Post on 16-Jan-2016
SNS Integrated Control System
MPS - Commissioning Plans
1. Quick MPS System Overview
2. Run Permit System
3. Fast Protect Auto Reset
4. Fast Protect Latched
5. High QA (Hard Wired) MPS System
SNS Integrated Control System
MPS Design Assumptions
Four layers of protection!» High QA (Hardware) PLC» Hardware / Software (Fast Protect System)» Software (Run Permit System)
Machine Protection System is not a “Safety Class” or “Safety Significant” System.
SNS will be built and commissioned in Phases, MPS must accommodate this schedule, (Flexible and Reliable).
Reliability – The Machine Protection System must inhibit the beam when required. It must fail in a SAFE state.
Availability – The machine availability should be as high as possible. The MPS must be easy to configure and have a “friendly” operator interface. False trips must be minimized.
SNS Integrated Control System
MPS - Layered Protection
PersonelProtection
System
Fast ProtectLatched
Fast ProtectAuto Reset
Run Permit
Incr
easi
ng
QA
Hard Wired and PLCapplication
3 MHz carrier linkKEY Bypassing
Jumper Bypassing
8 MHz carrier linkSoftware bypassSoftware Trips
EPICS ApplicationSoftware
EPICS Channel AccessInputs
Loss MonitorsRF Status
Machine Mode
Valve StatusPower Supply StatusSystem Level Inputs
Chipmunks,Doors, etc.
AC Breakers in frontend electronics &power supplies
65 KV supplyRFQ Power Supply
RFQ DriveLEBT Chopper
MPS FPAR, FPLTiming System
ProtectionSystem
Shutdownmechanism
SystemDescription
System Inputs
TargetProtection
SystemHard Wired
Target Sensors
TemperatureFlow
AC Breakers
No
n S
afet
y C
lass
Sys
tem
sS
afe
tyS
ign
ific
an
tS
afet
yC
lass
Hard WiredPermit
KEY BypassingPower Supply Shunts
PPS InputsBergoz MPCT
Front End PSHardwire interlocks
SNS Integrated Control System
MPS Commissioning (Verification, systems checked previously without beam, Commissioning and testing)
Run Permit System (1 second)» Verifies IOC configuration and beam line equipment status.» MPS masking, Beam Power limit verification
Fast Protect Auto Reset (20 microseconds)» Beam Loss Monitors» Beam Current Monitors
Fast Protect Latched System (20 microseconds)» Power Supply status, RF, Kicker status» System cooling status (Collimators, dumps, etc)» Etc.
High QA MPS (~ 33 msec)» Magnetic Field limit(s) verification» Beam Diagnostics verification, calibration, testing
SNS Integrated Control System
MPS Fast Protect System Layout
RING
RFQDrive
HEBT
Ldump
SRF
CCL
DTL
65 kV
RFQHVPPS
MPS Inputs
MPS Inputs
MPS InputsMPS Inputs
MPS Inputs
MPS Inputs
MPS Inputs
MPSMaster
Machinemode
RING
RTBT
Xdump
MPS Inputs
MPS Inputs
MPS Inputs
Idump
RTBT
Target
Fa
st
Pro
tec
tIn
pu
ts
FrontEnd
LINAC RING RTBT
Fa
st
Pro
tec
tIn
pu
ts
Fa
st
Pro
tec
tIn
pu
ts
Fa
st
Pro
tec
tIn
pu
ts
Target
LEBTChopper
RFQDrive
Fa
st
Pro
tec
tIn
pu
ts
Fa
ult
Be
am
Pe
rmit
Inp
uts
FrontEnd
LINAC RING RTBT Target
Ion Source65 Kv PS
RFQPower Supply
Fa
ult
Be
am
Pe
rmit
