to to send the report on monthly basis (i.e on 7th of every month)Consolidated (For Thermal & hydro stations) .
3 KSEB Reported Healthy
Reported Healthy*
Yet to Report Reported *Among the 76 Battery Banks 20 were reported not healthy. They were in the process of replacing them in stages.
4 KPTCL Yet to Report Yet to Report Yet to Report Yet to Report KPTCL is requested to
to send the report on monthly basis (i.e on 7th of every month)
5 KPCL Yet to Report Yet to Report Yet to Report Yet to Report KPCL
to send the report on monthly basis (i.e on 7th of every month)
6 TANTRANSCO Reported Healthy
Reported Healthy
Reported Healthy
Reported
7 SRTS I,PGCIL Reported Healthy
Yet to Report Yet to Report Yet to Report SRTS I ,PGCIL Is requested to send the consolidated List of Batteries installed in their system( Substation wise )–one time report.
8 SRTS II,PGCIL Reported Healthy
Reported Healthy
Reported Healthy
Reported
ANNEXURE III
2
9 NTPC, Ramagundam Reported Healthy
Reported Healthy
Reported Healthy -
Reported
10 NTPC, Simadhri Reported Healthy
Reported Healthy
Reported Healthy
Reported
11 NTPC, Kayankulam Reported Healthy
Reported Healthy
Reported Healthy -
Reported
12 NLC - Reported
Healthy Yet to Report Reported NLC
to send the report on monthly basis (i.e on 7th of every month)
13 MAPS,NPCIL - Reported Healthy
Yet to Report Reported MAPS to send the report on monthly basis (i.e on 7th of every month)
14 KAIGA,NPCIL Reported Healthy
Yet to Report Yet to Report Yet to Report KAIGA,NPCIL Is requested to send the consolidated List of Batteries installed in their system( Substation wise )–one time report.
15 KKNPP,NPCIL Yet to Report Yet to Report Yet to Report Yet to Report KKNPP,NPCIL Is requested to send
the consolidated List of Batteries installed in their system( Substation
wise )–one time report.
Yet to Report
16 Puducherry Reported Healthy
Yet to Report - Yet to Report
Yet to Report Puducherry is requested to send the report on monthly basis (i.e on 7th of every month)
17 JSWEL Yet to Report Yet to Report Yet to Report Yet to Report JSWEL is requested
to send the report on monthly basis (i.e on 7th of every month)
18 UPCL Yet to Report Yet to Report Yet to Report Yet to Report JSWEL is requested
to send the report on monthly basis (i.e on 7th of every month)
Note: Constituents are requested to send the consolidated List of Batteries available in their system as a one time report.