San Dieguito Wetland Restoration
Update on Progress by SCE
June 3, 2004
Final Design and Permits Update
• Work Completed
• Work in Progress
• Summary of Findings
• Schedule to Construction
• Discussion – Modifications to Final Plan– Other
Work Completed
• New Aerial Photography
• X-sections of River Bottom
• New 1 foot contour mapping
• Identification of existing utility conflicts
• Coordination with City of San Diego and City of Del Mar
• Coordination with JPA Trail Design
• Confirmation of Ownerships
• Geotechnical investigation
• Draft Grading Plan
• Updated Hydraulic Analysis based on new mapping
• Submitted Applications for City of Del Mar Permits
Work in Progress
• Final Grading Plans
• Planting Plans
• JPA Trail Plans
• Conditional Letter of Map Amendment
(CLOMR) from FEMA
• Resource Agency Permits
Summary of Findings
• Changes in Base Map – No significant changes in graded areas– Shift in river channel East of I-5– Significant scour near Jimmy Durante Bridge
• Grading – No significant changes in earthwork– Creates required wetlands
• Basic Concept of Final Plan Validated
ScheduleSouthern California Edison
San Dieguito Wetlands Restoration Project
June 3, 2004
1. Data Collection and Review
2. Engineering Documents
2.1 *Submit Plans to City of
San Diego/City of Del Mar
3. Permitting
Coastal Commission Approval
4. Construction
TASK
2004 2005 2006 2007 2008
July
Oct
Modifications to Existing Plan
• I-5 Embankment
• Berm Alignment East of I-5
Berm Alignment East of I-5
• Change in Alignment
• Impact of change on restoration
• Comments/Questions?
Change in Berm Alignment