Inp
uts
Be
am
Pe
rmit
Inp
uts
Be
am
Pe
rmit
Inp
uts
Be
am
Pe
rmit
Inp
uts
ExtractionKickersFault
EventSystem
"ABORT"
5.6 us 5.8 us 8.2 us 8.2 us
27.3 us
MEBTMPS Inputs
RFQ
LEBT
Src
MPS Inputs
MPS Inputs
MPS Inputs
0.8 us
MPS Inputs
MPS Inputs
SNS Integrated Control System
MPS Shutoff Equipment
Hard Wire Protect» RF drive to RFQ Power Supply interlocks» 65 KV Power Supply Interlocks
Fast Protect – Auto Reset» RF drive to RFQ» LEBT Chopper
Fast Protect - Latched» 65 KV Power supply» RFQ Power Supply
Run Permit» Fast Protect - Latched» Fast Protect - Auto Reset
( Time Line Decoder (un-schedule all beam) )
SNS Integrated Control System
MPS - Fast Protect Inputs
FPARRFHV PS I Wire Harp BLM LLRF Kick Dmp/TgtVac Total BLM
Mon.Scan. Coll InputsSRC 2 23 1 0 0 0 1 0 0 3 30 0
D-Plate 3 32 1 10 2 0 6 0 2 18 74 5
L_dmp 19 181 1 40 0 0 96 0 1 21 359 129
I_Dmp 1 32 1 11 2 2 2 0 2 2 55 33
Ring 2 143 1 2 2 2 4 8 2 2 168 87
E_Dmp 0 31 1 2 2 2 0 14 2 2 56 21
TGT 0 25 1 3 2 2 0 0 2 2 37 24
Total 27 467 7 68 10 8 109 22 11 50 779 299
Fast Protect Latched Inputs - ALL Correctors - LLRF
• LLRF Inputs could be auto reset (FPAR)• ~50% of corrector supplies will not initially be MPS inputs
• HEBT 12/18, RING 12/126, RTBT 12/19• BLM’s could be Latched, as determined during commissioning
SNS Integrated Control System
Bypassing MPS Inputs
Allow easy bypass (Software Masking)» Different rules for commissioning and operations
» Commissioning, FPAR devices can be masked
» Commissioning, FPL – subset of Quads and correctors can be masked, all dipoles and rest of quads need ASD Radiation safety approval.
» Commissioning team – ASD-RS should agree on list before commissioning.
Easy OPI for verifying, changing software MASK.
MODE masks are defined by ASD-RS, not easily changed.
SNS Integrated Control System
SNS Integrated Control System
Run Permit System – Tasks
Machine Mode Setup» Machine Mode (Dump) and Beam Mode (Power, Width restrictions)
Selection (From High QA System)» Longitudinal pulse profile verification and selection» Verifies machine setup before changing mode
Schedules Machine Sequence» Keeps Beam, RF, Modulator gates in sync» Schedules Pulse Profiles at requested rate» Calculates / verifies table checksums (pulse to pulse)
Operator Interface to MPS» Control and Status Displays» Software Masking of inputs / Trip limit Controls
Hardware configuration verification» SNL task scans IOC hardware configuration for verification
SNS Integrated Control System
Run Permit System – Mode Definitions
Machine Modes» Ion Source
» D-Plate
» Linac Dump
» Injection Dump
» Ring
» Extraction Dump
» Target
Beam Modes» Beam Off
» Diagnostics (10 usec)
» Diagnostics (50 usec)
» Diagnostics (100 usec)
» Full Pulse Width (1 msec)
» Low Power (7.5 kW)
» Medium Power (200 kW)
» Full Power (2 MW)
Machine mode selected by Key switch in control room, Beam Mode selected by Key or software. Switches read by High QA MPS system.
