Resources Planning - VINAY...

Post on 03-Mar-2019

213 views 0 download

Transcript of Resources Planning - VINAY...

11/17/2017

1

Survey No. 38, Cherlaguda Village, Shamshabad Mandal,

RR District, Hyderabad- 501218

Phone: +91-40-30461661

Email: info@imthyderabad.edu.in

Resources Planning

Vinay Kumar Kalakbandi Assistant Professor

Operations Management

Operations Management - II PGDM 2017-19

11/17/2017 1

Introduction • Computerised information system

– Aids in planning of materials in an organization

• Exploits certain unique characteristics of the production items – Utilize information on lead time, inventory status and master

production schedule to make material available exactly at the time of requirement

• Same logic could be extended to planning of other resources – Called generally as resources planning

11/17/2017 2

11/17/2017

2

Two types of inventories Distribution Inventory Independent Demand item

Operating Inventory Dependent demand item

11/17/2017 3

Characteristics of inventories Distribution Inventory

• Meant for market consumption

• Considerable uncertainty in demand

• Orders based on forecast

• 100% service level not feasible

• Continuous demand

Operating Inventory • Denotes all the resources

(broadly of material and capacity) that are available for the operating system to consume in the production process

• No uncertainty: Parent child relationship

• Production planning determines quantity

• Lumpy demand

11/17/2017 4

11/17/2017

3

Independent – Dependent Demand

11/17/2017 5

Dependency Relationship

11/17/2017 6

11/17/2017

4

Product structure

11/17/2017 7

level Level 4

Product structure

11/17/2017 8

11/17/2017

5

Bill of Materials – Single Level

11/17/2017 9

Indented BOM

11/17/2017 10

11/17/2017

6

Modular BOM

11/17/2017 11

MRP inputs and outputs

11/17/2017 12

11/17/2017

7

MRP Lot sizing rules

• Lot for Lot

• Economic Order Quantity

• Least Total Cost

• Least Unit Cost

11/17/2017 13

MRP terminologies • Explosion

– Iterative process of computing all requirements at a level and then moving down the level

• Product Structure – Graphically depicts relationships among various items that

make up final product

• Bill of Materials – List of all the materials needed to assemble one unit of

final product

11/17/2017 14

11/17/2017

8

Impact of Lead time

11/17/2017 15

Incorporating lead time

11/17/2017 16

11/17/2017

9

Lot Sizing Rules

11/17/2017 17

Master Production Schedule

• Drives MRP process with a schedule of finished products

• Quantities represent production not demand

• Quantities may consist of a combination of customer orders & demand forecasts

• Quantities represent what needs to be produced, not what can be produced

11/17/2017 18

11/17/2017

10

MRP Processing

• Takes the end item requirements specified by the master schedule and “explode” them into time-phased requirements for assemblies, parts, and raw materials using the bill of materials offset by the lead times

11/17/2017 19

Fields of MRP • Gross Requirements

– Total expected demand for an item or raw material in a time period

• Scheduled Receipts – Open orders scheduled to arrive from vendors or

elsewhere in the pipeline

• Project on-hand – Expected amount of inventory that will be on hand at the

beginning of each time period

11/17/2017 20

11/17/2017

11

Fields of MRP

• Net requirements – The actual amount needed in each time period

– Net requirements = gross requirements – Projected on hand + Safety stock

• Planned order releases – Planned amount to order in each time period

• Planned order receipts offset by lead time

11/17/2017 21

Fields of MRP

11/17/2017 22

11/17/2017

12

MRP Core logic

11/17/2017 23

Capacity Requirements planning

11/17/2017 24

11/17/2017

13

Comparison between MRP and CRP

11/17/2017 25

MPS – MRP – CRP

11/17/2017 26

11/17/2017

14

Manufacturing Requirements Planning (MRP II)

• Extension of MRP

• Plans all resources needed for running a business

• Variations include

– Service Requirements Planning (SRP)

– Business Requirements Planning (BRP)

– Distribution Requirements Planning (DRP)

11/17/2017 27

MRP II Modules • Forecasting • Customer order entry • Production planning / Master Production Scheduling • Product structure / Bill-of-Material processor • Inventory control • Material Requirements Planning • Capacity planning • Shop floor control • Purchasing • Accounting • Financial analysis

11/17/2017 28

11/17/2017

15

Enterprise Resource Planning (ERP)

11/17/2017 29

Typical modules of an ERP software • Sales and distribution • Production planning • Accounts payable/receivable, treasury • Operational (shop floor) control • Purchasing • Finance and cost control • Human resources

11/17/2017 30

11/17/2017

16

THANK YOU

11/17/2017 31