SNS Integrated Control System
RPS – Operating Envelope Calculations
Safe Operating Reqion
0.1
1
10
100
0 200 400 600 800 1000
# of turns injected
Bea
m in
ject
ion
Rat
e
7.5 kW envelope
200 kW envelope
2 MW envelope
60 Hertz
Safe Operation
Wire Scanners
SNS Integrated Control System
User Beam Profile Request
CP
UE
PS
VME
Tim
ing
EP
S
LEBTChopper
PhysicsApplication
Event linkEncoder
SystemSequencer
Control Room
RTDLMaster
DiagnosticsIOC's
UserProfile,
Raterequest
User ID
PV_List_ModeTimeout
Time Window
ControlsIOC's
Control SystemNetwork
SynchronousData
TimingDistribution
System
DiagnosticsIOC's
CP
UE
PS
VME
Tim
ing
EP
S
ControlsIOC's
WireScannerRequest
SNS Integrated Control System
MPS Top Level Screen
SNS Integrated Control System
Run Permit System – Operator Interface
SNS Integrated Control System
Typical Top Level Screens
Global Software Mask Status Display BLM Trip Point Display Time / Fault display line
» Post Mortem playback, Loss verses RF, etc
Time Line Recorder» Timing system faults, missing events, extra events, etc
PPS Status, Beam line readiness, etc Fault by system, Fault by area Beam Profile scheduling, Rate requests, etc.
Requests for specific displays seen elsewhere appreciated, a quick hand sketch is useful.
SNS Integrated Control System
SNS Integrated Control System
Fast Protect – Auto Reset
ALARA – Pulse Width Modulation, Tuning Aid
Concentrates Permit Inputs
Beamline Inputs Bypassed by Mode
Inhibits carrier link to disable Beam
Typical Inputs:» Loss Monitors
» Time Line Recorder (Noise detected on Event Link)
» Differential current monitors
Auto resets for next beam pulse, Latches to FAULT state after N trips in M pulses
Auto mask sets(MODE MASK) (Wire Scanners)» Mode allows WS to be bypassed, SW Mask bypasses WS input
SNS Integrated Control System
SNS BLM SYSTEM DESIGN CRITERIA
•Upper end signal: (Fast Protect Auto Reset)– Maximum beam loss of 1 % at a single location
–35-50 kHz signal BW
–Beam interrupt via MPS based on integrated loss during pulse ( 10 μsec response)
•Lower end signal: (Beam Loss Accounting System) –Set by 1 W/m requirement for maintenance
–Must resolve 1% of 1 W/m but at BW of < 1 Hz
–Warning only after extended period of loss (1 minute)
–(Saeed Assadi, MPS FDR slides)
SNS Integrated Control System
BLM-- Specification:
Fast Loss: (Determine thresholds during commissioning)1)10 µsec Detect-to-Beam Inhibit time.2) Programmable threshold, each detector, level changes/macro-pulse3) Each detector maskable (eliminate bad channels, permit studies resulting in higher than normal losses) Single output line/analog crate
Long-term: (Calibration Studies)1) Low level loss: "Soft" alarm through network or2) Programmable threshold, each detector,3) Each detector maskable (eliminate bad channels, permit studies resulting in higher than normal losses) Single output line/analog crate
Local Data Storage:"Flight-Recorder Mode, 60 (1-second) records of "Detailed Losses" for each detector. Available for read-back on beam abort.In-Situ System check: On-line check of all detectors, connections and electronicsby cycling HV Off/On.
SNS Integrated Control System
BLM AFE Configuration
SNS Integrated Control System
Beam and Loss Display (Simulated data II)
SNS Integrated Control System
LINAC Dose Rate:
** Data is provided by Franz X Gallmeier.
SNS Integrated Control System
LINAC Dose Rate (Simulated data) Distance along LINAC
Tim
e
SNS Integrated Control System
Beam Loss Monitors (Commissioning)
Verify BLM Operation (Part of BLM / Diagnostics commissioning plans)
MPS» Measure (Verify) Integration Times (1 % Loss) » Determine Trip Point Limits for each BLM» Determine Radiation Dose Calibration» Calibrate losses in units of W/m» Verify Masking Capabilities (Software masks)» Verify Wire Scanner Masks (BLM Mode masks)
BLM Accounting» Calibrate low loss measurements
– Change vacuum by order(s) of magnitude?
See Saeed’s slides from Ring commissioning meeting in Dec and slides from MPS FDR:
» http://www.sns.gov/projectinfo/ics/192/1923/1923.html
SNS Integrated Control System
Commissioning activities
Select device and mask (or desensitize) adjacent devices
Loose beam, verify time response» Log MPS input fault time» Log Front end shutdown time» Verify response time with diagnostics:
– Current monitors, analog signal, scope mode
– Fast Loss Monitor(s)
– BPM Power (Amplitude)
Verify Loss mechanism (Change vacuum, monitor response)
Determine appropriate trip levels for commissioning, operations» Poor vacuum conditions, Energy changes, Tune changes (Instabilities)
Calibrate differential current monitors vs. Beam loss monitors
Identify, Eliminate(minimize) sources of false trips» Beam noise (50 amps @ 1MHz), Kicker noise, etc.
SNS Integrated Control System
Conclusions:
1) SNS expects to maintain losses below 1Watt/meter over most of the Accelerator in order to allow hands-on maintenance. As such the BLM system will play a major roll in commissioning.
2) Important loss mechanisms include gas stripping, magnetic stripping and Halo generation from “mismatches”. We hope to use the BLM system to confirm the models and set the limits for the BLM-to-MPS trip levels.
3) Loss Monitor system will provide signals to the MSP system which are not modifiable by software (a layer of protection).
4) HARPS and specialized edge loss detection diagnostics are under studies but not included in the base-line systems yet.
SNS Integrated Control System
SNS Integrated Control System
Fast Protect - Latched System
Concentrates Permit Inputs
Latches carrier link in FAULT state to disable beam
Input bypassing allowed with Jumper, Key or PLC
Beam line inputs bypassed by machine mode (event link)
Equipment maintained in locked racks
Documentation control of changes
System verification after changes
When MPS inputs need bypassing for beam studies, Software masking will be available as required. (Masking some devices will need the approval from Radiation safety committee)
SNS Integrated Control System
Fast Protect - Latched Inputs
Power supply status (Fault when PS is not ON)
Valve Status (Fault when valve is not OPEN)
LLRF RF Status (Fault when PS is not Enabled)
Target Status» Response should be faster than target shutdown signal.» Time Stamp verifies MPS ACTED FIRST
Dump Status (Fault when all dump sensor not OK)
Loss monitors (High QA chipmunks)
Timing System Status» Ring RF required for IDMP, RING, EDPM, and target modes» Local Oscillator allowed for LDMP, D-plate, and Ion Source modes
PPS Input» PPS search status will latch off beam
SNS Integrated Control System
Vacuum Level – MPS trip levels
Vacuum Level RequirementsSystem Design Conditioning Operational(1) Document
Trip TripFE 5x10-7 1x10-6 5x10-6 Front End Systems SRDDTL 1x10-7 1x10-6 1x10-6 Linac Systems SRDCCL 5x10-8 1x10-6 5x10-7 Linac Systems SRDSCL 1x10-9 1x10-6 1x10-8 Vacuum System Interrupts (2)Coupler 1x10-8 1x10-6 1x10-7 Vacuum System Interrupts (3)HEBT 5x10-8 1x10-6 5x10-7 Ring and Transfer lines (4)Ring 1x10-9 1x10-6 1x10-8 Ring and Transfer linesRTBT 1x10-8 1x10-6 1x10-7 Ring and Transfer lines (1) Actual trip points can vary and will be set during commissioning.(2) Gate valves close if vacuum > 1x10-9 longer than 3600 seconds or > 10-6 ASAP.(3) Inhibit RF and Beam if pressure >10-8 for 10 seconds, 10-7 for 1 second, or 10-6 ASAP.(4) Estimated losses due to H- stripping (50% H ~10-19 cm2/atom, 50% Oxygen, Nitrogen ~10-18 cm2/atom) is 0.3 nA/m at 5x10-8 Torr.
Vacuum Status – Valve closures operate trip defined below. Integrated vacuum levels produce EPICS Alarms, which could shut off the beam (MPS). MPS trips on VALVE Closure.
SNS Integrated Control System
Fast Protect - Latched Inputs
Injection Kickers
Extraction Kickers
Ring RF
Current monitors
HARP – Backup to HQA-MPS
SEM» Possible backup to HARP
Beam Position Monitors» Beam off target/dump violation
SNS Integrated Control System
Fast Protect - Latched Inputs
EPICS Alarm Inputs» EPICS Alarms for any PV can trigger latched input on a board level or
input signal level.
MPS Verification Software» SNL program verifies jumper settings, Latches beam off in case of
discrepancy.
Beam Loss Accounting» Integrated loss sets Alarm, could trip beam
Beam Current Accounting
SNS Integrated Control System
SNS Integrated Control System
Injection Kicker
2 Horizontal, 2 Vertical pairs, 8 power supplies
Power supply status inputs to MPS-FPL
Each kicker in a pair should be matched
Fault on unmatched waveforms ?» Run Loss studies on unmatched waveforms.
» Sensitivity studies on painting schemes
2 kHz comparators for Reference and Shunt
SNS Integrated Control System
Injection Foil
Foil Failure» Beam Loss Monitors
» HARPS
» Integrating Current Monitor
» Peak Current Monitor
» Foil Video monitor
Foil Motion » Low power mode required? (LANSCE allows)
» LVDT – Motion range available
» Limit Switches
Foil Position» Use Mode Mask to allow beam for BLANK foil position or
Phosphorous screen in place
SNS Integrated Control System
Ring RF MPS Considerations
RF Power Supply
RF Cavity Field Error Signals
Reflected Power
RF Phase Error monitoring
RF – Beam phase monitoring?
RF Power Ramping (Amplitude modulation?)
Commissioning studies to determine acceptable losses verses RF parameters.
SNS Integrated Control System
Ring Collimator MPS Inputs
Temperature sensors
Water Flow
Normal loss monitors? (Dynamic range OK?)
Motion – (Drop to lower beam power?)
Motion out of range (LVDT’s?)
Limit Switches
SNS Integrated Control System
Extraction Kicker
“Fast and Slow” Kicker protection will be combined to give MPS one Fault output. (Charging supply status, Kicker Charged, Thyratron supply OK, Filament supply status, temp, flow, etc.)
One MPS signal per kicker. » Allow Operations to mask one kicker out. EPICS App. Does not allow more
than one kicker to be masked
Kicker System needs 3 pulses from timing system, Start charge, Stop Charge, and Extract.
False firing – Abort ASAP or synchronous with beam gap.
Storage mode: If kickers are used to abort beam in storage mode additional timing signals are required, charging current goes through kicker magnets (1/e ~1sec), and kickers would need to be masked during storage.
SNS Integrated Control System
SNS Integrated Control System
High QA MPS Dump, TGT, Window
HQA – Time response, 32 msec (12 msec measured )» Latched in PLC
» Does not rely on Software
Machine Can Take Two Full Pulses
High QA configuration Controls» Hardware normally inaccessible
» System Verification, routine testing
» Documentation trail
» Operational procedures
Redundancy –1 PLC, double up on sensors, use MPS-FPL for redundancy
Redundant shutdown devices
SNS Integrated Control System
Control Net Layout
P PS E NTRY
IonSource
LDMP
IDMP
RING
EDMP
TGT
MPSPLC
PPS
ZO
NE
Sta
tus
65 KVPSRFQ-RFRFQ-PS
Plasma-RF
Control Net - Flex IO Redundant Network - Fast Diagnostics
D-Plate
Avg. IPWmon
Harp
Imon
ImonMachine ModeBeam Mode
SelectKey switch
SNS Integrated Control System
High QA PPS Inputs and Selection Switches
Personnel Protection System» Linac zone» HEBT Zone» Ring Zone» RTBT Zone» Target Zone
Machine Mode Selection» Ion Source» D-Plate» L_DMP» I_DMP» RING» E_DMP» TGT
Beam Mode Selection» 7.5 kW» 200 kW» 2 MW» 10 μsec» 50 μsec» 100 μsec» 1 msec
SNS Integrated Control System
High QA Dump, Target PLC Remote Inputs
Target (or Dump) Status» Pressure, Temperature» Flow, Vacuum status
Power supply current monitor’s» Current and Voltage window comparators» Quads – Hi window, Dipoles, Hi and Off windows.» Steering corrector’s – Window (RTBT only)
HARP Status, P-P Permit Signal (Target only, Baseline)
Beam Current Monitor (Not in baseline, Hardware not chosen)» Co-Injection (Pulse-to-Pulse Species Modulation) ?» P-P Pulse Width verification» Beam Power, Integrated Beam Current
Beam Loss Monitor (2 per current monitor)
SNS Integrated Control System
Injection Dump inputs
Beam LossMonitor
BeamCurrentMonitor
QuadCurrentWindow
Comparator
WireScanner
InjectionDumpStatus
FastValve
HarpSEM
SNS Integrated Control System
Target MPS Inputs
SNS Integrated Control System
Power Supply Window monitors
Quad (Dipole) Magnet current compared with upper and lower limits, set in PLC Code. Limits determined by Accelerator Physics group. Magnet voltage used as redundant sensor.
Commissioning:
1. With any input beam characteristics, quads limit peak current density at window and dump(tgt) below charge density threshold.
2. Upper and lower limits allow tunability from lowest LINAC energy to highest energy.
3. Beam size (density) verified by Wire Scanners and HARPS.
SNS Integrated Control System
Power Supply Setting’s – Linac Dump (Data from Deepak)
Nominal 5e-3 limit A/m^2
Quad # Gradient Quad settingTransmission from window to dump
Max Current Density A/m^2
T/m out/inQuad 12 2.61431 5547/5610 9.93E-04
5% up 5547/5610 9.67E-045% down 5547/5610 9.34E-0410% up 5549/5610 9.72E-0410% down 5546/5610 9.02E-04
Quad 13/11 1.93365 5% up 5590/5610 9.67E-045% down 5547/5610 9.54E-0410% up 5546/5610 9.76E-0410%down 5547/5610 9.37E-04
Quad 14/15 3.03287 10% up 5546/5610 8.96E-0410% down 5547/5610 9.36E-0420%up 5546/5610 8.17E-0420% down 5548/5610 9.93E-04
Quad 16/17 3.10172 20% up 5545/5610 8.29E-0450% up 5541/5610 6.54E-0450% down 5549/5610 1.33E-04
Current Density at Linac dump
SNS Integrated Control System
Power Supply Setting’s – Linac Dump Window (Data from Deepak)
Current density at windowNormal 5610/5610 8.40E-02Quad 16/17 3.10172 10% up 5610/5610 1.06E-01
10% down 5610/5610 6.01E-02Quad 14/15 3.03287 10% up 5610/5610 7.18E-02
10% down 5610/5610 9.58E-0220% up 5610/5610 5.97E-0220% down 5610/5610 9.14E-02
quad 12 2.61431 20% up 5610/5610 1.40E-0120% down 5610/5610 3.77E-02
Quqd 13/11 1.93265 20% up 5610/5610 7.26E-0220% down 5610/5610 7.40E-02
Problem in this case was percent of beam outside allowable area on dump)
SNS Integrated Control System
Harp Commissioning
Target Harp can not operate 1 Yr. Pulse to Pulse
Target Harp is not retractable and is connected to window
Harp will probably survive a few months.
Operating Philosophy» Install set of redundant, retractable HARPS 180º upstream
» Commission retractable HARPs with Window HARP
» Set comparator limits on Optics
» Once a year, verify system HARPS
SNS Integrated Control System
Beam Current Monitor
Beam Power on Target (Dump) measurement
Target has maximum charge on target spec
Current monitor used to normalize Harp and WS
Current monitor problems:» Droop (L_DMP, I_DMP)
– Use baseline correction for toroids
» False signals with beam spray– Use Beam Loss Monitors (2) to monitor loss on toroid core.
» Baseline monitors use software– Purchase Bergoz PDCCT or equivalent